Ministry of Power

Under PM’s Gati Shakti Master Plan, 27,000 circuit kilometers of transmission lines to be added at an investment of Rs. 75,000 crores by 2024-25: Union Power & NRE Minister Shri R. K. Singh

Posted On: 06 APR 2023 4:26PM by PIB Delhi

Under Prime Minister’s ‘Gati Shakti Master Plan’, the power transmission network is planned to be expanded from 4,25,500 circuit kilometer (existing as on 31.05.2020) to 4,54,200 circuit kilometer (ckm) by 2024-25 resulting in addition of nearly 28,700 ckm. This addition has been proposed in the Inter State Transmission system (ISTS) network at 220kV and above voltage level.

Based on the detailed survey, length of some transmission lines has undergone changes. Some of the transmission system are likely to be completed beyond 2024-25. Also, some new transmission projects have been considered. Hence, against the planned transmission lines addition of 28700 ckm, the transmission network to be added by 2024-25 is about 27,000 ckm. The estimated cost of these projects is around Rs. 75,000 crores. Since, these are Inter-State Transmission projects and not confined to a particular State/UT and State/UT-wise cost is not feasible to be determined.

Summary of Capacity Addition under PM GatiShakti National Master Plan is at Annexure.

India has a robust National Grid which facilitates seamless power transfer from the resource rich areas to major load centres of the country with reliability & security. Power can be transferred from surplus regions/States to deficit regions/States. The capacity of National Grid is being expanded on a continuous basis to commensurate with the growth in electricity generation and electricity demand. As on 28-02-2023, Indian Transmission network includes 4,68,977 ckm of transmission lines (220kV and above voltage level) and 11,58,875 MVA of the transformation capacity in substations (220kV and above voltage level). The inter-regional capacity of the National Grid is 1,12,250 MW.

The country has adequate transmission capacity. Power cuts are sometimes reported due to constraints in the State line transmission network and distribution networks or financial constraints with some Distribution Companies.

The proposed Transmission projects under PM Gati Shakti National Master Plan is expected to further facilitate evacuation of power from generation projects with improved reliability of Power System Network in the country.

 

ANNEXURE

Sl. No.

Name of the project

 

States

Tentative planned initially (ckm)

Likely capacity addition by 2024-25 (ckm)

Commissioning schedule

1

Inter-regional Links

Chhattisgarh, Tamil Nadu, MP, UP, Maharashtra, Telangana

4000

4603

  • Commissioned: 3939 ckm
  • Under Construction: 664 ckm

Anticipated completion by Apr’23

2

Transmission system for integration of 66.5 GW potential Renewable Energy Zones (REZ)

  • Rajasthan (20 GW)
  • Gujarat (16 GW)
  • MP (5 GW)
  • Maharashtra (7 GW)
  • Karnataka (7.5 GW)
  • Andhra Pradesh (8 GW)
  • Tamil Nadu (3 GW)

13500

12784

  • Commissioned: 3904 ckm
  • Under construction: 8598 ckm
  • Under Tendering: 282 ckm

Anticipated completion progressively from Apr’23 to Dec’24

3

Transmission system for evacuation of 20 GW potential REZ in Rajasthan

Rajasthan

6800

4400

  • Under Tendering: 4400 ckm

Anticipated completion by Dec’24

4

Transmission system for evacuation of 11 GW from potential REZ’s in Gujarat i.e 7 GW from Khavda & 4 GW from Dholera

Gujarat

4400

0

Likely to be completed by 2025-26

 

 

Sub-total

28700

21787

 

5

Other Transmission projects

 

-

5201

 

 

 

Total

28700

26988

 

 

This information was given by the Union Minister of Power Sh. R.K. Singh in the Lok Sabha today.

 

******

AM/DP



(Release ID: 1914281) Visitor Counter : 2186