Ministry of Road Transport & Highways

PM Gati Shakti National Master Plan (NMP) envisages the creation of a system for inter-connected and multimodal transportation networks leading to integrated economic and infrastructure development

Posted On: 21 DEC 2022 2:40PM by PIB Delhi

The PM Gati Shakti National Master Plan (NMP) was launched in October 2021 with a vision to enable a mechanism for coordinated planning and to provide a bird’s eye view of planned development to all the Ministries for holistic and integrated development. PM Gati Shakti NMP envisages the creation of a system for inter-connected and multimodal transportation networks leading to integrated economic and infrastructure development, improved trade competitiveness, promotion of exports and employment generation. It envisages establishing integration and synergy amongst different infrastructure sector projects such as National Highways, Railways, Waterways, Telecom, etc., catering to development requirements/ logistic supports of different sectors and industries (e.g. Steel, Power, Fertilizers, Coal, etc.). The NMP will rely on creation of various data layers including geographical features, land records, etc., to facilitate coordinated and integrated planning, project preparations and implementations, optimization of logistics arrangements and efficient transportation systems.

PM Gati Shakti NMP provides the overall framework for planning, sanctioning and execution of projects. There are no separate funds allocated under PM Gati Shakti NMP. The budget is allocated NH projects-wise, as per project requirements, within the sanctioned project costs. However, the details of projects under Bharatmala & NH(O) in the State of Andhra Pradesh are annexed.   

The Ministry closely monitors various issues that affect project implementation such as land acquisition, encroachment removal, law & order issues, utility shifting, non-availability of soil/aggregate, environment/forest/wildlife clearances, ROB & RUB issues, contractual issues, etc. Regular reviews are held with all stakeholders including State Governments and other Central Ministries/Departments to resolve these issues and ensure timely completion of projects. Progress of projects is monitored through advanced digital platforms such as Bhoomi Rashi, Project            Monitoring     Information    System           (PMIS)            and     Data    Lake.

 

 

 

ANNEXURE   

  

ANNEXURE REGARDING “OBJECTIVES AND VISION OF PM GATI SHAKTI"

  

  1. Ongoing Projects

Sr. No.

Name of Project

Length (km)

Cost

(in Cr.)

Appointed Date

Scheduled /

Likely completion Date

Expenditure released/

incurred as

on 25.11.2022

(in. Crore)

1

Development of six lane Aluru Jakuvva section of NH-130CD (Pkg-I)

31.767

1128.68

31.03.2022

29.03.2024 /

29.03.2024

112.36

2

Development of  six lane Jakuvva - Korlam- section of NH-130CD (Pkg-II)

24.30

767.75

31.03.2022

29.03.2024 /

29.03.2024

113.58

3

Development of  six lane Korlam- Kantakpalle section of NH-130CD (Pkg-III)

24

957.43

19.02.2022

18.02.2024/

18.02.2024

247.97

4

Development of Six lane Kantakapalle –

Sabbavaram Section of NH – 130 CD (Pkg-4)

19.56

923.91

06.10.2022

04.10.2024/

04.10.2024

142.86

5

Development of 4-Lane road connectivity from existing East Break Waters up to Convent Junction

3.448

35.79

01.04.2022

31.12.2022 /

30.06.2023

6.44

6

Six laning of Anandapuram-Pendurthi-Anakapalli Section of NH-16 on HAM

50.780

2909

01.07.2021

31.12.2022

(PCOD Issued) /

31.03.2023

1641.75

7

4-laning of Achampeta Junction on NH-216 to Kakinada Anchorage Port Connecting Vakalapudi light house

13.198

90.20

13.07.2022

12.07.2024 /

12.07.2024

0

8

Four laning of Khammam – Devarapalle (Gurvaygudem Village to Devarapalle Village) section of NH – 365 BG (Pkg-4)

27.43

569.37

26.09.2022

26.09.2024/

26.09.2024

107.89

9

Four laning of Khammam – Devarapalle (Recherla village to Gurvaygudem Village) section of NH – 365 BG (Pkg -5)

29.46

711.94

26.09.2022

26.09.2024/

26.09.2024

133.83

10

Six-laning of existing 4-lane road from Gundugolanu to Kalaparru Section of NH-16 on EPC mode (Pkg-I)

27.40

641.90

27.01.2020

30.07.2021/

31.01.2023

  

552.79

11

Six laning of Vijayawada bypass from Chinna

Avutupalli Gollapudi of NH-16 (Pkg-III)

30

1321.79

18.02.2021

17.02.2023/

17.02.2023

  

460.17

12

Six laning of Vijayawada bypass from Gollapudi to Chinnakakni of NH-16 (Pkg-IV)

17.881

1194.57

07.07.2021

23.01.2024/

04.07.2024

  

281.94

13

Six laning of Chilakaluripet Bypass Section of NH16

16.384

  

907.79

28.06.2021

19.03.2023/

19.03.2023

  

247.95

14

Construction of Six Laning of Dedicated Port Road to Krishnapatnam Port (Package -I) on EPC mode

18.975

348.72

20.12.2018

18.12.2020/

20.12.2024

118.58

15

Development of ELF-1 near Km.1210.000 to Km. 1214.000 on EPC mode

4.60

79.13

06.03.2019

21.08.2020/

28.02.2023

69.70

16

Development of ELF-2 Km.1274+0000 to Km.1277+600 on EPC Mode

3.6

84.07

26.12.2019

31.10.2020/

31.05.2023

  

54.69

Sr. No.

Name of Project

Length (km)

Cost

(in Cr.)

Appointed Date

Scheduled /

Likely completion Date

Expenditure released/

incurred as

on 25.11.2022

(in. Crore)

17

4 or 6 laning of  Tada –Nellore (Permanent restoration of flood damaged section on EPC Mode

3.82

134.76

13.12.2019

05.06.2021/

28.02.2023

  

69.02

18

Construction of Six Lane Grade Separated Structures along with slip roads at Km 210+780

(ITC Junction in Kurnool Town), on NH-44 under EPC

3.17

91.55

04.12.2020

07.06.2022/

31.12.2022

  

99.53

19

6L of Renigunta to Naidupeta section of NH-71

57.046

1889

31.01.2022

  

31.01.2024/

30.01.2024

  

322.59

20

Four laning of Bangalore – Chennai Expressway (Bethamangala to Byreddypalli (phase-II) section of NE-7(Pkg -1)

31.00

2007

10.10.2022

10.10.2024/

10.10.2024

92.05

21

Four laning of Bangalore – Chennai Expressway (Bangarupalem to Gudipala (phase-II) section of NE-7(Pkg -3)

29.00

1060

04.10.2022

04.10.2024/

04.10.2024

167.05

22

Construction of Half Flyover at Vijayawada Airport near Gannavaram on Gundugolanu - Vijayawada

Section of NH-16

  

1.415

29.34

 --

--

--

 

This information was given by Union Minister for Road Transport and Highways, Shri Nitin Gadkari in a written reply in the Rajya Sabha.