20-December-2011 16:50 IST
Developmental Projects in North Eastern Region

 

The Minister of State (Independent Charge) for Development of North Eastern Region (DoNER) Shri Paban Singh Ghatowar has said that the Ministry of Development of North Eastern Region sanctions the developmental projects in North Eastern Region under Non-Lapsable Central Pool of Resources (NLCPR) scheme, Special Bodo Territorial Council (BTC) Package and also through North Eastern Council. 

 

In a written reply in Lok Sabha today, he said that the State-wise details of total projects underway under NLCPR scheme and those delayed by more than three years and less than three years but more than one year are enclosed at Annexure - I. Details of development projects underway at present with central assistance through the North Eastern Council and those delayed by more than three years and less than three years but more than one year are enclosed at Annexure - II.

 

 He said, the projects are implemented by State Governments.  The main reason for their delay, inter-alia, includes limitation of technical &  professional expertise, the restricted working season due to prolonged rainy season in the North Eastern Region and prevailing law and order situation in some areas of North Eastern Region.

 

Annexure - I

 

Status of development projects underway under NLCPR scheme in the North Eastern Region

 

 

 

State

 

No. of Projects ongoing

No. of ongoing Projects where completion is delayed by

More than 1 year but less than 3 years

(Delay by 12 to 35 months)

3 years and more

(Delay by 36 months and above)

Arunachal Pradesh

106

28

16

Assam

173

42

63

Manipur

90

15

25

Meghalaya

63

19

11

Mizoram

49

13

5

Nagaland

70

14

17

Sikkim

43

10

11

Tripura

61

9

7

BTC Package

26

2

13

Total

681

152

168

 

 

Annexure - II

 

Status of development projects underway through the North Eastern Council in the North East Region

 

 

 

State

 

No. of Projects ongoing

No. of ongoing Projects where completion is delayed by

More than 1 year but less than 3 years

(Delay by 12 to 35 months)

3 years and more

(Delay by 36 months and above)

Arunachal Pradesh

64

1

4

Assam

45

7

9

Manipur

28

0

2

Meghalaya

41

7

6

Mizoram

33

1

9

Nagaland

36

1

6

Sikkim

35

3

3

Tripura

17

4

7

Other Agencies

19

0

3

Total

318

24

49

 

***

 

NSK/DB