Under the Central Vista Development/ Re-development Master Plan, only 4 projects are being implemented, as on date

Posted On: 02 DEC 2021 4:45PM by PIB Delhi

Under the Central Vista Development/ Re-development Master Plan, only 4 projects viz. construction of New Parliament Building, Redevelopment of Central Vista Avenue, construction of Common Central Secretariat Buildings 1,2&3 and construction of Vice President Residence are being implemented, as on date. The details are as follows:

 

Name of the Project

Estimated cost

(₹Cr)

Amount incurred so far (₹Cr)

Estimated to be completed by

Physical progress

New Parliament Building

971

340.58

October 2022

35%

Redevelopment of Central Vista Avenue

608

190.76

December 2021

60%

Common Central Secretariat Buildings-1,2&3

3,690

7.85

November 2023

Mobilization of resources and site preparation is in progress

Vice President Residence

208.48

15

November 2022

Mobilization of resources and site preparation is in progress

 

₹1,289 cr has been allocated for the works of Development/Re-development of Central Vista in the ongoing FY 2021-22.

 

Quality-cum-cost based method of bidding has not been adopted for construction of the New Parliament Building or for other buildings in the Central Vista. Quality- cum-cost based method for bidding has been adopted only for engagement of consultant for comprehensive architecture and engineering planning for development/ redevelopment of Central Vista.

 

The ongoing works at the Central Vista have provided direct livelihood opportunities to more than 10,000 skilled, semi-skilled and unskilled workers on site and off site and generated more than 24.12 lakh man days of employment. In addition, substantial employment in manufacturing and transportation of cement, steel and other building materials have been provided. These works of Development/ Re-development of Central Vista will

 contribute to the economy of the country and will help realize our resolve for Aatmanirbhar Bharat. There is no link between the works of Central Vista Development/Re-development with the MPLADS scheme. Separately, the Union Cabinet, in its meeting held on November 10, 2021, has restored MPLAD Scheme (MPLADS) for the remaining part of the Financial Year (FY) 2021-22 and itscontinuationfrom FY 2022-23 to FY 2025-26 with an outlay of ₹17,417 cr.

This information was given by the Minister of State in the Ministry of Housing and Urban Affairs, Shri Kaushal Kishore, in a written reply in the Lok Sabha today.

 

*****