Ministry of Tourism
azadi ka amrit mahotsav

Spiritual Tourism

Posted On: 27 MAR 2025 4:21PM by PIB Delhi

The Ministry of Tourism through its ongoing schemes of Swadesh Darshan and ‘Pilgrimage Rejuvenation and Spiritual, Heritage Augmentation Drive (PRASHAD)’ complements the efforts of the State Governments (SGs)/UT Administrations (UTs) by extending financial assistance to SGs/UTs for tourism infrastructure development. The details of the current status of the projects under Spiritual Circuits of Swadesh Darshan Scheme and PRASHAD Scheme is given in the Annexure.

Development and completion of projects under PRASHAD scheme depend on various factors like successful tendering process, capacity of state implementing agency, timely project planning and designing, submission of requisite documents etc. The projects sanctioned under the above schemes are implemented by respective State Government/UT Administrations. However, in order to monitor and expedite progress of the projects and to guide the State Governments/UT Administrations, the Ministry of Tourism holds regular review meetings at different levels.

The Ministry of Tourism consults various stakeholders, including the temple trusts, State Governments/UT Administrations, local bodies, and concerned Union Ministries and other stakeholders while approving of the projects under the PRASHAD Scheme. In order to prevent delays in projects, the State Governments/UT Administrations are required to provide undertakings ensuring encumbrance-free land availability and other necessary clearances, etc.      

This information was given by Union Minister for Tourism and Culture Shri Gajendra Singh Shekhawat in a written reply in Rajya Sabha today.

***

ANNEXURE

 

Details of Projects sanctioned in Spiritual Circuit under Swadesh Darshan Scheme:

Sl.

No.

Name of State

Project Name

Amount Sanctioned

(₹ Crore)

Amount Released

(₹ Crore)

Amount Utilised (₹Crore)

Project Status/

Remarks

1.

Kerala

Development of Sabarimala - Erumeli-Pampa-Sannidhanam as a Spiritual Circuit in      District Pathanamthitta, Kerala (2016-17)

46.54

33.39

36.27

Project Reported Complete

2.

Manipur

Development of Shri Govindajee Temple, Shri Bijoy Govindajee Temple – Shri Gopinath Temple – Shri Bungshibodon Temple – Shri Kaina Temple (2016-17)

45.34

45.33

43.04

Project Reported Complete

3.

Kerala

 

Development of Sree Padmanabha Temple, Aranmula- Sabrimala

(2016-17)

78.08

 

73.77

 

68.98

Project Reported Complete

4.

Bihar

 

Development of Kanwaria Route: Sultanganj – Dharmshala- Deoghar (2016-17)

44.76

 

42.52

 

42.17

Project Reported Complete

5.

Uttar Pradesh

Development of Ahar-Aligarh-Kasganj-Sarosi (Unnao)-Pratapgarh- Kausambi-Mirzapur-Gorakhpur-Domariyaganj-Basti-Barabanki-Azamgarh-Kairana- Baghpat- Shahjahanpur (2016-17)

71.91

69.63

69.63

Project Reported Complete

6.

Uttar Pradesh

Development of Bijnor- Meerut- Kanpur- Kanpur Dehat- Banda- Ghazipur- Salempur- Ghosi- Balia- Ambedkar Nagar- Aligarh- Fatehpur- Deoria- Mahoba- Sonbhadra- Chandauli- Mishrikh- Bhadohi (2016-17)

67.51

64.14

63.62

Project Reported Complete

7.

Rajasthan

Development of Spiritual Circuit– 'Development of Churu (Salasar Balaji)-Jaipur (Shri Samodke Balaji, Ghatke Balaji, Bandheke Balaji)- Viratnagar (Bijak, Jainnasiya, Ambika Temple)- Bharatpur (Kaman Region)- Dholpur (Muchkund) - Mehndipur Balaji- Chittorgarh (Sanwaliyaji) (2016-17)

87.05

75.03

75.03

Project Reported Complete

8.

