During
the year 2013-14 the Railways have completed 1,532 km of New Line, Doubling and
Gauge Conversion against a revised target of 1,525 km.  Sections commissioned in 2013-14 include:
 
New Lines
a.     Karur – Salem (85 Km)
b.     Koderma – Nawadih (34 Km) 
c.      Lalitpur – Tikamgarh (51.5 Km)
d.     New Morinda to Sanewal (54 Km)
thereby complete commissioning of Chandigarh – Ludhiana
e.      Qazigund – Banihal (19 Km) 
f.       Kadur – Chikmaglur (46 Km) 
                             
                   Gauge Conversion:
a.    
Hanumangarh – Sriganganagar (64Km) 
b.    
Manamadurai – Virudunagar (67 Km) 
c.     
Darum  Madhepura – Murliganj (22 Km) 
d.    
Kolar – Chickballapur (85 Km)
e.     
 Rangiya – Rangapara North – Dekargaon (145 Km) 
 
                   Doubling:
a.     Panskura – Shyamchak (27 km) 3rd Line
b.     Muri – Tulin (1.5 km) Doubling 2nd Bridge over River Subernarekha
c.      Jirat – Ambika Kalna (20.23 km) 
d.     Magrahat – Diamond Harbour
(15 km) 
e.      Kursela-Karagola (17 km) 
f.       Katereah-Kosi cabin (4km) 
g.     Madur – Mandya (19 km) 
h.     Birur – Ajjampur (18km)
****
 
MKP/AD/DB