METRO SERVICE BETWEEN KOLKATA AND SUBURBAN AREAS

Posted On: 03 DEC 2025 5:55PM by PIB Kolkata

Kolkata, December 3, 2025

 

Metro project in Kolkata started in 1972. The details of the Metro commissioned since then are as under:

Period Metro Commissioned

1972 to 2014 (42 years) 28 km

2014 to 2025 (11 years) 45 km

Presently, four metro corridors totaling 52 km are under construction in and around Kolkata out of which 20 km is held up due to land acquisition and utility shifting issues pertaining to the State Government. This was stated by Minister for Railways, Information & Broadcasting and Electronics & Information Technology, Shri Ashwini Vaishnaw today in Lok Sabha in a written reply to a question raised by MP Shri Kalyan Banerjee.

Shri Vaishnaw added that, the Joka – Esplanade (14 km):- Joka - Majerhat (7.74 km) has been commissioned and balance work from Majerhat to Esplanade (6.26 km) has been taken up. However, progress of the work is affected due to the following issues:

SN    Location Issues

1.     Khidderpore Metro Station

For utility shifting and road traffic diversion, 837 sqm permanent and 1,702 sqm temporary land of the State Government (Kolkata Armed Police) is required. The proposal of this land was sent to the State Government on August 24, 2020. Several meetings were held with officials of Government of West Bengal (GoWB) for transfer of above land. After much persuasion, the State Government finally accorded approval in July 2025 only after almost five years.

SN      Location Issues

2.      Dr. B.C. Roy Market

For construction of Esplanade Metro Station, temporary shifting of unauthorised 528 shops at the B.C. Roy Market on Defence land is required. The proposal for NOC of temporary/permanent shifting of these shops was submitted to the State Government in February 2022. Shops for temporary shifting of these unauthorized shops have also been constructed by the Railway. The State Government has been requested to facilitate shifting. Regular follow up with State PWD is also being done. Issue is pending for more than 3.5 years.

(ii) New Garia - Dum Dum Airport (32 km): New Garia – Belaghata (9.8 km) has been commissioned and balance work from Belaghata to Dum Dum Airport (22.2 km) has been taken up. However, progress of the work is affected due to the following issues:

SN           Location Issues

1.              Chingrighata Crossing (Between Beleghata –Gour Kishore Ghosh stations)

Temporary traffic diversion at Chingrighata crossing for launching of viaduct segments is required for 3 nights each on either side of the road (8 hours on every night).

The proposal was submitted to the Government of West Bengal (GoWB) in December 2024. The diversion road as desired by Kolkata traffic police has already been constructed in February 2025. Since then, several meetings have been held with various State Government and Kolkata police officials for NOC. The NOC is still awaited even after about 10 months.

The Railway Minister said, Noapara – Barasat (18 km): Noapara - Jai Hind Airport (6.77 km) has been commissioned and work from Jai Hind Airport to Michael Nagar is in progress. However, work from New Barrackpore to Barasat (7.5 km) is held up due to land acquisition and encroachment issues by State authorities.

SN        Location Issues

1.          New Barrackpore to Barasat

Land acquisition (23,000 sq. m) and removal of heavy encroachments (1,277 hutments, 764 shops) are involved in this section. The matter is not yet resolved by GoWB.

So far as Baranagar – Barrackpore - Dakshineshwar (14.5 km): Baranagar – Dakshineshwar (2 km) is concerned, the job has been commissioned and balance work from Baranagar to Barrackpore (12.5 km) is held up due to pending utility shifting in the alignment by State Government authorities, Shri Vaishnaw stated. The details are as below:

SN      Location Issues

1.        Baranagar to Barrackpore

The original alignment along the B.T road was agreed in 2011 as per MoU among Metro Railway, RVNL and Kolkata Municipal Corporation. As per the MoU, the existing pipeline was to be replaced by a new 64-inch diameter pipeline by the State Government. Shifting of this pipeline was completed in 2012. However, NOC is still awaited from the Government of West Bengal.

According to the Minister, Sheoraphuli is already connected with Howrah. Sheoraphuli is an existing station of Indian Railway Network on Howrah – Bandel Junction mainline having 5 tracks. Tarakeswar - Bishnupur (83 km) new line project is held up due to law-and-order issues in Goghat - Kamarpukur section falling in Hooghly district. The work was stopped by local villagers in about 900m length near Bhabadighi Pond. The work has been held up since 2016.

