National Aluminium Company
Limited (NALCO), a Navratna PSU of Govt. of India,
has crossed another milestone in implementation of its ambitious Rs.4402 crore 2nd phase expansion. The company has
started commissioning various expanded capacities of its Alumina Refinery, at Damanjodi, including cogeneration power plant, evaporation
plant, stacker and bauxite circuit for production of alumina. Other packages in
the plant are now under advance stage of commissioning.
It may be mentioned that
under the 2nd phase expansion NALCO is enhancing its Alumina
Refinery capacity from 1.575 million tonnes to 2.1
million tonnes. Further, the company has ordered
equipments to upgrade the total alumina capacity to 2.275 million tonnes under its 4th stream upgradation
programme.
Earlier, the 4th
potline of NALCO’s Smelter Plant and the 9th
& 10th units of its Captive Power Plant, both located at Angul, were commissioned. The work at Refinery in Damanjodi lagged after the Maoist attack there in April
2009, when several contractors & their workers left the place. Some works
were then off-loaded to other contractors.
The capacities of
various project segments after second phase expansion are as follows:
Project Segment
|
Capacity after 2nd phase
expansion
|
Bauxite Mine
|
63,00,000 tpa
|
Alumina Refinery
|
21,00,000 tpa (to be
upgraded to 22,75,000 tpa)
|
Aluminium
Smelter
|
4,60,000 tpa
|
Captive Power Plant
|
1200 mw
|
KKP/ska