Sl.
No
|
State/ Name of the Project
|
Latest Estimated Cost of the Project
(Rs. in cr.)
|
Central Assistance Released under scheme of National Project
(Rsin Cr.)
|
1)
Irrigation (ha.)
2)
Power (MW)
3) Storage (MAF)
|
Remarks
|
1.
|
Kulsi
Dam Project (Assam)
|
1139.27
(PL
2014)
|
Nil
|
1) 20,500 ha.
2) 55 MW
3) 0.28 MAF
|
Appraisal
stage
|
2
|
Polavaram
Project (Andhra Pradesh)
|
10,151.04
(PL
2005-06)
Revised
cost - 16010.45
(PL
2010-11)
|
Before
N.P.-562.47
After N.P.:-
2014-15
= 250
2015-16 = 600
Total 850
|
1) 4.68Lakh
2) 960 MW
3) 23.44 TMC
of water to Vizag city for drinking and industrial purpose and Diversion of
84.70 TMC to Krishna basin
|
Ongoing
|
3.
|
Noa-Dihing Dam
Project (Arunachal Pradesh)
|
1086.06
(PL
2013)
|
Nil
|
1) 3605 ha.
2) 71 MW
3) 0.26 MAF
|
Appraisal stage
|
4.
|
Upper Siang
Project(Arunachal Pradesh)
|
-
|
Nil
|
1) Indirect
2) 9500 MW
3) 1.44 MAF
4) Flood
moderation
|
Pre-Feasibility
Report (PFR) Stage
|
5
|
Renuka
Dam Project(Himachal Pradesh)
|
5242.89
(PL 2015)
|
Nil
|
1) Drinking
water
2) 40 MW
3) 0.404 MAF
|
Appraisal
stage
|
6.
|
Gyspa
HE Project (Himachal Pradesh)
|
-
|
Nil
|
1) 0.50 lakh
ha
2) 300 MW
3) 0.74 MAF
|
Detailed Project Report (DPR) Stage
|
7.
|
Kishau
Multipurpose Project (Himachal Pradesh/ Uttarakhand)
|
7193.24
(PL 2010)
|
Nil
|
1) 0.97 Lakh
2) 660 MW
3) 1.04 MAF
|
Appraisal
stage
|
8
|
Ujh
Multipurpose project (Jammu & Kashmir)
|
3630.73
(PL 2013)
|
Nil
|
1) 0.32 lakh
2) 212 MW
3) 0.82 MAF
|
Appraisal
stage
|
9.
|
Bursar
HE Project(Jammu & Kashmir)
|
-
|
Nil
|
1) 1 lakh
(indirect)
2) 1230 MW
3) 1 MAF
|
DPR
Stage
|
10.
|
Gosikhurd
Irrigation Project (Maharashtra)
|
7777.85
(PL
2007-08);
|
2008-09
= 450
2009-10
= 720
2010-11
=1412.94
2012-13
=405
Total = 2987.94.
|
1) 2.50 lakh
2) 3 MW
3) 0.93 MAF
|
ongoing
|
11.
|
Ken
Betwa Link Project Phase-I (Madhya Pradesh & Uttar Pradesh)
|
18057.08
(PL 2015-16)
|
Nil
|
1) 6.35 lakh
2) 78 MW
3)2.18 MAF
|
Appraisal
stage
|
12.
|
Shahpurkandi
Dam Project (Punjab)
|
2285.81
(PL
04/08)
|
2009-10
= 10.80
2010-11
=15.236
Total = 26.036
|
1) 0.37 lakh
2) 168 MW
3) 0.012MAF
|
ongoing
|
13.
|
2nd
Ravi Vyas Link Project (Punjab)
|
-
|
Nil
|
Harness water
flowing across border (about 0.58 MAF in non-monsoon period)
|
PFR
Stage
|
14.
|
SaryuNaharPariyojna(Uttar
Pradesh)
|
.
7270.32
(PL 2008-09)
|
2012-13=67.98
2013-14=
380.75
2014-15=210.85
2015-16
= 500
Total =1159.58
|
1) 14.04(NP
Component:4.73)
2) –
3)
Barrage
|
ongoing
|
15..
|
Lakhwar
Multipurpose Project (Uttarakhand)
|
3966.51
(PL
2012)
|
Nil
|
1) 33,780 lakh.
2) 300 MW
3) 0.267 MAF
|
Appraisal
stage
|
16.
|
Teesta
Barrage Project (West Bengal)
|
2988.61
(PL
2008)
|
2010-11=81
2011-12=
97.20
Total = 178.20
|
1) 9.23 lakh
(NP component:5.27)
2) 1000 MW
3)
Barrage
|
ongoing
|