Ministry of Jal Shakti08-March, 2021 16:35 IST
Completion of polavarm Irrigation project

Government of Andhra Pradesh has informed that the earlier completion schedule for Polavaram Irrigation Project (PIP) was December, 2021. However, in the 12th meeting of Polavaram Project Authority (PPA) held in April, 2020, a Committee was constituted to study and come up with a project schedule and completion programme with proper planning duly backed with adequate resource mobilization. Based on the recommendations of the above Committee, the PPA, in its 13th meeting held in November, 2020, revised the tentative date of completion of the project to April, 2022.

The component-wise revised tentative date of completion as proposed earlier, and as per the revised construction schedule, including the schedule for rehabilitation and resettlement measures, is as below:

 

Sl.

No.

Components/Activities

Earlier completion schedule

Revised completion schedule

1

Spillway

April, 2021

May, 2021

2

Erection of Radial Gates

Nov, 2021

April, 2021

3

Coffer Dams

Jan, 2021

June, 2021

4

Earth Cum Rock-Fill Dam- Gap-II

Oct, 2021

April, 2022

5

Left Main Canal

July, 2021

April, 2022

6

Right Main Canal

June, 2021

April, 2022

7

Land Acquisition and Rehabilitation & Resettlement

  1. Upto EL 41.15m :

July, 2020

(ii) Upto EL 45.72m : March, 2022

  1. Upto EL 41.15m :

January, 2021

(ii) Upto EL 45.72m : April, 2022

 

This information was given by the Minister of State for Jal Shakti & Social Justice and Empowerment, Shri. Rattan Lal Kataria in a written reply in Rajya Sabha today.

*****

BY/AS


(Release ID :219910)