Construction
of Bansagar Unit I Dam was started in 1978.The Bansagar Unit I Dam was completed in the year 2006 and the
reservoir was impounded in 2006 monsoon. The Canal system of the project is
being executed by the respective State Govt. in Madhya Pradesh, Uttar Pradesh
and Bihar.
Total
expenditure on Bansagar Unit I Dam up to December, 2011
was Rs. 1534.694 crores. An amount of Rs.
364.984 crore for Bansagar
Unit I Dam (Madhya Pradesh) and Rs 368.428 crore for Bansagar Unit II Canal
(Madhya Pradesh) has been released as Central Assistance under the Accelerated
Irrigation Benefits Programme (AIBP) up to March,
2012.
The following irrigation potential is proposed to be created :-
Annual Irrigation in
Madhya Pradesh : 2.49 lakh
hectare.
Annual
Irrigation in Uttar Pradesh : 1.5
lakh hectare
Annual
Irrigation in Bihar : 0.94
lakh hectare
This information was given by the
Minister of Water Resources & Parliamentary Affairs Shri Pawan
Kumar Bansal in a written reply to a question in Lok Sabha today.
…
MA/KT/VN