Ministry of Railways

Most advanced Electronic Interlocking System installed on the Grand Chord route


This new Electronic system replaces outdated 65-year old mechanical signaling system at Tundla Jn. in Uttar Pradesh on the route

This technological upgradation en-route will pave safer, faster, efficient and more punctual train operations on New Delhi-Howrah route

Around 500 persons worked day and night for around 50 days to execute the most challenging work in minimum possible time and with minimum inconvenience to the public

This interlocking system at Tundla is the second largest in the country after Kharagpur Station in South Eastern Railway

Train handling capacity at Tundla Jn. improved to 250 per day from existing 200 maximum

Faster movement of Medical Relief Train during accident becomes possible

Posted On: 22 OCT 2019 5:23PM by PIB Delhi

Most advanced Electronic Interlocking System has been installed on the Grand Chord route.  The measure is expected to help Indian Railways speed up trains and to achieve its future objective of reducing the travel time between Delhi and Howrah to about 12 hours from the existing 17-19 hours.

Grand Chord is part of the Howrah-Gaya-Delhi line and Howrah-Allahabad-Mumbai line. It acts as a link between Sitarampur, (West Bengal) and Pt. Deen Dayal Upadhyay Junction, Uttar Pradesh, and covers a stretch of 450 kms falling in North Central Railway (NCR) Zone of Indian Railways, which maintains and operates 53% portion of this New Delhi-Howrah route.This achievement become possible by replacement of the 65-year old outdated Mechanical Signaling System with the most advanced and safer Electronic Interlocking System at Tundla station in Uttar Pradesh now.

Around 500 persons worked day and night without break from 2nd September, 2019 to 20th October, 2019 to execute this complex and challenging work in minimum possible time and with minimum inconvenience to public using innovative and out of the box methodologies and meticulous planning.

Tundla Jn. is an important station on this super-saturated route operating 160% of its designed capacity. Tundla also connects mainline with Agra Cantt. Jn. This important Electronic Interlocking work at Tundla Jn. was having 613 route combinations which is only second to Kharagpur in South Eastern Railway with 800 routes.

Despite being extremely important from train operation point of view, Tundla Jn. was still continuing with mechanically interlocked signaling system of 1955 vintage. This system required manual operation of levers for receipt and dispatch of trains from 05 different cabins. Manual operation and coordination among cabins took approximately 05-07 minutes to handle each train at important Jn. station thus limiting its handling capacity to maximum 190-200 train on daily basis. Further Mechanical signaling also required upgrade to match with global safety standards in train operation. Layout of Tundla Jn. also needed important changes to accommodate longer trains and more route combinations for efficient train operations.

Need for this change was felt a long back ago and work for remodeling and removal of Mechanical signaling was sanctioned way back in 1998-99, however actual execution got delayed due to extreme pressure of train operation at Tundla Jn. station as execution required cancellation of sizable number of trains which was not feasible unless an innovative and out of the box solution to this problem was found by NCR in 2019.

Realizing the importance of this work, GM, NCR, Sri Rajiv Chaudhry motivated and guided the team of multi-disciplinary team of plannerswho came out with innovative solution to utilize newly constructed eastern dedicated freight corridor section between Bhadhan- Khurja section for diversion of some goods trains bypassing Tundla Jn. thus minimizing cancellation of passenger trains during execution of this work.

On the historic day of 20th October, 2019, 65 years old Mechanical Signaling system was replaced by the most advanced and safer system of Electronic Interlocking. With commissioning of this system and some post commissioning works expected to be over by 17.11.2019 following major benefits shall be achieved in trains operation:

 

  1. Train handling time to be reduced from existing 05-07 minutes to 30-60 seconds through centralized power cabin enhancing handling capacity of Jn. to 250 per day from existing 200 maximum, thus less detention of trains outside Tundla and improved Punctuality of Trains.
  2. Train operation towards Agra will be immensely benefitted with two additional platforms and extension of three existing platforms no. 3,4&5 to cater full length trains on main line.
  3. All UP-direction yard lines are now fit for passenger train movement thus efficient handling of more coaching train.
  4. Length of Yard lines increased to handle longer freight and passenger trains.
  5. Double exit facility provided to Medical Relief Train (ARME) for immediate movement in both sides during accidents etc.
  6. Centralized fail-safe operation through power cabin by just click of the mouse button replacing cumbersome, inefficient and manual operation spread across 05 cabins. Substantial saving on manpower requirement.

This work will go a long way in improving punctuality of trains on New Delhi- Howrah main lineand benefits shall be manifold during incoming foggy season through safe and detention free handling of trains at Tundla Jn. 

*****

KSP/MKV/AP


(Release ID: 1588737) Visitor Counter : 1352


Read this release in: Urdu , Hindi , Bengali