Ministry of Petroleum & Natural Gas
Monthly Production Report for December 2021
Posted On:
19 JAN 2022 1:02PM by PIB Delhi
- Production of Crude Oil
Crude oil production during December 2021 was 2509.98 TMT, which is 5.19% lower than target for the month and 1.81% lower than the production of December 2020. Cumulative crude oil production during April-December, 2021 was 22378.40 TMT, which is 4.47% and 2.63% lower than target for the period and production during corresponding period of last year respectively. Unit-wise and State-wise crude oil production is given at Annexure-I. Unit-wise crude oil production for the month of December 2021 and cumulatively for April-December 2021 vis-à-vis same period of last year has been shown in Table-1 and month-wise in Figure-1.
Table-1: Crude Oil Production (in TMT)
Oil Company
|
Target
|
December (Month)
|
April-December (Cumulative)
|
2021-22 (Apr-Mar)*
|
2021-22
|
2020-21
|
% over last year
|
2021-22
|
2020-21
|
% over last year
|
Target*
|
Prod.*
|
Prod.
|
Target*
|
Prod.*
|
Prod.
|
ONGC
|
20272.88
|
1733.83
|
1652.90
|
1700.54
|
97.20
|
15262.19
|
14596.31
|
15209.09
|
95.97
|
OIL
|
3182.60
|
278.70
|
254.36
|
241.35
|
105.39
|
2352.31
|
2243.85
|
2226.69
|
100.77
|
PSC Fields
|
7718.52
|
634.87
|
602.72
|
614.27
|
98.12
|
5811.27
|
5538.24
|
5547.64
|
99.83
|
Total
|
31173.99
|
2647.40
|
2509.98
|
2556.16
|
98.19
|
23425.76
|
22378.40
|
22983.42
|
97.37
|
- Note: Totals may not tally due to rounding off. *: Provisional
Figure-1: Monthly Crude Oil Production
Unit-wise production details with reasons for shortfall are as under:
- Crude oil production by ONGC (Oil and Natural Gas Corporation) in nomination block during December 2021 was 1652.90 TMT, which is 4.67% lower than target of the month and 2.8% lower when compared with production of December 2020. Cumulative crude oil production by ONGC during April-December, 2021 was 14596.31 TMT, which is 4.36% and 4.03% lower than target for the period and production during corresponding period of last year respectively. Reasons for shortfall in production are as under:
- Less than anticipated production from WO-16 cluster due to delay in mobilization of MOPU Sagar Samrat.
- Less than anticipated production from Cluster-8 fields due to delay in inputs as installation of wellhead platforms got delayed due to Covid impact.
- Loss in oil production in Ratna & R-Series due to due to scaling in wells and delay in H2S package at R-13A wells.
- Less condensate receipt at Hazira due to less gas production from B&S Asset and due to constraints in 36” SBHT line.
- Crude oil production by OIL (Oil India Ltd) in the nomination block during December 2021 was 254.36 TMT, which is 5.39% higher when compared with production of December 2020 but 8.73% lower than target of the month. Cumulative crude oil production by OIL during April-December 2021 was 2243.85 TMT, which is 0.77% higher than the production during corresponding period of last year but 4.61% lower than target for the period. Reasons for shortfall in production are as under:
- Less than planned contribution from workover wells and drilling wells.
- Less than planned due to local disturbance & miscreants activities in main producing area (MPA).
- Crude oil production by Pvt/JVs companies in the PSC/RSC regime during December 2021 was 602.72 TMT, which is 5.06% lower than the target of the reporting month and 1.88% lower than the month production of December 2020. Cumulative crude oil production by Pvt/JVs companies during April-December 2021 was 5538.24 TMT, which is 4.7% and 0.17% lower than target for the period and production during corresponding period of last year respectively. Reasons for shortfall in production are as under:
- MB/OSDSF/B80/2016 (Hindustan Oil Exploration Company Ltd.): Delay in commencement of production.
- RAVVA (Cairn Energy India Ltd): Production shortfall is due to less water injection in RC-4ST and RC-11z which has caused lower production from producer wells.
- CB-OS/2 ((Cairn Energy India Ltd): Production shortfall is due to Natural decline, increase in water cut observed in aquifer supported pools and Recent sanding/loading issues in the wells.
- CB-ONN-2004/2 (ONGC): Three development wells in VD-3 discovery and one development well in VD-5 discovery could not be drilled as planned in Q1, Q2 & Q3. The production rate of new development well Vadatal#21 is not as expected.
- Production of Natural Gas
Natural gas production during December 2021 was 2896.69 MMSCM, which is 19.45% higher than the production of December 2020 but 14.93% lower than the monthly target. Cumulative natural gas production during April-December 2021 was 25673.90 MMSCM, which is 21.51% higher than production during corresponding period of last year but 8.75% lower when compared with target for the period. Unit-wise and state-wise natural gas production is given at Annexure-II. Unit-wise natural gas production for the month of December 2021 and cumulatively for April-December 2021 vis-à-vis same period of last year has been shown in Table-2 and month-wise in Figure-2.
