Ministry of Railways
azadi ka amrit mahotsav

PIRPAINTI–JASIDIH NEW RAIL LINE PROJECT

प्रविष्टि तिथि: 13 AUG 2026 6:57AM by PIB Patna

Budget allocation in the recent years has increased significantly. Budget allocation for infrastructure projects falling fully/partly in the Bihar is as under:-

Period

Outlay

2009-14

₹1,132 Cr./year

2026-27

₹10,379 Cr. (More than 9 times)

 Track construction:

The details of commissioning/laying of new track falling fully/partly in the State of Bihar is as under:-

Period

New Track Commissioned

Average Commissioning of new tracks

2009-14

318 Km

63.6 Km/year

2014-26

2,034 Km

169.5 Km/year (More than 2.5 times)

Projects sanctioned:

As on 01.04.2026, 59 projects (32 New Lines, 01 Gauge Conversions and 26 Doubling), covering a total length of 5,067 km, costing ₹96,651 crore, falling fully/partly in Bihar are sanctioned. The summary is as under:-

Category

No of sanctioned Projects

Total Length

 (in Km)

Length Commissioned till Mar'26
(in Km)

Total Exp upto Mar'26

(₹ in Cr)

New Lines

32

2,616

533

14,806

Gauge Conversion

1

69

52

544

Doubling/Multi-tracking

26

2,382

465

14,509

Total

59

5,067

1,050

29,860

 Recently completed projects:

Details of some of the recently completed projects falling fully/partly in Bihar are as under:-

SN.

Project 

Cost

(In Crores of Rs)

1

Patna bridge (28 Km)

3,310

2

Munger rail cum road Bridge (15 Km)

3,040

3

Kosi Bridge (22 Km)

863

4

Daniawan-Biharsharif new line (38 Km)

354

5

Chandan-Banka new line (40 Km)

496

6

Rampurhat-Mandarhill new line (130 Km)

908

7

Maharajganj-Masrakh new line (35 Km)

412

8

Rajgir-Tilaiya & Natesar-lslampur new line (67 Km)

726

9

Jaynagar-Narkatiaganj gauge conversion (260 Km)

967

10

Kaptanganj-Chhapra gauge conversion  (234 Km)

819

11

Sakri-Nirmali, Saharasa-Forbesganj gauge conversion   (206 Km)

2,113

12

Mansi-Saharsa, Saharsa-Purnia, Banmakhi- Bihariganj gauge conversion (169 Km)

752

13

Sahibganj-Pirpainti doubling (23 Km)

129

14

Maheshkunt-Thanabihpur doubling (32 Km)

115

15

Hajipur-Ramdayalu Nagar doubling (48 Km)

367

16

Pirpainti-Bhagalpur doubling (51 Km)

493

17

Kiul-Gaya doubling (124 Km)

2,462

18

Hajipur-Bachwara doubling (72 Km)

930

19

Araria-Galgalia (Thakurganj) new line  (110 Km)

2,132

20

Samastipur-Darbhanga Doubling (38 Km)

874

Ongoing projects:

Some of the projects falling fully/partly in the State of Bihar which have been taken up are as under:

SN.

Project

Cost (Rs. in Cr.)

1

Sakri-Hasanpur new line (76 Km)

802

2

Fatuha-lslampur new line (167 Km)

3,158

3

Koderma-Tilaiya new line (65 Km)

2,287

4

Hajipur-Sagauli new line (151 Km)

2,820

5

Araria-Supaul new line (96 Km)

2,170

6

Kursela-Bihariganj new line (58 Km)

194

7

Pirpainti-Jassidih new line (97 Km)

2,700

8

Chhitauni-Tumkuhi Road new line (59 Km)

1,881

9

Jalalgarh-Kishanganj new line (51 Km)

407

10

Sitamarhi-Nirmali new line (189 Km)

2,833

11

Bihta-Aurangabad new line (120 Km)

3,606

12

Gaya-Chatra and Gaya-Natesar new line (135 Km)

4,543

13

Sultanganj-Katuria new line (77 Km)

291

14

Jaynagar-Bijalpura Gauge conversion (69 Km)

900

15

Dhanbad-Sonnagar 3rd line (291 Km)

7,906

16

Sagauli-Valmikinagar Doubling (110 Km)

1,456

17

Muzaffarpur-Sugauli Doubling (101 Km)

1,745

18

Barauni-Bachwara 3rd & 4th line (32 Km)

486

19

Narkatiaganj-Darbhanga, Sitamarhi-Muzaffarpur doubling (256 Km)

4,080

20

Chhapra-Ballia Patch Doubling (65 Km)

1,046

21

Katihar-Kumedpur and Katihar-Mukuria Doubling
(65 Km)

943

22

Son Nagar-Andal Multitracking (749 Km)

12,334

23

Punarakh- Bhaktiyarpur New 4th line & balance 3rd line (28 Km)

422

24

Aluabari Road-Thakurganj Doubling (20 Km)

327

25

Bhagalpur-Jamalpur 3rd line (53 Km)

1,156

26

Bhagalpur-Dumka-Rampurhat doubling (177 Km)

3,169

27

Bakhtiyarpur-Rajgir-Tilaiya doubling (104 Km)

2,192

28

Bakthiyarpur-Fatuha 3rd and 4th line (24 Km)

931

29

Punarakh-Kiul 3rd and 4th line (50 Km)

2,668

30

Kiul-Jhajha 3rd Line (54 Km)

962

31

Mansi-Saharsa doubling (44 Km)

499

Zonal Railway wise details of Railway projects are made available in public domain on Indian Railway’s website.

