INDEPENDENCE DAY 2011
Indian road network is the
second highest with 42.36 lakh km of length. It
comprises 70,934 km
National Highways, 1,54,522 km of State Highways, 25,77,396 km of Major
District Roads and other District Roads &
14,33,577 km of rural roads
.
The National Highways serve as
the arterial network of the country. The development of National Highways is
the responsibility of the Government of India. The Government of India has
launched major initiatives to upgrade and strengthen National Highways through
various phases of National Highways Development project (NHDP) Phase-I to
Phase-VII which are briefly as under:
Phase I
NHDP Phase I approved by Cabinet Committee
on Economic Affairs (CCEA) in December 2000 comprises mostly of GQ (5,846 km) and NS-EW
Corridor (981km), port connectivity (356 km) and others (315 km). Under Golden
Quadrilateral only 19 km
remain to be completed.
Phase II
Approved in December 2003 comprises mostly
NS-EW Corridor (6,161 km)
and other National Highways of 486
km length, the total length being 6,647 km. The total length
of Phase II is 6,647 km.
Phase-II is targeted for completion by December 2011. 5733 km (80.2 %) of NS-EW
corridor is completed till June 2011.
Phase III
It consists of upgradation
and 4 laning of 12190 km of National
Highways. Construction of 2351 km under
NHDP-Phase-III is completed till June 2011. The target for NHDP Phase-III for
completion is December 2013.
Phase IV
Under this 20000 km planned to be
constructed as 2 - laning with paved
shoulders. Out of this, the Government has approved in July, 2008 the proposal upgradation/ strengthening of 5,000 km of
single/intermediate/two lane NHs to 2-lane standards with paved shoulders under
NHDP Phase-IVA on BOT (Toll) and BOT (Annuity) basis at an estimated cost of
Rs. 6,950 crore.
So far,
5 projects aggregating to 719
km length has been awarded by NHAI and 1 project of 108 km length has been
awarded by Madhya Pradesh Road Development Corporation (MPRDC). In addition to
the above identified list of 5,000
km under NHDP-IVA, about 15,000 km have been
identified so far by this Ministry on the basis of recommendations received
from various State Governments, NHAI and inter assessment. Phase-IV is targeted for completion by
December 2015 as per the financing plan.
Phase V
It comprises six laning
of 6,500 km
includes 5,700 km
of GQ and other (800 km)
stretches on Design Build Finance and operation (DBFO) basis. Phase-V is
targeted for completion by December 2012. 619 km of six laning is completed under NHDP-Phase-V till June 2011.
Phase VI
The Government has approved construction
of 1000 km
of Expressway under NHDP Phase-VI at a cost of Rs. 16,680 crore
on DBFO basis. NHDP Phase-VI is targeted for completion by December, 2015.
Phase-VII
It includes construction of 700 km of ring
roads/bypasses and flyovers and selected stretches. NHDP Phase-VII is targeted
for completion by December, 2014.
Port Connectivity
The NHDP inter alia includes port
connectivity projects for improvement of roads connecting 12 major Ports in the
country. Programme for connectivity to
Major Ports was approved in December, 2000 for 393 km (connectivity to Kandla for 56
km on NH-8 was on-going. Hence, total length is 449 km).
The Government under its various phased
programmes sanctioned an amount of Rs.1896 crore on
10 major projects in the country for port connectivity. These phased programmes also include one project
for four-lane connectivity to the International Container Transshipment
Terminal (ICTT) at Cochin
at a cost of Rs.557 crore. Similarly, another project on
Build-Operate-Transfer (BOT) basis, at a cost of Rs.1655 crore,
was sanctioned for construction of an elevated road for Chennai Port
to Maduravoyal.
Most of the major ports in the country were likely to be connected by
four lane connectivity projects. Among
these projects, the JNPT Phase-I and II, Paradip Port in Odisha
and Visakhapatnam
project in Andhra Pradesh have been completed.
The projects, at the remaining ports, are at various stages of
completion. Kolkatta
Port connectivity project
was dropped since the proposed alignment was passing through defense land which was not made available. Mumbai port
connectivity project was also dropped since the proposed alignment was passing
through salt pan areas. Therefore, out of 12 major ports 2 (Kolkata and Mumbai)
were dropped, on one (Kandla) the work was already in
progress and now it has been completed. In the remaining projects the work is
either complete or in progress at various stages.
