PARLIAMENT QUESTION: NUCLEAR POWER GENERATION CAPACITY

प्रविष्टि तिथि: 29 JUL 2026 4:05PM by PIB Delhi

The present installed nuclear power capacity in the country is 8,780 MW comprising of

24 nuclear power plants, contributing about 3.1% in 2025-26 in total electricity generation. The details are tabulated in Annexure.

  1. The details of nuclear power projects under construction and their present status are tabulated below.

Location

Project

Capacity (MW)

Physical Progress/ Status

(as of June 2026)

Expected Date Of Commissioning

Projects Under Construction / Commissioning

 

 

Rajasthan

 

RAPP-8

 

1 X 700

 

96.26 %

In advanced stage of commissioning (expected to be operational in 2026)

Kudankulam, Tamilnadu

KKNPP-3&4

2 X 1000

82.65 %

June-2027/ June-2028

KKNPP- 5&6

2 X 1000

45.00 %

June-2029/ March-2030

 

 

 

 

 

Gorakhpur, Haryana

 

 

 

 

 

GHAVP-1&2

 

 

 

 

 

2 X 700

 

Completion of construction and commissioning is expected to be completed in about 6 years from First Pour of Concrete.

FPC will start after completion of ground improvement works of Nuclear Island.

Kaiga, Karnataka

KAIGA-5&6

2 X 700

 

June-2031/ June-2032

The Government has drawn up a roadmap for reaching the 100 GW nuclear power capacity by 2047, as announced in the Nuclear Energy Mission. As per the roadmap, the present nuclear power capacity of 8.78 GW is expected to reach about 22 GW by 2031-32. Another 32 GW of nuclear power capacity is envisaged to be set up under NPCIL beyond 2032 which will comprise of indigenous Pressurised Heavy Water Reactors (PHWRs) and Light Water Reactors (LWRs). Additionally, the Government has approved the pre-project activities of 2 x 500 MW FBR 1 & 2, to be built with the same design as of PFBR of Kalpakkam. The balance of 45 GW comprising of reactors of different technologies, is expected to be set up by other Public Sector Enterprises (Central & State), Private sector and Joint Ventures in different business models.

Highest priority is accorded to safety in all aspects of nuclear power viz. siting, design, construction, commissioning, and operation. Nuclear power plants are designed adopting safety principles of redundancy, diversity and provided fail-safe design features following an overlapping defence-in-depth approach, in line with codes and guides of Atomic Energy Regulatory Board (AERB). There is a robust regulatory mechanism of safety reviews at multiple levels. The safety of nuclear power plants is continuously monitored and reviewed by the AERB. Required fuel security is ensured by Nuclear Fuel Complex, a constituent unit of Department of Atomic Energy, Government of India.

The Government has announced a Nuclear Energy Mission to reach a capacity of 100 GW nuclear power capacity by 2047 and formulated a roadmap for the same. The Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India (SHANTI) Act 2025 enables wider participation in the nuclear power sector, both from public and private sector.

This information was given by Union Minister of State for Prime Minister’s office and Personnel, Public Grievances and Pensions, Atomic Energy and Space, Dr. Jitendra Singh, in a written reply in the Lok Sabha today.

*****

NKR/AK/NM

Annexure

 

Maharashtra

 

Tarapur

TAPS-1

160

TAPS-2

160

TAPS-3

540

TAPS-4

540

 

 

Rajasthan

 

 

Rawatbhata

RAPS-2

200

RAPS-3

220

RAPS-4

220

RAPS-5

220

RAPS-6

220

RAPS-7

700

 

Tamilnadu

Kalpakkam

MAPS-1

220

MAPS-2

220

Kudankulam

KKNPP-1

1000

KKNPP-2

1000

Uttar Pradesh

Narora

NAPS-1

220

NAPS-2

220

 

Gujarat

 

Kakrapar

KAPS-1

220

KAPS-2

220

KAPS-3

700

KAPS-4

700

 

Karnataka

 

Kaiga

KGS-1

220

KGS-2

220

KGS-3

220

KGS-4

220

*****