Kavach Protection System tender awarded in various states

Posted On: 02 AUG 2023 5:00PM by PIB Delhi

Regarding installation and safety features of Kavach, the details are:

                          

  1. Kavach is indigenously developed Automatic Train Protection (ATP) system.  Kavach is a highly technology intensive system, which requires safety certification of highest order.
  2. Kavach aids the loco pilot in train running within specified speed limits by automatic application of brakes in case Loco Pilot fails to do so and also help the train safely run during inclement weather.
  3. The first field trials on the passenger trains were started in February 2016. Based on the experience so gained and Independent Safety Assessment of the system by a 3rd party (Independent Safety Assessor: ISA) three firms were approved in 2018-19, for supply of Kavach.
  4. Subsequently Kavach was adopted as a National ATP system in July 2020.
  5. Kavach has so far been deployed on 1465 Route km (Rkm) and 121 locomotives (including Electric Multiple Unit rakes) on South Central Railway in Telangana (684 Rkm), Andhra Pradesh (66 Rkm), Karnataka (117 Rkm) & Maharashtra (598 Rkm) States.
  6. Kavach tenders have been awarded for Delhi – Mumbai & Delhi – Howrah corridors (approximately 3000 Route km) and work is in progress on these routes in West Bengal (229Rkm), Jharkhand (193Rkm), Bihar (227Rkm), Uttar Pradesh (943Rkm), Delhi (30Rkm), Haryana (81Rkm), Rajasthan (425Rkm), Madhya Pradesh (216Rkm), Gujarat (526Rkm), Maharashtra (84Rkm) States.
  7. Indian Railways is preparing Detailed Project Report (DPR) and detailed estimate for another 6000 RKm.
  8. Presently there are three Indian OEMs who are approved for Kavach. Efforts are being made to develop more vendors to enhance the capacity and scale up the implementation of Kavach.
  9. The Cost for provision of Track side including Station equipment of Kavach is approximately 50 Lakhs/Km and cost for provision of Kavach equipment on loco is approximately 70 lakh/ loco.  The amount spent so far on Kavach implementation is ₹ 351.91 Crores.  The budgetary allocation for Kavach during the year 2023-24 in 710.12 Crores.  The projects are sanctioned zone-wise and not State wise as Indian Railway’s projects may span across State boundaries. Therefore, State wise expenditure is not maintained.

This information was given by the Minister of Railways, Communications and Electronic & Information Technology, Shri Ashwini Vaishnaw in a written reply to a question in Lok Sabha today.

****