The overall status of National Highway Development Programme is given below There have been some delays in
implementation of the projects mainly due to poor performance of some contractors, delays in obtaining forest/wild
life/ railway clearances, law & order problems in some states, delay in
land acquisition. In order to expedite implementation of projects Regional
Officers each headed by Chief General Manager have been set up by NHAI for
close monitoring of implementation of projects. Measures have been taken to expedite land
acquisition, shifting of utilities etc. Projects are periodically reviewed at
field and at Head Quarters.
Overall status of NHDP
Status as on 31.10.2011
NHDP
Phases
|
Total Length in km
|
Length Completed in km
|
Length under
Implementation in km
|
To be
awarded in km
|
I
GQ,EW-NS corridors, Port connectivity &
others
|
7,522*
|
7454
|
68
|
-
|
II
4/6-laning
North South- East West Corridor, Others
|
6,647
|
5344
|
859
|
444
|
III
|
12,109
|
2714
|
6063
|
3341
|
IV
2 - laning with paved
shoulders
|
20,000
|
-
|
2073
|
17927
|
V
6-laning of GQ and High density corridor
|
6,500
|
661
|
2532
|
3307
|
VI
Expressways
|
1000
|
NIL
|
NIL
|
1000
|
VII
Ring Roads, Bypasses and flyovers and
other structures
|
700 km of ring roads/ bypass + flyovers
|
-
|
41
|
659
|
This information was given by the Minister of
State of Road Transport and Highways, Dr. Tushar A.
Chaudhary, in a written reply in Rajya Sabha today.
SK/kd
|