Units-3&4 of Kakrapar Atomic Power Station (KAPS-3&4), the first pair of indigenous 700 MW Pressurized Heavy Water Reactors (PHWR) setup at Kakrapar in Gujarat are already operational, having commenced commercial operation on 30.06.2023 and 31.03.2024 respectively.
Two units of 700 MW indigenous PHWRs were sanctioned to be setup at Rawatbhata in Rajasthan (RAPP-7&8, 2X700 MW)
One of the units, RAPP-7 has been connected to the grid on 17.03.2025, while RAPP- 8 is under advanced stage of commissioning and is expected to be completed in 2025-26.
This information was given by Dr. Jitendra Singh, Union Minister of State (Independent Charge) for Science and Technology, Earth Sciences, MoS PMO, Department of Personnel, Public Grievances and Pensions, Department of Space and Department of Atomic Energy, in a written reply in the Rajya Sabha today.
***