01 JUL 2019 4:38PM by PIB Delhi
Progress in completion of Delhi-Meerut Highway

 The Delhi Meerut Expressway has been taken up in four. packages.  The details of packages and status of work are as under:

Sr. No.

NH No.

Details of Project

Lanes

Status

1

24

(New NH-9)

Pkg.-I: From km 0.00 to km 8.716 (Nizamuddin to U.P. Gate) in Delhi

6-Lane Expressway + 8 National Highway

The project has been completed in June, 2018.

2

24

(New NH-9)

Pkg.-II:  From km 8.716 to km 28.000 (U.P. Border to Dasna) in UP

6-Lane Expressway + 8 National Highway

The present physical progress is 53%.  The scheduled date of completion is May, 2020.

3

24

(New NH-9)

Pkg.-III: From km 28.000 to km 50.270 (Dasna to Hapur Bypass) in U.P.

6-National Highway

The present physical progress is 93%.  Expected date of completion is 31st July, 2019.

4

New Alignment

Pkg.-IV:  Greenfield alignment  from Dasna to Meerut (km 27.740 to km 59.777) in UP.

6-Lane Expressway

The present physical progress is 51%.   Expected date of completion is 31st December, 2019.

 

This information was given by Shri Nitin Gadkari, Union Minister for Road Transport & Highways in response to a question in Rajya Sabha today.         

*****