The Government has given top priority to
the development of national highways which will facilitate the overall
development of road infrastructure and transport sector at a faster rate.
New
Initiatives
The Ministry
has taken initiatives to develop 6,700 km of single lane/intermediate lane NHs
to minimum 2 lane standards on corridor concept keeping in view the targets
stipulated in the Eleventh Plan for accelerated efforts to bring NHs network to
a minimum of two-lane standard. The program is targeted to be completed by 2014. A length of 3770 km (33 Stretches) is
proposed to be funded from a World Bank loan of US $ 2.96 billion and the balance
length is proposed to be taken up through budgetary resources. A preparation of
DPR for all the 33 stretches is nearing completion. Stretches having length
more than 25 km
in plain terrain or more than 15
km in hilly/rolling terrain and costing less than Rs 150
crore are being considered for taking up through
budgetary provisions.
Road Development in Extremism Affected
Areas
The Government has approved approved in February 2009 scheme estimated to cost about
Rs. 7,300 crore for development of NHs and State
roads in Extremism affected areas. It
includes 34 districts in eight States namely, Andhra Pradesh, Bihar,
Chhattisgarh, Jharkhand, Madhya Pradesh, Maharashtra,
Orissa and Uttar Pradesh. Under the scheme, development of identified stretches
of NHs (1202 km)
and State roads (4363 km)
to two lane standards are planned to be taken up in a phased manner. An
allocation of Rs. 1,200 crore has been made from GBS
under Annual Plan during 2011-12 for this programme. The total additional fund requirement for
this programme for the Eleventh Five Year Plan is Rs. 5,376 crore. Sanction has been issued so for 186 works
for 4,967 km
costing Rs. 6,629 crore. Out of these, 146 works for 3,889 km length costing
Rs. 4,827 crore have been awarded.
Special
Accelerated Road Development Programme for North-East Region (SARDP-NE): Phase ‘A’ of SARDP-NE approved by the Government envisages
improvement of about 4,099
km length of roads (2,041 km NHs and 2,058 km State
roads). The SARDP-NE Phase-A is expected
to be completed by March, 2015. Phase ‘B’ of SARDP-NE, covering 3,723 km (1,285 km NH and 2,438 km State road), has
been approved for DPR preparation only and so far DPRs for about 450 km has been completed.
So far, about 742 km
length has been completed under SARDP-NE Phase-A till May 2011. It is targeted
to complete 270 km
roads during 2011-12.
The Arunachal Pradesh Package for
Road and Highways involving development of about 2,319 km length of road (1,472 km is NHs & 847 km is State/General
Staff/Strategic roads) has also been approved by the Government. Projects on 776 km are to be taken up on
BOT (Annuity) mode and the balance 1,543 km is to be developed on EPC basis. The entire Arunachal Package is targeted for
completion by June 2016. The status of Projects under this Programme is as
follows:
BOT(Annuity) Projects – 2 Projects
awarded in 58 km
costing Rs. 1,553 crore; tendering for 3rd time
completed for remaining 2 projects for balance 718 km & projects are on
the verge of award.
EPC Projects
–sanctioned 359 km;
under tendering 25 km;
under process for sanction 118
km; DPRs under preparation for balance 900 km; target for award of
all civil works – March, 2012.
Progress of works under Major
Projects
In order to make a visible
impact, the Ministry has targeted to accomplish construction of National
Highways at the pace of 20 km
per day keeping in view the requirement to achieve the quantum jump from the
current pace of construction. At present
works on over 10,500 km
is in progress and to achieve the target of completing 20 km per day, works of about
20,000 km
should be in progress at any point of time.
As on 1/4/2011 works were in progress is about 15,600 km length under
NHDP, Spl. Programme for development of roads in
extremism affected areas and SARDP-NE including Arunachal Pradesh package. It
is being targeted to award works in a total length of about 11,050 km and complete
works in about 3,570 km
under these programmes. With this, it is being targeted to have works in
progress in about 23,079
km length as on 1/4/2012. Thus, it
is being targeted to progressively build up the works in progress. (PIB
Features)
*Inputs from the Ministry of Road Transport
& Highways
PRA/RTS/VN
SS-129/SF-129/11.08.2011