West Bengal

Budget allocation in recent years has increased significantly. Budget allocation for infrastructure projects and safety works, falling fully/partly in the State of West Bengal is as under: -

Period Outlay

2009-14 ₹4,380 Cr./year

2025-26 ₹13,955 Cr. (More than 3 times)

As on April 1, 2025, 42 projects (12 New Lines, 04 Gauge Conversions and 26 Doubling), of total length of 4,402 km, costing ₹67,991 crore falling fully/partly in the State of West Bengal have been sanctioned, out of which, 1,702 km length has been commissioned and an expenditure of ₹23,410 crore has been incurred till March, 2025.

Details of some of the recently completed projects falling fully/partly in the State of West Bengal are as under:

SN                                                                                                               Project Cost

                                                                                                                         (₹ in Cr.)

1 Rampurhat-Mandarhill new line & Rampurhat-

Murarai 3rd line (159 km)

                                                                                                                           1,500

2 Azimganj - Murshidabad new line (7 km)                                                      164

3 Bardhaman - Katwa Gauge Conversion (52 km)                                            696

4 Ahmedpur - Katwa Gauge Conversion (52 km)                                             440

5 Panskura - Kharagpur Doubling (45 km)                                                       408

6 Lalgola - Jiaganj Doubling (23 km)                                                                124

7 Krishnanagar - Bethuadahari Doubling (28 km)                                             152

8 Nabadwip Dham - Patuli Doubling (22 km)                                                   170

9 Bethuadahari - Plassey Doubling (23 km)                                                       132

10 Ambikakalna - Nabadwip Dham Doubling (23 km)                                      145

11 Nalhati - Sagardighi Doubling (26 km)                                                          193

12 Tamluk Jn. – Basulya Sutahata Doubling (24 km)                                         245

13 Plassey - Jiaganj Doubling (54 km)                                                               234

14 Azimganj - Manigram Doubling (21 km)                                                      150

15 New Coochbehar - Gumanihat Doubling (29 km)                                         330

16 New Coochbehar- Samuktala Road Doubling (29 km)                                 445

17 Sainthia - Tarapith 3rd line (22 km)                                                               186

18 Ambari Falakata - New Maynaguri Doubling (37 km)                                  843

19 Bandel - Boinchi 3rd line (31 km)                                                                 546

20 Boinchi - Shaktigarh 3rd line (26 km)                                                           424

21 Bazar Sau - Azimganj Jn. Doubling (42 km)                                                 343

22 Sagardighi - Malda Town Doubling (25 km)                                                 248

23 Kharagpur - Narayangarh 3rd line (24 km)                                                 270

24 Monigram - Nimtita Doubling (24 km)                                                       713

25 Purulia - Kotshila Doubling (36 km)                                                           393

Shri Vaishnaw pointed out that during the last three years (i.e. 2022-23, 2023-24, 2024-25) and current Financial Year i.e. 2025-26, total 97 Nos. of Surveys (10 New Lines, 87 Doubling) falling fully/partly in the State of West Bengal having a total length of 4,004 km have been sanctioned, stated the Railway Minister. He added, Execution of important infrastructure projects falling fully/partly in the State of West Bengal is held up due to delay in land acquisition.

Deshapran - Nandigram (18.5 km) Line was sanctioned in 2009-10 at a cost of ₹121.44 crores. The entire Project length is located in East Midnapore District. The project could not progress due to problems in land acquisition and was kept in abeyance. In April 2023 it was decided to re-start the work. However, Survey for land acquisition from Deshapran to 5.0 km could not be completed due to law-and-order issues. As Deshapran is the connecting station, acquisition of this land is essential for commissioning of this project. Sanction of any railway project depends upon many parameters/factors which include the following:

·      Anticipated traffic projections and remunerativeness of the

proposed route

 First and last mile connectivity provided by the project

 Connection of missing links and providing additional route

 Augmentation of congested/saturated lines

 Demands raised by State Governments/Central Ministries/Public representatives

 Railway’s own operational requirements

 Socio-economic considerations

 Overall availability of funds

Completion of Railway project/s depends on various factors

which include the following:

 Land acquisition by State Government

 Forest clearance

 Shifting of infringing utilities

 Statutory clearances from various authorities

 Geological and topographical conditions of area

 Law and order situation in the area of project site

 Number of working months in a year for a particular project site etc.

 

*******

SSS/3.12.25…….