Development Of Waterways In The Country

Posted On: 29 MAR 2022 4:30PM by PIB Delhi

Based on the outcome of techno-economic feasibility and Detailed Project Reports (DPRs) of the NWs completed, action plan has been formulated for 26 NWs which have been found viable for cargo/passenger movement. The list of the 26 NWs with their status (state-wise) is at Annex-1. Development activities have been initiated in the first 13 NWs out of these 26 NWs. Details and status of waterways of Karnataka undertaken for development is at Annex-2.

The details of targets set and expected expenditure involved for completion of waterways projects are at Annex-3.

Under National Perspective Plan (NPP) prepared in year 1980 for inter-basin water transfer, National Water Development Agency (NWDA), Ministry of Jal Shakti has identified 30 links (16 under Peninsular Component and 14 under Himalayan Component) for preparation of Feasibility Reports (FRs) under Inter-linking of Rivers Project. Detailed Project Reports (DPRs) of 8 link projects, FRs of 24 links and Pre Feasibility Reports (PFRs) of all the 30 links have been completed.

Ken-Betwa link is the first link under NPP that is ready for implementation. A tripartite agreement has been signed amongst states of MP and UP and Central Govt, for the implementation of Ken-Betwa Link project in March, 2021 in the august presence of Hon’ble Prime Minister of India. Govt. of India has approved the implementation of Ken-Betwa Link Project with an estimated cost of Rs. 44605 Cr at year 2020-21 price level and central support of Rs. 39317 Cr.  [90: 10 (Central: State) ] through a Special Purpose Vehicle viz; Ken Betwa Link Project Authority. A Gazette notification for the same has been issued by Ministry of Jal Shakti on 11.2.2022. The implementation of the link has been initiated. The funding pattern as approved by Govt. of India for Ken-Betwa Link project is applicable to Ken-Betwa Link project only.

 The funding pattern and sanction of funds for any ILR project is decided on case to case basis at the time / stage of their implementation.

Annex-1

 

LIST OF 26 NATIONAL WATERWAYS FOUND FEASIBLE FOR CARGO / PASSENGER MOVEMENT

 

Sl. No

National Waterway

Details of Waterways

STATES

Status

1

National Waterway 1

Ganga-Bhagirathi-Hooghly River System (Haldia - Allahabad)

Uttar Pradesh, Bihar, Jharkhand & West Bengal

Development taken up with Assistance from World Bank Jal Marg Vikas Project

2

National Waterway 2

Brahmaputra River (Dhubri - Sadiya)

Assam

Development taken up as per approved SFC for FY 2020-21 to 2024-25

3

National Waterway 16

Barak River

Assam

4

National Waterway 3

West Coast Canal (Kottapuram - Kollam), Champakara and Udyogmandal Canals

Kerala

Mostly Operational Waterways and development and maintenance work taken up.

 

 

5

National Waterway 4

Krishna River (Vijayawada – Muktyala)

Andhra Pradesh

6

National Waterway 5

Dhamra-Paradio via Mangalagadi to Pankopal

Odisha

7

National Waterway 8

Alappuzha- Changanassery Canal

Kerala

8

National Waterway 9

Alappuzha - Kottayam – Athirampuzha Canal

Kerala (Alternate route: 11.5km)

9

National Waterway 27

Cumberjua River

Goa

10

National Waterway 68

Mandovi River

Goa

11

National Waterway 86

Rupnarayan River

West Bengal

12

National Waterway 97

Sunderbans Waterway

West Bengal

13

National Waterway 111

Zuari River

Goa

14

National Waterway 10

Amba River

Maharashtra

Development proposal at appraisal stage.

15

National Waterway 40

Ghagra River

Bihar

16

National Waterway 44

Ichamati River

West Bengal

17

National Waterway 52

Kali River

Karnataka

18

National Waterway 57

Kopili River

Assam

19

National Waterway 25

Chapora River

Goa

20

National Waterway 37

Gandak River

Bihar

21

National Waterway 28

Dabhol Creek Vasisti River

Maharashtra

22

National Waterway 73

Narmada River

Maharashtra & Gujarat

23

National Waterway 85

Revadanda Creek - Kundalika River System

Maharashtra

24

National Waterway 94

Sone River

Bihar

25

National Waterway 100

Tapi River

Maharashtra & Gujarat

26

National Waterway 31

Dhansiri River

Assam

 

Annex-2

Details and status of waterways of Karnataka undertaken for development:

 

Sl.No.

PROJECT

Cost (in Rs. Cr.)

1.

Integrated Development of Tadadi-Aghanshini Waterway in Kumta Taluka of Uttar Kannada District

20

2.

Development of waterways on Gurupur (NW-43) in Mangalore Taluka of Karnataka

29.62

3.

Development of waterways from Hangarkatte to Manipal in Udupi Taluka of Karnataka

25

4.

Development of waterways from Almatti to Bagalkot in Karnataka

12.2

5.

Development of waterways on Kali river (NW-52 ) in Karwar Taluka of Karnataka (Phase-1)

14.46

 

            Out of above, in-principal approval for funding under Sagarmala Scheme has been conveyed by the Ministry for projects at Sl. No. 1, 2 & 4 above. W.r.t Sl. No. 5, an amount of Rs. 2.70 Cr.  has been released by IWAI to Govt. of Karnataka in 2021.

 

Annex.-3

The details of targets set and expected expenditure involved for completion of waterways projects:

 

Project

Cost (in Cr.)

Completion

National Waterway-1 (NW-1)

 

 
  • JMVP

Rs. 3887.81

Dec, 2023

  • JMVP-II (ArthGanga )

Rs. 746.00

Dec, 2023

     

National Waterway-2 (NW-2)

Rs. 461.00

Mar, 202 5

National Waterway-16 (NW-16)

Rs. 145.00

Mar, 2025

 

This information was given by the Union Minister for Ports, Shipping and Waterways, Shri Sarbananda Sonowal in a written reply to the Rajya Sabha.

******