  1. Crude Oil

 

Crude oil production[1] during August, 2018 was 2908.12 TMT which is 6.47% lower than target and 3.70% lower when compared with August, 2017. Cumulative crude oil production during April-August, 2018 was 14611.53 TMT which is 3.55% lower than target for the period and 3.27% lower than production during corresponding period of last year. Unit-wise and State-wise crude oil production is given at Annexure-I. Unit-wise crude oil production for the month of August, 2018 and cumulatively for the period April-August, 2018 vis-à-vis same period of last year has been shown in Table-1 and month-wise in Figure-1.

Table-1: Crude Oil Production (in TMT)

Oil Company

Target

August (Month)

April-August (Cumulative)

2018-19 (Apr-Mar)

2018-19

2017-18

% over last year

2018-19

2017-18

% over last year

Target

Prod.*

Prod.

Target

Prod.*

Prod.

ONGC

23040.00

1929.83

1783.38

1898.47

93.94

9364.06

8964.81

9457.73

94.79

OIL

3738.00

311.37

286.34

288.48

99.26

1487.59

1411.41

1417.25

99.59

PSC Fields

10233.60

868.05

838.40

832.98

100.65

4298.00

4235.31

4230.04

100.12

Total

37011.60

3109.25

2908.12

3019.93

96.30

15149.66

14611.53

15105.02

96.73

Note: Totals may not tally due to rounding off.                                       *: Provisional

 

Figure-1: Monthly Crude Oil Production

 

 

Unit-wise production details with reasons for shortfall are as under:

    1. Crude oil production by ONGC during August, 2018 was 1783.38 TMT which is 7.59% lower than the monthly target and 6.06% lower when compared with August, 2017. Cumulative crude oil production by ONGC during April-August, 2018 was 8964.81 TMT which is 4.26% lower than target for the period and lower by 5.21% than production during corresponding period of last year. Reasons for shortfall are as under:

 

      1. Electric Submersible Pumps (ESP) problem in wells of NBP field (Rig deployment post monsoon).
      2. Less than planned production from WO-16 and B-127 fields in the absence of MOPUs Sagar Samrat and Sagar Laxmi.
      3. Sub-sea leakage in some well fluid lines of Mumbai High & Neelam Heera Assets leading to flow restriction (line replacement to commence post monsoon under PRP-V scheme).
      4. Low Gas injection pressure in Geleki, Lakwa & increase in water cut in Geleki, Lakwa, Lakhmani & Rudrasagar fields.

 

    1. Crude oil production by OIL during August, 2018 was 286.34 TMT which is 8.04% lower than monthly target and 0.74% lower when compared with August, 2017. Cumulative crude oil production by OIL during April-August, 2018 was 1411.41 TMT which is 5.12% lower than target for the period and 0.41% lower than production during the corresponding period of last year. Major reason for lower production is less than planned contribution from work over wells and drilling wells.

 

    1. Crude oil production by Pvt/JVs during August, 2018 was 838.40 TMT which is 3.42% lower than the monthly target but 0.65% higher than August, 2017. Cumulative crude oil production by Pvt/JVs during April-August, 2018 was 4235.31 TMT which is 1.46 % lower than target for the period but marginally higher by 0.12% than production during the corresponding period of last year. Reasons for shortfall are as under:

 

  1. Panna-Mukta: Natural decline in the field (SHELL).
  2. Ravva: Natural Decline in the field (CEIL).
  3. RJ-ON-90/1: Mangala production is less due to power fluid pump P-417B under maintenance for seal inspection (CEIL).

 

2. Natural Gas

Natural gas production during August, 2018 was 2789.34 MMSCM which is 8.10% lower than the target for the month but 0.59% higher when compared with August, 2017. Cumulative natural gas production during April-August, 2018 was 13571.68 MMSCM which is 7.77% lower than target for the period and 0.86% lower than the production during corresponding period of last year. Unit-wise and state-wise natural gas production is given at Annexure-II. Unit-wise natural gas production for the month of August, 2018 and cumulatively for the period April-August, 2018 vis-à-vis same period of last year has been shown in Table-2 and month-wise in Figure-2.

 

Table-2: Natural Gas Production (MMSCM)

Oil Company

Target

August (Month)

April-August (Cumulative)

2018-19 (Apr-Mar)

2018-19

2017-18

% over last year

2018-19

2017-18

% over last year

Target

Prod.*

Prod.

Target

Prod.*

Prod.

ONGC

25981.00

2206.36

2061.90

1953.25

105.56

10659.76

10013.07

9737.62

102.83

OIL

3120.00

271.19

236.97

261.47

90.63

1327.45

1137.41

1235.22

92.08

PSC Fields

6498.11

557.66

490.47

558.22

87.86

2728.48

2421.20

2716.82

89.12

Total

35599.11

3035.21

2789.34

2772.93

100.59

14715.69

13571.68

13689.66

99.14

Note:  Totals may not tally due to rounding off.                                      *: Provisional

 

Figure-2: Monthly Natural Gas Production

 

 

    1. Natural gas production by ONGC during August, 2018 was 2061.90 MMSCM which is 6.55% lower than the monthly target and but 5.56% higher when compared with August, 2017. Cumulative natural gas production by ONGC during April-August, 2018 was 10013.07 MMSCM which is 6.07% lower than the cumulative target but 2.83% higher than the production during the corresponding period of the last year. The reasons for shortfall are as under:

 

  1. Restricted off-take ex-Odalarevu in Eastern Offshore Asset.
  2. Less than planned gas production from WO-16 and B-127 fields in the absence of MOPUs Sagar Samrat and Sagar Laxmi.
  3. Pressure / potential decline in gas wells of Gandhar field.
  4. Less off-take by consumers/ grid restrictions in Tripura.