Table-2: Natural Gas Production (in MMSCM)
Oil Company
|
Target
|
December (Month)
|
April-December (Cumulative)
|
2021-22 (Apr-Mar)*
|
2021-22
|
2020-21
|
% over last year
|
2021-22
|
2020-21
|
% over last year
|
Target*
|
Prod.*
|
Prod.
|
Target*
|
Prod.*
|
Prod.
|
ONGC
|
23335.10
|
2008.98
|
1757.10
|
1857.73
|
94.58
|
17488.56
|
15541.83
|
16544.32
|
93.94
|
OIL
|
2949.65
|
251.22
|
240.37
|
201.63
|
119.21
|
2222.91
|
2189.77
|
1869.83
|
117.11
|
PSC Fields
|
11834.60
|
1144.96
|
899.22
|
365.57
|
245.98
|
8425.47
|
7942.31
|
2714.81
|
292.55
|
Total
|
38119.35
|
3405.16
|
2896.69
|
2424.93
|
119.45
|
28136.95
|
25673.90
|
21128.96
|
121.51
|
Note: Totals may not tally due to rounding off. *: Provisional
Figure-2: Monthly Natural Gas Production
- Natural gas production by ONGC in the nomination blocks during December 2021 was 1757.10 MMSCM, which is 12.54% lower than target for the month and 5.42% lower than the production of December 2020. Cumulative natural gas production by ONGC during April-December, 2021 was 15541.83 MMSCM, which is 11.13% and 6.06% lower than target for the period and production during corresponding period of last year respectively. Reasons for shortfall in production are as under:
- Less than anticipated production from WO-16 cluster due to delay in mobilization of MOPU Sagar Samrat.
- Less than planned production from Vasistha /S1 wells in EOA due to certain reservoir related issues.
- Delay in commencement of gas production from U1 field of KG-98/2 Cluster-II due to covid impact as manufacturing of subsea items and well completion got delayed.
- Less production due to decline in Tapti-Daman block.
- Less production in Mandapeta field due to delay in inputs and decline in production from Pasarlapudi & Endamuru fields in Rajahmundry.
- Natural gas production by OIL in the nomination block during December 2021 was 240.37 MMSCM which is 19.21% higher than target for the month and 4.32% lower than the production of December 2020. Cumulative natural gas production by OIL during April-December 2021 was 2189.77 MMSCM, which is 17.11% higher than production during corresponding period of last year but 1.49% lower than target for the period. Reasons for shortfall in production are as under:
- Less than planned contribution from workover wells and drilling wells.
- Less offtake by the consumers in main producing area (MPA).
- Natural gas production by Pvt/JVs companies in the PSC/RSC/CBM regime during December 2021 was 899.22 MMSCM, which is 145.98% higher than the production of December 2020 but 21.46% lower than the target for the month. Cumulative natural gas production by Pvt/JVs during April-December 2021 was 7942.31 MMSCM, which is 192.55% higher than production during corresponding period of last year but 5.73% lower than target for the period. Reasons for shortfall in production are as under:
- KG-DWN-98/2 (ONGC): Delay in commissioning of Wells U1-A of KG-DWN-98/2 block. Well U1-2 (U1-B) producing less than the estimated profile.
- RJ-ON-90/1 (Cairn Energy India Ltd): Few Gas wells of RDG field are not producing as per expectations.
- RANIGANJ EAST (Essar Oil and Gas Exploration and Production Ltd.): Shortfall because delay in scheduled operations.
- KG-DWN-98/3 (RIL): Workover job ongoing in well No. AR1-DEV1.
- Crude Oil Processed (Crude Throughput)
Crude Oil Processed during December 2021 was 21482.88 TMT, which is 2.18% higher than December 2020 but 0.44% lower than the target for the month. Cumulative crude throughput during April-December 2021 was 177215.39 TMT, which is 10.51% higher than the production of corresponding period of last year but 0.97% lower than target for the period. Refinery-wise details of the crude throughput and capacity utilization during the month of December 2021 vis-à-vis December 2020 are given at Annexure-III and Annexure-IV. Company-wise crude throughput for the month of December 2021 and cumulatively for the period April-December 2021vis-à-vis same period of last year has been shown in Table-3 and month-wise in Figure-3.
