INTELLIGENT TRANSPORT SYSTEMS

Posted On: 05 DEC 2024 5:57PM by PIB Delhi

Intelligent  Transport  System  (ITS)  can  be implemented as Advanced Traffic Management System (ATMS) or it can be part of broader (Vehicle to Everything) V2X communication. The objective is to reduce accidents, traffic violations and incident response time by implementation of ATMS. Government plans to implement the ATMS solution in Highways and Expressways in phased manner. The standalone ATMS projects are as under:

Corridor Name

Length (km)

State(s)

Status

Bangalore    –    Mysore (Augmentation)

117

Karnataka

Completed in July, 2024

Dwarka Expressway

58

Delhi, Haryana

Awarded

Delhi-Agra

180

Uttar Pradesh

Awarded

Lucknow Ring Road

103

Uttar Pradesh

Awarded

UER-II

75

Delhi, Haryana

Under Bidding

Bangalore Ring Road

80

Karnataka

Under Bidding

Chardham Connectivity

825

Uttrakhand

Under Bidding

In addition to above, Government has implemented/implementing ATMS as part of highway projects like Delhi-Mumbai Expressway, Trans-Haryana Expressway, Delhi-Dehradun Expressway, Amritsar- Jamnagar Expressway etc.

In some projects, for e.g. in Bangalore-Mysuru Expressway, the accident data before and after installation of ATMS was reviewed and it was found that there is decrease in fatality post implementation of ATMS in July, 2024. (Accident Data attached as Annexure A).

These two separate systems can be integrated. However it is understood that Smart Cities Mission essentially deals with only urban areas included in the Mission whereas Highways criss-cross the country.

Under the scheme "Central assistance for strengthening the ITS in Public Transport System in the Country" the Government provides financial support for development and implementation of advanced Information and Communication Technology (ICT) and Intelligent Transport System (ITS) in buses being operated by State Road Transport  Undertakings(SRTUs)/ State Transport Undertakings(STUS/State Transport Corporations(STCs).

The Details of approved projects under ITS scheme of MoRTH for the Transport Bodies is attached as Annexure B.

ANNEXURE A

ANNEXURE REFERRED TO IN REPLY TO PART (B) OF LOK SABHA UNSTARRED QUESTION NO. 1706 ON 05TH DECEMBER, 2024 ASKED SHRI K RADHAKRISHNAN REGARDING “INTELLIGENT TRANSPORT SYSTEMS"

Road accident details from 2023 and 2024 on Bangalore to Mysore 6 Lane Access controlled Highways

 

Sl. No.

 

Month

No. of Persons Killed

2023

2024

1

Jan

14

12

2

Feb

17

6

3

Mar

20

9

4

Apr

20

3

5

May

29

3

6

June

27

9

7

July

10

6

8

Aug

10

2

9

Sep

16

0

10

Oct

14

0

11

Nov

6

0

12

Dec

5

0

Total

188

50

 

ANNEXURE B

ANNEXURE REFERRED TO IN REPLY TO PART (D) OF LOK SABHA UNSTARRED QUESTION NO. 1706 ON 05TH DECEMBER, 2024 ASKED SHRI K RADHAKRISHNAN REGARDING “INTELLIGENT TRANSPORT SYSTEMS"

 

 

STU

Proposal Submission

 

 

 

Proposal scope from central share

 

Date

Total Project Cost Sanctioned (in Crs.)

Central Share Sanctioned (in Crs.)

Apprisal-cum- sanction

Committee meeting

Gujarat GSRTC

3/24/2023

39.73

27.81

3/29/2023

Hardware components only CAPEX:

  1. ETIM 12000 (8300+ buses)
  2. Passenger Information Display System
  3. POS smart card with reader
  4. Automatic vehicle location system

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Telangana TSRTC

8/16/2022

29.96

20.97

27.02.2023

  1. Updation of Bus pass/ Online passenger reservation system (Desktop, UPS, Internet connection)
  2. Automatic fare collection system (AFCS)

for fleet of 9607 buses.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Karnataka KSRTC

7/26/2022

30.75

21.53

27.02.2023

  1. Vehicle Location Tracking platform

(Devices, panic button , central command and control centre) (8800 fleet)

  1. Mobile application & Web Portal
  2. Cloud hosting Data Centre (DC) & Data

Recovery Centre (DRC)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Bhopal BCLL

1/31/2023

6.81

4.77

30.06.2023

Focus on software portion:

  1. Centralised Automatic Vehicle Location

 

 

 

 

 

 

 

 

 

 

 

Sikkim SNT

14.07.2023

15.24

10.67

30.06.2023

  1. Command and Control Centre for 390

fleet size.

 

 

 

 

 

 

 

 

 

 

 

Assam State transport

Corporation (ASTC)

29.03.2023

23.39

16.37

1.12.2023

  1. Fleet Strength of 2255+ buses
  2. Passenger information system (PIS)
  3. Automatic Vehicle Location System

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Mira Bhainder Municipal

Corporation transport undertaking (MBMTU)

4/28/2023

11.29

7.90

1.12.2023

  1. On-board Intelligent Transport System (OBITS) for 74 Buses
    1. Driver Display Unit
    2. Passenger Information display in Buses

 

 

 

 

 

 

 

 

 

 

 

Puducherry (PRTC)

14.10.2023

9.05

6.34

1.12.2023

  1. Fleet strength of 140 Buses
  2. Vehicle Scheduling and Dispatch System

 

 

 

 

 

 

 

 

 

 

 

 

 

166.22

116.354

 

 

Andhra APSRTC

12/15/2020

29.71

 

 

UTS project of ITS Scheme 15.03.2010 to 31.03.2020 (Guidelines dated 05.01.2018 )

 

This information was given by the The Union Minister of Road Transport & Highways, Shri Nitin Gadkari in a written reply in Lok Sabha today.

******

DS/AK


(Release ID: 2081193) Visitor Counter : 596