 

    1. Natural gas production by OIL during August, 2018 was 236.97 MMSCM which is 12.62% lower than the monthly target and 9.37% lower than August, 2017. Cumulative natural gas production by OIL during April-August, 2018 was 1137.41 MMSCM which is 14.32% and 7.92% lower than the cumulative target and production respectively during the corresponding period of last year. Major reason for lower production is loss of well head production potential of high producing wells of Deohal area, due to downhole tubing corrosion.

 

    1. Natural gas production by Pvt/JVs during August, 2018 was 490.47 MMSCM which is 12.05% lower than the monthly target and 12.14% lower when compared with August, 2017. Cumulative natural gas production by Pvt/JVs during April-August, 2018 was 2421.20 MMSCM which is 11.26% lower than the cumulative target and 10.88% lower than the production during the corresponding period of last year. Reasons for shortfall are as under:

 

  1. Panna-Mukta: Gas Production Lower due to wells underperformance and water loading post unplanned shutdown (SHELL).
  2. KG-DWN-98/3: Closure of 2 wells in D1D3 and 1 well in MA field.  Well B6 ceased to flow due to low reservoir pressure. (RIL)
  3. Sohagpur West CBM Block: Underperformance of CBM wells (RIL).
  4. Raniganj East CBM Block: Some wells closed for planned maintenance and refrac jobs. Major customer 'Matix' operational shutdown (NEL/ESSAR)

 

  1. Refinery Production (in terms of crude oil processed)

 

Refinery production during August, 2018 was 21437.85 TMT which is 3.11% higher than the target for the month and 4.84% higher when compared with August, 2017. Cumulative production during April-August, 2018 was 107806.48 TMT which is 2.08% higher than the target for the period and 5.79% higher than the production during corresponding period of last year. Unit-wise production is given at Annexure-III. Company-wise production for the month of August, 2018 and cumulatively for the period April-August, 2018 vis-à-vis same period of last year has been shown in Table-3 and month-wise in Figure-3.

 

 

Figure 3: Monthly Refinery Production (Crude Processed)         

 

 

 Table 3: Refinery Production (Crude Processed) (TMT)

Oil Company

Target

August (Month)

April-August (Cumulative)

2018-19 (Apr-Mar)

2018-19

2017-18

% over last year

2018-19

2017-18

% over last year

Target

Prod.*

Prod.

Target

Prod.*

Prod.

CPSE

147759

12103.30

12456.45

11193.78

111.28

61079.74

62492.31

58879.07

106.14

IOCL

71150

5955.98

5998.90

5293.07

113.34

29499.23

29776.70

28191.72

105.62

BPCL

29000

2517.87

2510.66

2128.41

117.96

12365.56

12898.99

10866.36

118.71

HPCL

18000

1554.71

1601.31

1572.10

101.86

7509.46

7720.99

7656.98

100.84

CPCL

10500

727.50

954.19

944.76

101.00

4187.50

4565.65

4507.82

101.28

NRL

2850

242.05

271.49

233.25

116.39

1194.66

1186.04

1176.76

100.79

MRPL

16200

1100.00

1115.38

1017.27

109.64

6300.00

6319.88

6448.29

98.01

ONGC

59

5.18

4.52

4.93

91.68

23.33

24.07

31.14

77.32

JVs

17240

1315.00

1188.27

1507.39

78.83

7231.00

7706.03

4864.70

158.41

BORL

6400

400.00

153.96

620.35

24.82

2690.00

2515.13

3004.83

83.70

HMEL

10840

915.00

1034.31

887.04

116.60

4541.00

5190.90

1859.87

279.10

Private

88896

7372.65

7793.13

7746.64

100.60

37301.23

37608.13

38165.26

98.54

RIL

70470

5967.65

6011.99

5967.65

100.74

29489.23

28796.42

29489.23

97.65

NEL

18426

1405.00

1781.15

1778.99

100.12

7812.00

8811.72

8676.04

101.56

TOTAL

253895

20790.94

21437.85

20447.81

104.84

105611.96

107806.48

101909.03

105.79

 Note: Totals may not tally due to rounding off.                     *: Provisional

               

    1. CPSE Refineries’ production during August, 2018 was 12456.45 TMT which is 2.92% higher than the target for the month and 11.28% higher when compared with August, 2017. Cumulative production by CPSE refineries during April-August, 2018 was 62492.31 TMT which is 2.31% higher than the target for the period and 6.14% higher than the production during corresponding period of last year

 

3.2    Production in JV refineries during August, 2018 was 1188.27 TMT which is 9.64% lower than the target for the month and 21.17% lower when compared with August, 2017. Cumulative production by JVs refineries during April-August, 2018 was 7706.03 TMT which is 6.57% higher than the target for the period and 58.41% higher than the production during corresponding period of last year. Major reason for lower production is BORL Bina refinery planned turnaround commenced on 17.08.18.

3.3    Production in private refineries during August, 2018 was 7793.13 TMT which is 5.70% higher than the target for the month and 0.6% higher when compared with August, 2017. Cumulative production by private refineries during April-August, 2018 was 37608.13 TMT which is 0.82% higher than the target for the period and 1.46% lower than the production during corresponding period of last year.

3.4    Refinery-wise details of the capacity utilization and production of petroleum products during the month of August, 2018 and cumulatively for the period April-August, 2018 vis-à-vis April-August, 2017 are given at Annexures - IV and V respectively.

 

Click here to see Annexure-I

Click here to see Annexure-II

Click here to see Annexure-III

Click here to see Annexure-IV

Click here to see Annexure-V

****

YB/SK

 

 


(Release ID: 1547019) Visitor Counter : 1211


Read this release in: Marathi