Ministry of Jal Shakti
Status of Inter-Linking of Rivers (ILR) Programme
Posted On:
08 FEB 2024 3:40PM by PIB Delhi
Under the National Perspective Plan (NPP), prepared in the year 1980 for inter-basin water transfer, the National Water Development Agency (NWDA) has identified 30 links (16 under Peninsular Component & 14 under Himalayan Component) for preparation of Feasibility Reports. Out of 30 identified link projects, Pre - Feasibility Reports (PFRs) of all the 30 links, Feasibility Reports (FRs) of 24 links and Detailed Project Reports (DPRs) of 11 links have been completed. Details and current status of the proposals for inter-State linking of rivers under the Inter-Linking of Rivers (ILR) Programme is furnished at Annexure.
The Government has been pursuing the inter-linking of rivers (ILR) program in a consultative manner and has accorded top priority to it. A “Special Committee on Interlinking of Rivers” has been constituted in September, 2014 for the implementation of ILR programme. Twenty one meetings of the Special Committee have been held so far. Further, a "Task Force for Interlinking of Rivers" was also constituted in April, 2015 for expediting the works under ILR programme and 18 meetings of the Task Force have been held so far. States have wide representation and active participation in these meetings. The implementation of the ILR projects depends on the party States to reach a consensus.
Ken-Betwa Link Project (KBLP) is the first ILR project, for which implementation has been initiated. Subsequent to the signing of a tripartite Memorandum of Agreement amongst the States of Madhya Pradesh and Uttar Pradesh and Government of India, the project was approved by the Government of India, in December, 2021, for implementation at an estimated cost of Rs. 44,605 crore (at year 2020-21 price level), including a central support of Rs. 39,317 crore. During the financial year 2021-22, the budget allocation made for implementation of KBLP was Rs. 4,642.03 crore, while the expenditure made was Rs. 4,639.46 crore. During the financial year 2022-23, a budget allocation of Rs. 1,400 crore was made for the project, while the expenditure out of the central grants made was Rs.622.43 crore. For financial year 2023-24, out of a budget allocation of Rs. 3,500 crore made for the project, central grants amounting to Rs.1459.97 crore has been made so far.
This information was given by the Minister of State for Jal Shakti, Shri Bishweswar Tudu in a written reply in Lok Sabha today.
****
AS
ANNEXURE
Details and current status of the ILR Projects under the NPP
Peninsular Component
Sl. No
|
Name
|
States benefited
|
Status
|
1
|
- Mahanadi (Manibhadra) - Godavari (Dowlaiswaram) link
|
Andhra Pradesh (AP) & Odisha
|
FR completed
|
- Alternate Mahanadi (Barmul) - Rushikulya – Godavari (Dowlaiswaram) link
|
AP& Odisha
|
FR completed
|
2
|
Godavari (Polavaram) - Krishna (Vijayawada) link
|
AP
|
FR completed
|
3
|
a.)Godavari (Inchampalli) - Krishna (Nagarjunasagar) link
|
Telangana
|
FR completed
|
b.) Alternate Godavari (Inchampalli) - Krishna (Nagarjunasagar) link *
|
Telangana
|
DPR completed
|
4
|
Godavari (Inchampalli/ SSMPP) - Krishna (Pulichintala) link
|
Telangana & AP
|
DPR completed
|
5
|
a.) Krishna (Nagarjunasagar) - Pennar (Somasila ) link
|
AP
|
FR completed
|
b.)Alternate Krishna (Nagarjunasagar) - Pennar (Somasila ) link *
|
AP
|
DPR completed
|
6
|
Krishna (Srisailam) – Pennar link
|
AP
|
Draft DPR completed
|
7
|
Krishna (Almatti) – Pennar link
|
AP & Karnataka
|
Draft DPR completed
|
8
|
a.)Pennar (Somasila) - Cauvery (Grand Anicut) link
|
AP, Tamil Nadu & Puducherry
|
FR completed
|
b.) Alternate Pennar (Somasila) - Cauvery (Grand Anicut) link *
|
AP, Tamil Nadu & Puducherry
|
DPR completed
|
9
|
Cauvery (Kattalai) - Vaigai -Gundar link
|
Tamil Nadu
|
DPR completed
|
10
|
- Parbati –Kalisindh - Chambal link
|
Madhya Pradesh(MP) & Rajasthan
|
FR completed
|
b) Modified Parbati – Kalisindh-Chambal link (duly integrated with ERCP)
|
MP & Rajasthan
|
Draft PFR completed
|
11
|
Damanganga - Pinjal link
(As per DPR )
|
Maharashtra (only water supply to Mumbai)
|
DPR completed
|
12
|
Par-Tapi-Narmada link (As per DPR)
|
Gujarat & Maharashtra
|
DPR completed
|
13
|
Ken-Betwa link
|
Uttar Pradesh (UP) & Madhya Pradesh
|
DPR completed & project is under implementation
|
14
|
Pamba - Achankovil - Vaippar link
|
Tamil Nadu & Kerala
|
FR completed
|
15
|
Bedti - Varda link
|
Karnataka
|
DPR completed
|
16
|
Netravati – Hemavati link**
|
Karnataka
|
PFR completed
|
* Due to pending consensus on Manibhadra and Inchampalli dams, Alternate study to divert unutilized waters of Godavari river was carried out and DPR of Godavari (Inchampalli) – Krishna (Nagarjunasagar) - Pennar (Somasila) – Cauvery (Grand Anicut) link projects was completed. Godavari-Cauvery (Grand Anicut) link project has been prepared comprising of Godavari (Inchampalli ) - Krishna (Nagarjunasagar), Krishna (Nagarjunasagar)- Pennar (Somasila) and Pennar(Somasila)-Cauvery(Grand Anicut) link projects.
** Further studies are not taken up since after implementation of Yettinahole project by Govt. of Karnataka, no surplus water is available in Netravati basin for diversion through this link.
Himalayan Component
Sl. No
|
Name
|
States / Countries benefited
|
Status
|
1.
|
Kosi-Mechi link
|
Bihar & Nepal
|
PFR completed
|
2.
|
Kosi-Ghaghra link
|
Bihar, UP & Nepal
|
FR completed
|
3.
|
Gandak - Ganga link
|
UP & Nepal
|
FR completed
(Indian portion)
|
4.
|
Ghaghra - Yamuna link
|
UP & Nepal
|
FR completed (Indian portion)
|
5.
|
Sarda - Yamuna link
|
UP & Uttarakhand
|
FR completed
|
6.
|
Yamuna-Rajasthan link
|
Haryana & Rajasthan
|
FR completed
|
7.
|
Rajasthan-Sabarmati link
|
Rajasthan & Gujarat
|
FR completed
|
8.
|
Chunar-Sone Barrage link
|
Bihar & UP
|
PFR completed
|
9.
|
Sone Dam - Southern Tributaries of Ganga link
|
Bihar & Jharkhand
|
PFR completed
|
10.
|
Manas-Sankosh-Tista-Ganga (M-S-T-G) link
|
Assam, West Bengal (WB) & Bihar
|
FR completed
|
11.
|
Jogighopa-Tista-Farakka link (Alternative to M-S-T-G)
|
Assam, WB & Bihar
|
PFR completed
(The proposal has been dropped)
|
12.
|
Farakka-Sundarbans link
|
WB
|
FR completed
|
13.
|
Ganga(Farakka) - Damodar-Subarnarekha link
|
WB, Odisha & Jharkhand
|
FR completed
|
14.
|
Subarnarekha-Mahanadi link
|
W.B. & Odisha
|
FR completed
|
****
(Release ID: 2003960)