Table 3: Crude Oil Processed (Crude Throughput) (in TMT)
Oil Company
|
Target
|
December (Month)
|
April-December (Cumulative)
|
2021-22 (Apr-Mar)*
|
2021-22
|
2020-21
|
% over last year
|
2021-22
|
2020-21
|
% over last year
|
Target*
|
Prod.*
|
Prod.
|
Target*
|
Prod.*
|
Prod.
|
CPSE
|
145812.84
|
12810.22
|
12469.20
|
12141.04
|
102.70
|
107290.52
|
98998.10
|
89728.66
|
110.33
|
IOCL
|
70299.81
|
6219.93
|
5904.51
|
5987.56
|
98.61
|
52480.95
|
49399.71
|
44758.56
|
110.37
|
BPCL
|
30499.94
|
2410.00
|
2663.74
|
2529.29
|
105.32
|
22620.00
|
21665.07
|
17895.11
|
121.07
|
HPCL
|
17199.69
|
1579.58
|
1483.18
|
1284.48
|
115.47
|
11939.77
|
9278.64
|
12025.73
|
77.16
|
CPCL
|
10000.00
|
930.00
|
840.14
|
766.27
|
109.64
|
7300.00
|
6134.82
|
5604.29
|
109.47
|
NRL
|
2750.35
|
240.17
|
136.55
|
259.78
|
52.56
|
2053.08
|
1930.22
|
1990.51
|
96.97
|
MRPL
|
15000.00
|
1425.00
|
1433.92
|
1306.56
|
109.75
|
10850.00
|
10534.36
|
7395.96
|
142.43
|
ONGC
|
63.04
|
5.53
|
7.16
|
7.11
|
100.79
|
46.71
|
55.29
|
58.50
|
94.51
|
JVs
|
18021.00
|
1536.00
|
1774.71
|
1652.06
|
107.42
|
13554.00
|
15214.50
|
12523.88
|
121.48
|
BORL
|
7000.00
|
600.00
|
656.99
|
625.34
|
105.06
|
5250.00
|
5389.97
|
4291.59
|
125.59
|
HMEL
|
11021.00
|
936.00
|
1117.72
|
1026.72
|
108.86
|
8304.00
|
9824.53
|
8232.29
|
119.34
|
Private
|
78008.07
|
7231.30
|
7238.96
|
7231.30
|
100.11
|
58109.00
|
63002.80
|
58109.00
|
108.42
|
RIL
|
60940.96
|
5687.66
|
5528.85
|
5687.66
|
97.21
|
45610.26
|
47825.18
|
45610.26
|
104.86
|
NEL
|
17067.11
|
1543.64
|
1710.11
|
1543.64
|
110.78
|
12498.74
|
15177.62
|
12498.74
|
121.43
|
TOTAL
|
241841.91
|
21577.52
|
21482.88
|
21024.40
|
102.18
|
178953.52
|
177215.39
|
160361.54
|
110.51
|
- Totals may not tally due to rounding off. *: Provisional
Figure 3: Crude Oil Processed (Crude Throughput)
3.1 CPSE Refineries’ crude oil processed during December 2021 was 12469.20 TMT, which is 2.66% higher than target for the month but 2.70% lower than the production of December 2020. Cumulative crude throughput during April-December 2021 was 98998.10 TMT which is 10.33% higher than corresponding period of last year but 7.73% lower than target for the period. Reasons for shortfall in production are as under:
- IOCL-Guwahati and Bongaigaon Refinery: Monthly Crude processed lower due to low crude receipts.
- IOCL-Haldia Refinery: Monthly Crude processed lower due to deferment of Crude Distillation Unit-2 (CDU) shutdown from Nov-Dec'21 to Dec'21-Jan'22 and Extension of CDU-2 shutdown.
- IOCL-Mathura, Panipat and Paradip Refinery: Monthly Crude processed in line of products demand.
- BPCL-Kochi Refinery: Monthly Crude processed lower due to lower diesel evacuation during the first fortnight and higher stock of HSHSD as hydro-treating unit charges were limited due to lower amine strength.
- HPCL, Mumbai Refinery: Crude throughput is less due to shutdown of secondary units.
- HPCL, Visakh Refinery: Crude throughput is less due to delay in crude tanker berthing.
- CPCL-Manali Refinery: Monthly Crude processed lower due to poor Bitumen & Petcoke demand leading to Vacuum Residue containment.
- NRL-Numaligarh Refinery: Monthly Crude processed lower due to H2U/HCU (Hydrocracker Unit) and Diesel Hydrotreating (DHDT) shutdown due to HTER-p tube bundle replacement in H2U unit
3.2 JV refineries’ crude oil processed during December 2021 was 1774.71 TMT, which is 15.54% higher than the target for the month and 7.42% higher than December 2020. Cumulative crude throughput during April-December 2021 was 15214.50 TMT, which is 12.25% and 21.48% higher than target for the period and production during corresponding period of last year respectively.
3.3 Private refineries’ crude oil processed during December 2021 was 7238.96 TMT, which is 0.11% higher than the corresponding month of last year. Cumulative crude throughput during April-December 2021 was 63002.80 TMT, which is 8.42% higher than the corresponding period of last year.
