Department of Atomic Energy
PARLIAMENT QUESTION: GENERATION OF NUCLEAR ENERGY
प्रविष्टि तिथि:
05 AUG 2026 3:34PM by PIB Delhi
The Government has announced an ambitious Nuclear Energy Mission for Viksit Bharat with a target of reaching a nuclear power capacity of 100 GW by 2047. Nuclear Power Projects are having a Project/ Construction period of 10-12 years. No specific Nuclear Power Projects have been sanctioned after the Middle East conflict.
The details of Nuclear Power Projects under various stages of implementation and those planned are tabulated in Annexure.
There have been apprehensions in a section of the people at few sites, about safety of the site & plant, issues related to Rehabilitation, and fears of loss of traditional means of livelihood like fishing and horticulture. The apprehensions have been addressed through public awareness programmes adopting a multipronged approach in a credible manner. Highest priority is accorded to safety in all aspects of nuclear power viz. siting, design, construction, commissioning, and operation. Further, safety is not static and improvements/ upgrades are effected in nuclear power plants based on evolving global standards, events and operating experience feedback.
This information was given by Union Minister of State for Prime Minister’s office and Personnel, Public Grievances and Pensions, Atomic Energy and Space, Dr. Jitendra Singh, in a written reply in the Lok Sabha today.
*****
NKR/AK/NM
Annexure
|
Nuclear Power Projects under Construction/ Commissioning
|
|
|
Location & State
|
Project
|
Capacity
(MW)
|
Expected Completion Date/
Status
|
Indigeneous/
Foreign Technology
|
|
Rawatbhata, Rajasthan
|
RAPP-8
|
1 X 700
|
Unit-8 is in advanced stage of commissioning (expected to
be operational in 2026).
|
Indigeneous
|
|
Gorakhpur, Haryana
|
GHAVP
1&2
|
2 X 700
|
Completion of construction and commissioning is expected to be completed in about 6 years from First Pour of Concrete.
|
Indigeneous
|
|
Kudankulam, Tamilnadu
|
KKNPP-3&4
|
2 X 1000
|
June-2027/ June-2028
|
Foreign Technology
|
|
KKNPP-5&6
|
2 X 1000
|
June-2029/ March-2030
|
Foreign
Technology
|
|
Kalpakkam,
Tamilnadu
|
PFBR
|
1 X 500
|
Attained criticality on 06.04.2026
|
Indigeneous
|
|
Kaiga, Karnataka
|
KAIGA-5&6
|
2 X 700
|
June-2031/ June-2032
|
Indigeneous
|
|
Projects Under Pre-project Activities
|
|
|
Gorakhpur,
Haryana
|
GHAVP–
3&4
|
2 X 700
|
Projects Under Pre-project activities are expected to be completed progressively by
2031/ 32.
|
Indigeneous
|
|
Chutka, Madhya
Pradesh
|
Chutka-1&2
|
2 X 700
|
Indigeneous
|
|
Mahi Banswara, Rajasthan
|
Mahi
Banswara-1&2
|
2 X 700
|
Indigeneous
|
|
Mahi
Banswara 3&4
|
2 X 700
|
Indigeneous
|
|
Kalpakkam,
Tamilnadu
|
FBR 1& 2
|
2 X 500
|
Indigeneous
|
|
Planned Nuclear Power Projects/ Sites
|
|
|
Rawatbhata,
Rajasthan
|
RAPP-9&10
|
2 X 700
|
Proposed Nuclear Power Projects
|
Indigeneous
|
|
Kakrapar, Gujarat
|
KAPP-5&6
|
2 X 700
|
Indigeneous
|
|
Narora, Uttar
Pradesh
|
NAPP-3&4
|
2 X 700
|
Indigeneous
|
|
Jaitapur,
Maharashtra
|
JNPP-1 to 6
|
6 X 1730
|
In-Principle approved sites
|
Foreign
Technology
|
|
Kovvada,
Andhra Pradesh
|
Kovvada-
1 to 6
|
6 X 1208
|
Foreign
Technology
|
|
Haripur,
West Bengal
|
Haripur-
1 to 6
|
6 X 1000
|
Foreign
Technology
|
|
Mithi Virdi, Gujarat
|
Mithi Virdi-
1 to 6
|
6 X 1000
|
Foreign
Technology
|
|
Bhimpur,
Madhya Pradesh
|
Bhimpur-
1 to 4
|
4 X 700
|
Indigeneous
|
*****