Puducherry

Development of Karaikal, Yanam and Puducherry (2017-18)

34.96

31.40

31.40

Project Reported Complete

9.

Bihar

Development of Mandar Hill & Ang Pradesh (2017-18)

44.55

42.32

42.32

Project Reported Complete

10.

Maharashtra

Development of Waki- Adasa- Dhapewada- Paradsingha- Chota Taj Bagh- Telankhandi- Girad (2018-19)

45.47

43.19

 

38.24

Project Reported Complete

11.

Uttar Pradesh

Development of Jewar-Dadri-Sikandrabad-Noida-Khurja-Banda (2018-19)

12.03

11.43

11.69

Project Reported Complete

12.

Uttar Pradesh

Development of Gorakhnath Temple (Gorakhpur), Devipattan Temple (Balrampur) and Vatvashni Temple (Domariyaganj) (2018-19)

18.30

18.12

18.12

Project Reported Complete

13.

Kerala

Development Sivagiri Sree Narayana Guru Ashram- Arruvipuram- KunnumparaSreeSubrahmania- ChembazhanthiSree Narayana Gurukulam (2018-19)

66.42

42.01

32.91

Project under progress

Project is delayed due Covid, NoC & Clearances from Local Authority.

TOTAL

662.92

592.28

573.42

 

 

 

List of projects sanctioned under PRASHAD Scheme (as on 10.03.2025)

(Rs. in Crore)

State/UT

S.

No.

Project Name

Sanction Year

Approved

Cost

Amount

Released

Physical
Progress

%

Financial Progress %

Andhra Pradesh

  1.  

Development of Pilgrim Amenities at Amaravati

2015-16

27.77

27.77

100%

100%

  1.  

Development of Srisailam Temple

2017-18

43.08

43.08

100%

100%

  1.  

Development of Pilgrimage Amenities at Sri Varaha Lakshmi Narsimha Swami Vari Devasthanam at Simhachalam

2022-23

54.04

13.69

59%

25%

  1.  

Development of Pilgrimage Tourism Infrastructure in Annavaram Temple Town

2024-25

25.33

-

0%

0%

Arunachal Pradesh

  1.  

Development of Parshuram Kund

2020-21

37.88

31.02

92%

82%

Assam

  1.  

Development of Pilgrimage amenities at Kamakhya Temple

2015-16

29.80

29.80

100%

100%

Bihar

  1.  

Development at Patna Sahib

2015-16

29.62

29.62

100%

100%

  1.  

Development of basic facilities at Vishnupad temple

2014-15

3.63

3.63

100%

100%

Chhattisgarh

  1.  

Development of Pilgrimage amenities at Maa Bamleshwari Devi Temple

2020-21

48.44

40.19

90%

83%

Goa

  1.  

Development of Bom Jesus Basilica

2024-25

16.46

-

0%

0%

Gujarat

  1.  

Development of Dwarka

2016-17

10.46

10.46

100%

100%

  1.  

Development of Pilgrimage Amenities at Somnath

2016-17

45.36

45.36

100%

100%

  1.  

Development of Promenade at Somnath

2018-19

47.12

47.12

100%

100%

  1.  

Development of Pilgrimage Facilities at Ambaji Temple

2022-23

50.00

10.54

35%

21%

Haryana

  1.  

Development of Mata Mansa Devi Temple and Nada Saheb Gurudwara

2019-20

48.53

34.68

74%

71%

Jammu and Kashmir

  1.  

Development at Hazratbal Shrine

2016-17

40.46

34.30

100%

85%

Jharkhand

  1.  

Development of Baba Baidya Nath Dham

2018-19

36.79

34.95

100%

89%

Karnataka

  1.  

Development of Pilgrimage Amenities at Sri Chamundeshwari Devi Temple

2023-24

45.71

0.00

0%

0%

Kerala

  1.  