- Production of Petroleum Products
Production of Petroleum Products during December 2021 was 22754.72 TMT, which is 5.93% higher than production of December 2020 and 3.27% higher than target for the month. Cumulative production during April-December, 2021 was 186008.63 TMT, which is 10.02% higher when compared with the production of corresponding period of last year but 0.28% lower than target for the period. Unit-wise production of petroleum products is given at Annexure-V. Company-wise production for the month of December 2021 and cumulatively for April-December, 2021 vis-à-vis same period of last year has been shown in Table-4 and month-wise in Figure-4.
Figure 4: Monthly Refinery Production of Petroleum Products
Table 4: Production of Petroleum Products (TMT)
Oil Company
|
Target
|
December (Month)
|
April-December (Cumulative)
|
2021-22 (Apr-Mar)*
|
2021-22
|
2020-21
|
% over last year
|
2021-22
|
2020-21
|
% over last year
|
Target*
|
Prod.*
|
Prod.
|
Target*
|
Prod.*
|
Prod.
|
CPSE
|
137873.44
|
12100.54
|
11880.30
|
11445.19
|
103.80
|
101428.13
|
93765.34
|
84944.79
|
110.38
|
IOCL
|
66984.33
|
5907.05
|
5686.47
|
5756.96
|
98.78
|
50007.34
|
47403.38
|
42921.76
|
110.44
|
BPCL
|
29279.04
|
2327.29
|
2530.33
|
2399.72
|
105.44
|
21697.48
|
20715.04
|
17151.93
|
120.77
|
HPCL
|
16019.55
|
1467.24
|
1451.21
|
1157.16
|
125.41
|
11110.27
|
8650.98
|
11160.27
|
77.52
|
CPCL
|
9279.11
|
864.85
|
787.75
|
683.29
|
115.29
|
6768.27
|
5594.15
|
5130.58
|
109.04
|
NRL
|
2749.06
|
240.06
|
127.45
|
256.32
|
49.72
|
2052.12
|
1892.20
|
2014.72
|
93.92
|
MRPL
|
13502.33
|
1288.78
|
1290.28
|
1184.93
|
108.89
|
9748.18
|
9456.79
|
6509.45
|
145.28
|
ONGC
|
60.02
|
5.27
|
6.82
|
6.80
|
100.19
|
44.48
|
52.79
|
56.08
|
94.13
|
JVs
|
16361.00
|
1395.00
|
1624.27
|
1515.95
|
107.14
|
12417.00
|
14103.57
|
11623.20
|
121.34
|
BORL
|
6095.00
|
523.00
|
580.11
|
578.73
|
100.24
|
4569.00
|
4794.09
|
3769.93
|
127.17
|
HMEL
|
10266.00
|
872.00
|
1044.16
|
937.22
|
111.41
|
7848.00
|
9309.49
|
7853.27
|
118.54
|
Private
|
93222.97
|
8146.49
|
8918.13
|
8146.49
|
109.47
|
69302.56
|
75042.98
|
69302.56
|
108.28
|
RIL
|
76683.16
|
6610.23
|
7254.40
|
6610.23
|
109.75
|
57172.73
|
60421.67
|
57172.73
|
105.68
|
NEL
|
16539.81
|
1536.26
|
1663.73
|
1536.26
|
108.30
|
12129.83
|
14621.30
|
12129.83
|
120.54
|
Total Refinery
|
247457.41
|
21642.02
|
22422.70
|
21107.63
|
106.23
|
183147.69
|
182911.89
|
165870.55
|
110.27
|
Fractionators
|
4516.39
|
391.71
|
332.02
|
372.66
|
89.09
|
3392.11
|
3096.74
|
3200.42
|
96.76
|
TOTAL
|
251973.80
|
22033.74
|
22754.72
|
21480.30
|
105.93
|
186539.80
|
186008.63
|
169070.97
|
110.02
|
Note: Totals may not tally due to rounding off. *: Provisional
- Production of petroleum Products by Oil’s Refineries during December 2021 was 22422.70 TMT, which is 6.23% higher than production of December 2020 and 3.61% higher when compared with target for the month. Cumulative production during April-December, 2021 was 182911.89 TMT, which is 10.27% higher than the production of corresponding period of last year but 0.13% lower than target for the period.
- Production of petroleum Products by Fractionators during December 2021 was 332.02 TMT, which is 15.24% lower than the target for the month and 10.91% lower than production of December 2020. Cumulative production during April-December, 2021 was 3096.74 TMT, which is 8.71% and 3.24% lower than target for the period and production during corresponding period of last year respectively.
Click here to see Annexure-I
Click here to see Annexure-II
Click here to see Annexure-III
Click here to see Annexure-IV
Click here to see Annexure-V
***********
YB/RKM
(Release ID: 1790899)