NHPC has so far commissioned three Hydroelectric Projects
during 11th Five Year Plan.
The aggregate installed capacity of three projects is 1150 MW as per
details given below:
Sl.
No.
|
Name
of Project
|
State
|
Installed Capacity
(MW)
|
Commissioning
Schedule
|
1.
|
Omkareshwar (in Joint Venture)
|
Madhya
Pradesh
|
520
|
November,
2007
|
2.
|
Teesta-V
|
Sikkim
|
510
|
March,
2008
|
3.
|
Sewa-II
|
Jammu & Kashmir
|
120
|
July,
2010
|
|
Total
|
1150
|
|
Plant Load Factor is used for measuring performance of
Thermal Power Stations, whereas as per present CERC regulation, performance of
Hydro Power Stations is measured in terms of Plant Availability Factor
(PAF). Average PAF of Omkareshwar, Teesta-V and Sewa-II Power Station is 98.2%, 86.3%& 90.5%
respectively.
This
information was given by the Minister of State for Power Shri
K. C. Venugopal in a written reply
to a question in Rajya Sabha
today.
…