Development at Guruvayur Temple

2016-17

45.19

45.19

100%

100%

Madhya Pradesh

  1.  

Development of Amarkantak

2020-21

49.99

34.73

89%

69%

  1.  

Development of Omkareshwar

2017-18

43.93

43.93

100%

100%

Maharashtra

  1.  

Development of Trimbakeshwar

2017-18

45.41

29.93

93%

66%

Meghalaya

  1.  

Development of Pilgrimage Facilitation at Nongswalia Church, Nartiang Shakti Peeth, Aitnar Pool and Charantala Kali Temple

2020-21

29.29

27.78

100%

95%

Mizoram

  1.  

Development of Infrastructure for Pilgrimage and Heritage Tourism at Chite Vang, Zuangtai, Reiek and Aizawl

2022-23

44.89

13.18

29%

29%

Nagaland

  1.  

Development of Pilgrimage Infrastructure at Molungkimong, Noksen Church, Aizuto, Wokha and Kohima

2018-19

25.20

23.56

100%

93%

  1.  

Development of Pilgrimage Tourism Infrastructure at Zunheboto

2022-23

18.18

15.45

72%

85%

Odisha

  1.  

Infrastructure Development at Puri

2014-15

50.00

10.00

-

20%

Punjab

  1.  

Development of Karuna Sagar Valmiki Sthal at Amritsar

2015-16

6.40

6.40

100%

100%

  1.  

Development of Chamkaur Sahib

2021-22

31.57

17.49

79%

55%

Rajasthan

  1.  

Integrated Development of Pushkar/Ajmer

2015-16

32.64

26.11

100%

80%

  1.  

Development at Shri Karni Mata Temple, Bikaner

2024-25

22.58

-

0%

0%

Sikkim

  1.  

Development of Pilgrimage Facilitation at Four Patron Saints, Yuksom

2020-21

33.32

28.31

87%

85%

Tamil Nadu

  1.  

Development of Kanchipuram

2016-17

13.99

13.99

100%

100%

  1.  

Development of Velankanni

2016-17

4.86

4.86

100%

100%

Telangana

  1.  

Development of Jogulamba Devi Temple

2020-21

38.90

33.07

72%

85%

  1.  

Development of Pilgrimage and Heritage Tourism Infrastructure at Rudreshwara (Ramappa) Temple

2022-23

62.00

32.73

37%

53%

  1.  

Development of Pilgrimage Infrastructure at Bhadrachalam

2022-23

41.38

8.43

29%

20%

Tripura

  1.  

Development of Tripura Sundari Temple

2020-21

34.43

28.01

79%

81%

Uttar Pradesh

  1.  

Development of Varanasi –Phase –I

2015-16

18.73

18.73

100%

100%

  1.  

Development of Mathura-Vrindavan as Mega Tourist Circuit (Ph-II)

2014-15

10.98

10.98

100%

100%

  1.  

Development of River Cruise Tourism at Varanasi

2017-18

9.02

9.02

100%

100%

  1.  

Construction of Tourist Facilitation Centre at Vrindavan

2014-15

9.36

9.36

100%

100%

  1.  

Development of Varanasi – Phase II

2017-18

44.60

31.77

100%

71%

  1.  

Development of Infrastructure facilities at Govardhan

2018-19

37.59

30.97

100%

78%

Uttarakhand

  1.  

Integrated Development of Kedarnath

2015-16

34.77

34.77

100%

100%

  1.  

Development of Infrastructure for Pilgrimage Facilitation in Badrinath Ji Dham

2018-19

56.15

38.38

85%

68%

  1.  

Augmentation of Pilgrimage Infrastructure Facilities at Gangotri and Yamunotri Dham

2021-22

54.36

10.22

100%

18%

West Bengal

  1.  

Development of Belur Math

2016-17

30.03

23.39

100%

78%

 

*******

Sunil Kumar Tiwari

tourism4pib[at]gmail[dot]com


(Release ID: 2115759) Visitor Counter : 504