Posted On: 27 NOV 2024 3:30PM by PIB Delhi

The MDoNER has sanctioned 90 projects costing Rs 3417.68crore under North East Special Infrastructure Development Scheme (NESIDS) during the last 03 financial years from 2021-22 to 2023-24 and the current financial year 2024-25. The state-wise and scheme wise details are at Annexure-I.

The projects sanctioned under NESIDS are executed by the State Governments of North Eastern Region (NER) and the primary responsibility of monitoring of these projects lies with the concerned State Governments. The MDoNER also closely monitors the progress of the ongoing projects under NESIDS is at different levels.

The officials of Ministry of DoNER and NEC carry out inspection of the select projects on a regular basis. The Field Technical Support Units (FTSU) have been set upby the Ministry in all the 08 NE States, who regularly interact with project Implementing Agencies and maintain and update the database of projects on Gati Shakti Portal of MDoNER, and also carry out inspections of the ongoing projects.

In order to further strengthen the monitoring mechanism of the ongoing projects under the various schemes of MDoNER inter-alia including NESIDS, the SOP for engagement of the Project Quality Monitors/Third Party Technical Inspection (PQM/TPTI) Units has been issued in February 2024.The projects costing up to Rs 20 crore are being inspected by the PQMs and for bigger infrastructure projects, with project size more than Rs 20 crore, the government engineering colleges in NER have been empanelled as Third Party Technical Inspection (TPTI) agencies for monitoring of these projects..

The NESIDS scheme of Ministry of DoNER has two components: NESIDS(Roads) and NESIDS Other Than Roads Infrastructure (OTRI). Under NESIDS (Roads), projects leading to the creation of physical assets in roads/bridges and auxiliary infrastructure only are considered for sanction. Under NESIDS (OTRI), projects leading to the creation of infrastructure for Primary and Secondary Health care, Primary and Secondary Education, water supply, solid waste management, Industrial development, Civil aviation, sports, telecom etc, with project size between Rs 5 crore to Rs 50 crore, are considered for sanction.

All the North Eastern States are eligible for sanction of projects to the extent of their normative allocations as applicable under NESIDS.

This information was given by the Union Minister of State for Development of North Eastern Region Dr. Sukanta Majunmdar in a written reply to a question in Lok Sabha today.

****

SB/DP/ARJ

Annexure-I

(Rs. in crore)

Sl. No

State

NESIDS (Other Than Roads Infrastructure)

NESIDS (Roads) projects

Total under NESIDS

No.

Amount

No.

Amount

No.

Amount

1

Arunachal Pradesh

7

297.26

8

306.65

15

603.91

2

Assam

12

543.74

11

848.69

23

1392.43

3

Manipur

9

253.46

4

96.13

13

349.59

4

Meghalaya

2

101.42

2

102.87

4

204.29

5

Mizoram

13

172.13

1

33.19

14

205.32

6

Nagaland

3

63.37

4

130.35

7

193.72

7

Sikkim

3

29.93

2

127.83

5

157.76

8

Tripura

6

142.38

3

168.28

9

310.66

 

Total:

55

1603.69

35

1813.99

90

3417.68

 

********