Establishment of New Nuclear Power Plants in the Country

                There are six nuclear power reactors installed at Rawatbhata in Rajasthan with a total capacity of 1180 MW. The details are given below :-

Unit

Capacity (MW)

Date of Commercial operation

1.

RAPS-1

100

16- Dec- 1973

2.

RAPS-2

200

01-Apr-1981

3.

RAPS-3

220

01-Jun-2000

4.

RAPS-4

220

23-Dec-2000

5.

RAPS-5

220

04-Feb-2010

6.

RAPS-6

220

31-Mar-2010

Total Capacity

1180

 

Legend: RAPS : Rajasthan Atomic Power Station.

 

Presently, 1080 MW capacity is in operation, as Rajasthan Atomic Power Station (RAPS) Unit-1 (100 MW) is under extended shutdown for techno-economic assessment for continued operation.

 

                                There are two nuclear power reactor Rajasthan Atomic Power Project (RAPP) - Units 7 & 8 (2x700 MW), with a total capacity of 1400 MW, under construction at Rawatbhata. In addition, the Government has accorded ‘In-principle’ approval for setting up four more nuclear power reactors, each of 700 MW at Mahi-Banswara in Rajasthan. These are planned in two phases, each of 2x700 MW.

 

                                The XII Five Year Plan proposals envisage start of work on 19 new nuclear power reactors with a total capacity of 17400 MW. The details are as under :-

Project

Location

Type

 Capacity (MW)

Indigenous Reactors

GHAVP 1&2

Gorakhpur, Haryana

PHWR

2 x 700

CMAPP 1&2

Chutka, Madhya Pradesh

2 x 700

MahiBanswara, 1&2

MahiBanswara, Rajasthan

2 x 700

Kaiga 5&6

Kaiga, Karnataka

2 x 700

FBR 1&2

Kalpakkam, Tamilnadu

FBR

2 x 500

AHWR

Location to be decided

AHWR

300

Reactors with International Co-operation

KKNPP 3&4

Kudankulam, Tamilnadu

LWR

2 x 1000

JNPP 1&2

Jaitapur, Maharashtra

2 x 1650

Kovvada, 1&2

Kovvada, Andhra Pradesh

2 x 1500

ChhayaMithiVirdi, 1&2

ChhayaMithiVirdi, Gujarat

2 x 1100

 

 

 

 

 

 

 

                       The Minister of State for Personnel, Public Grievances & Pensions and Prim Minister’s Office Shri V.Narayansamy gave this information in reply to a written question in the Rajya   Sabha today.

*****