Ministry of Ports, Shipping and Waterways
Sagarmala Projects
Posted On:
26 JUL 2024 1:29PM by PIB Delhi
Sagarmala is the flagship Central Sector Scheme of the Ministry of Ports, Shipping and Waterways to promote port-led development in the country through harnessing lndia's 7,500 km long coastline, and 14,500 km of potentially navigable waterways. Under the Sagarmala Scheme, the Ministry provides financial assistance to State/UT Governments for Port infrastructure projects, Coastal berth projects, Road & Rail projects, fish harbours, skill development projects, Coastal community development, cruise terminal and projects such as Ro-Pax ferry services etc. The details of number of projects, funds sanctioned and project status state wise in enclosed [ Annexure-I].
The details of the projects undertaken with assistance under Sagarmala Scheme along with status in respect to port modernisation and connectivity is annexed [ Annexure-II]
Based on the request of Government of Karnataka, Ministry under Sagarmala Scheme has sanctioned projects related to Port Modernisation, Coastal Shipping & IWT, and Coastal Community Development,for financial assistance at various location in the State. The details of the projects undertaken in the State of Karnataka is annexed [ Annexure III].
Annexure 1:
State/UT
|
No. of Projects
|
Total Funds Sanctioned
(₹ Cr)
|
Total Project Cost (₹ Cr)
|
Completed (₹ Cr)
|
Under Development (₹ Cr)
|
Under Implementation
(₹ Cr)
|
No. of Projects
|
Total Project Cost
|
No. of Projects
|
Total Project Cost
|
No. of Projects
|
Total Project Cost
|
Andaman & Nicobar Islands
|
3
|
46
|
46
|
1
|
13
|
0
|
0
|
2
|
32
|
Andhra Pradesh
|
13
|
429
|
2,483
|
7
|
1,114
|
1
|
73
|
5
|
1,295
|
Goa
|
9
|
170
|
763
|
5
|
85
|
0
|
0
|
4
|
677
|
Gujarat
|
10
|
969
|
1,422
|
3
|
364
|
1
|
33
|
6
|
1,024
|
Karnataka
|
18
|
214
|
537
|
3
|
71
|
10
|
44
|
5
|
422
|
Kerala
|
8
|
110
|
252
|
5
|
122
|
0
|
0
|
3
|
131
|
Maharashtra
|
30
|
794
|
1,905
|
16
|
790
|
0
|
0
|
14
|
1,115
|
Odisha
|
6
|
159
|
350
|
1
|
4
|
2
|
160
|
3
|
186
|
Puducherry
|
2
|
30
|
30
|
1
|
27
|
0
|
0
|
1
|
2
|
Tamil Nadu
|
22
|
513
|
1,225
|
14
|
1,004
|
2
|
15
|
6
|
206
|
West Bengal
|
9
|
280
|
569
|
6
|
404
|
0
|
0
|
3
|
165
|
Total
|
130
|
3,714
|
9,580
|
62
|
3,999
|
16
|
326
|
52
|
5,255
|
Annexure 2:
Project Pillar
|
Total
|
Completed
|
Under Implementation
|
No of Projects
|
Project Cost
(₹ Cr)
|
No. of projects
|
Project Cost
(₹ Cr)
|
No. of projects
|
Project Cost
(₹ Cr)
|
Port
Connectivity
|
17
|
1,259
|
14
|
655
|
3
|
603
|
Port Modernization
|
16
|
860
|
10
|
521
|
6
|
340
|
GrandTotal
|
33
|
2,119
|
24
|
1,176
|
9
|
943
|
Annexure3:
S.No
|
Name of Project
|
Project Pillar
|
Project Cost (₹ Cr)
|
Status
|
1
|
Creation of berthing facilities and land-side facilities at Sandpit Bengre, Karnataka
|
Coastal Shipping and IWT
|
1.70
|
Under Development
|
2
|
Creation of berthing facilities and land-side facilities at Bandaru ferry, Karnataka
|
Coastal Shipping and IWT
|
1.78
|
Under Development
|
3
|
Creation of berthing facilities and land-side facilities at SulthanBathery, Karnataka
|
Coastal Shipping and IWT
|
5.06
|
Under Development
|
4
|
Creation of berthing and landside facilities at ThannirBhavi Church, Karnataka
|
Coastal Shipping and IWT
|
5.23
|
Under Development
|
5
|
Creation of berthing and landside facilities at BangraKuluru, Karnataka
|
Coastal Shipping and IWT
|
3.41
|
Under Development
|
6
|
Creation of berthing and landside facilities at Kulur Bridge, Karnataka
|
Coastal Shipping and IWT
|
4.58
|
Under Development
|
7
|
Creation of berthing and landside facilities at JappinaMogaru NH bridge, Karnataka
|
Coastal Shipping and IWT
|
5.28
|
Under Development
|
8
|
Construction of coastal cargo berth at Old Mangaluru Port
|
Coastal Shipping and IWT
|
65.00
|
Under Implementation
|
9
|
Third stage expansion including modernisation of the existing fishing harbour of Malpe in Udupi District in Karnataka
|
Coastal Community Development
|
50.00
|
Completed
|
10
|
Modernisation of the existing fishing harbour at Amadalli in Uttara Kannada
|
Coastal Community Development
|
19.00
|
Completed
|
11
|
Coastal Districts Skill Development Program - Phase I -Karnataka
|
Coastal Community Development
|
1.53
|
Completed
|
12
|
Development of Fishing Harbour at Kulai
|
Coastal Community Development
|
197.00
|
Under Implementation
|
13
|
Development of HejmaadiKodi Fishing Harbour in Udupi District
|
Coastal Community Development
|
139.00
|
Under Implementation
|
14
|
Installation of Fire Fighting Equipment at Karwar Port in Karnataka
|
Port Modernization
|
19.00
|
Under Implementation
|
15
|
Development of waterways in Kali River (NW 52) in Karwar Taluka (Phase 1)
|
Coastal Shipping and IWT
|
9.54
|
Under Development
|
16
|
Creation of berthing facilities and land-side facilities at JappinaMogaru Old ferry, Karnataka
|
Coastal Shipping and IWT
|
5.23
|
Under Development
|
17
|
Creation of berthing & landside facilities at Northern Sandbar, Karnataka
|
Coastal Shipping and IWT
|
2.22
|
Under Development
|
18
|
Coastal Districts Skill Development Program - Phase II -Karnataka
|
Coastal Community Development
|
2.18
|
Under Implementation
|
Total
|
537
|
|
This information was given by the Union Minister of Ports, Shipping and Waterways Shri Sarbananda Sonowal in a written reply in Lok Sabha today.
*****