Ministry of Jal Shakti

Polavaram Project

Posted On: 05 AUG 2021 5:19PM by PIB Delhi

Polavaram Irrigation Project (PIP) is being implemented by the Government of Andhra Pradesh (GoAP). As per information made available by the GoAP, component-wise details of works completed in respect of PIP are as under:

 

Sl no.

Components

Progress achieved upto June, 2021, in %age

1.

Head Works

 

(a) Earth Work

87.33

 

(b) Embankment

33.63

 

(c) Concrete

79.75

 

(d) Gates

72.12

2.

Left Main Canal

 

(a) Earth Work

91.69

 

(b) Lining

71.60

 

(c) Structures

62.78

3.

Right Main Canal

 

(a) Earth Work

100

 

(b) Lining

92.73

 

(c) Structures

94.84

4.

Land Acquisition (LA)

67.26

 

 

                 GoAP has informed that out of total 1,06,006 Project Displaced Families (PDFs) to be rehabilitated, 4,283 PDFs have been rehabilitated so far.

Government of India has been reimbursing the expenditure on Irrigation component, including the cost of land acquisition and rehabilitation & resettlement (R&R), of the PIP with effect from 01.04.2014, upon receipt of bills from GoAP and their verification from the PolavaramProject Authority (PPA) and Central Water Commission (CWC), with the approval of Ministry of Finance (MoF) from time to time. 

Government of India has, till date, reimbursed Rs.11,181.36crore including expenditure towards land acquisition and R&R. Further, sanction for reimbursement of Rs. 418.83 crore has been issued on 09.07.2021 by this Ministry.

      

Presently, bills totaling Rs.19.29 crore for land acquisition, and Rs.236.75 crore for R&R, have been submitted by GoAP to PPA. Reimbursement of the bills depends upon their verification from PPA and CWC, and subsequent approval of Ministry of Finance.

 

This information was given by the Union Minister for Jal Shakti,  ShriGajendra Singh Shekhawat in a written  reply in LokSabha  today.

*****