As
on 30th November, 2015, more than 93% of the mandated activities of
Phase I of the Project have been completed.
|
S. No.
|
Module
|
Status as
on
30.11.2015
|
%
Completion
|
|
1.
|
Sites
readiness
|
14249
|
100.0
|
|
2.
|
Hardware
installation
|
13436
|
94.29
|
|
3.
|
LAN
installation
|
13643
|
95.75
|
|
4.
|
Software
deployment
|
13273
|
93.15
|
In
addition to above, ICT infrastructure of the Supreme Court and High Court has
also been upgraded. A unified national core application software – Case
Information System (CIS) software - has been developed and made available for
deployment at all computerized courts. The national e-Courts portal (http://www.ecourts.gov.in) has become
operational and has been opened for public access through websites of
individual districts as well as through the National Judicial Data Grid (NJDG).
The portal provides online services to litigants such as details of case
registration, cause list, case status, daily orders, and final judgments.
Currently, litigants can access case status information in respect of over 5.59
crore pending and decided cases and more than 1.93 crore orders/judgments
pertaining to district and subordinate Courts. NJDG data will also help the
judiciary in judicial monitoring and management and the Government to get data
for policy purposes.
Against
the approved cost of Rs.935 crore, Rs.617.35 crore have been released to
National Informatics Centre (NIC, the Implementing Agency for Phase I of the
Project) upto 30th November, 2015 for the above components of the
e-Courts Phase I project for all the states on consolidated basis.
E-filing
was taken up in Phase I of the Project, but it is included in Phase II of the
Project. The implementation of Phase II commenced on 4th August,
2015.
This
information was given by Union Minister of Ministry of Law & Justice, Shri
D. V. Sadananda Gowda in a written reply in Lok Sabha today.