Pirpainti-Jasidih new line (97 km)

Pirpainti-Jasidih new line (97 km) has been sanctioned at a cost of ₹2700 Cr. Expenditure of ₹1697 Cr has been incurred in this project and ₹270 Cr has been allocated in FY 2026-27. 38 Km out of 97 km has been commissioned. Works have been taken up in balance sections.

  • 338 Ha out of 613 Ha land acquisition has been completed and balance land acquisition taken up. 

  • 03 major bridges out of 31 have been completed. Work on balance bridges have been taken up. 

  • 45 minor bridges out of 119 have been completed. Work on balance bridges have been taken up.

  • 25 ROBs out of 37 have been completed. Work on balance ROBs have been taken up. 

  • 02 RUBs out of 39 have been completed. Work on balance RUBs have been taken up. 

  • 38 Km track linking out of 97 Km has been completed. Work on balance track has been taken up.

Completion of Railway projects/s depends on various factors which include the following:

  • Land acquisition by State Government

  • Forest clearance 

  • Shifting of infringing utilities

  • Statutory clearances from various authorities 

  • Geological and topographical conditions of area

  • Law and order situation in the area of project site

  • Number of working months in a year for particular project site etc.

All these factors affect the completion time and cost of the project/s.  

Station Redevelopment:

Ministry of Railways has launched Amrit Bharat Station Scheme for redevelopment of stations with a long-term approach.

The scheme involves preparation of master plans and their implementation in phases to improve the stations of Indian Railways. The master planning, keeping in view the necessity of each station, includes:

  • Improvement of access to station and circulating areas

  • Integration of station with both sides of city

  • Improvement of station building

  • Improvement of waiting halls, toilets, sitting arrangement, water booths

  • Provision of wider foot over bridge/subway to commensurate with passenger traffic

  • Provision of lifts/escalators/ramps

  • Improvement of platform surface/ provision of platform shelter

  • Provision of kiosks for local products through schemes like 'One Station One Product'

  • Parking development

  • Amenities for Divyangjans

  • Better passenger information systems

  • Provision of air concourse, executive lounges, Multimodal integration, landscaping, etc.

The scheme also envisages sustainable and environment friendly solutions etc. as per necessity, phasing and feasibility and creation of city centre at the station in the long term.

So far, 1,340 stations have been identified for development under this scheme, out of which 98 stations are located in Bihar. The names of stations identified for development under Amrit Bharat Station Scheme in Bihar are as following:

State

No. of Stations

Name of Stations

Bihar

98

Anugraha Narayan Road, Ara, Arariya Court, Bakhtiyarpur, Banka, Banmankhi, Bapudham Motihari, Barahiya, Barauni, Barh, Barsoi Jn, Begusarai, Bettiah, Bhabua Road, Bhagalpur, Bhagwanpur, Bihar Sharif, Bihiya, Bikramganj, Buxar, Chakia, Chausa, Chhapra, Dalsingh Sarai, Darbhanga, Dauram Madhepura, Dehri On Sone, Dholi, Dighwara, Dumraon, Durgauti, Ekma, Fatuha, Gaya, Ghorasahan, Guraru, Hajipur Jn, Jamalpur Jn, Jamui, Janakpur Road, Jaynagar, Jehanabad, Jhanjharpur, Kahalgaon, Karhagola Road, Katihar Jn, Khagaria Jn, Kishanganj, Kudra, Labha, Laheria Sarai, Lakhminia, Luckeesarai Jn, Madhubani, Maheshkhunt, Mairwa, Mansi Jn, Masrakh, Mokama, Motipur, Munger (Monghyr), Muzaffarpur Jn, Nabinagar Road, Narkatiaganj Jn, Naugachia, Nawadah, Paharpur, Patliputra, Patna Jn, Piro, Pirpainti, Rafiganj, Raghunathpur., Rajendra Nagar Terminal (Patna), Rajgir, Ram Dayalu Nagar, Raxaul, Sabaur, Sagauli, Saharsa, Sahibpur Kamal, Sakri, Salauna, Salmari, Samastipur, Sasaram, Shahpur Patoree, Shivanarayanpur, Simri Bakhtiyarpur, Simultala, Sitamarhi, Siwan, Sonpur Jn., Sultanganj, Supaul, Taregna, Thakurganj, Thawe

 

Completed stations:

Development works at railway stations under Amrit Bharat Station Scheme in Bihar have been taken up at a good pace. Details of stations completed in Bihar are as under:

State

No. of Stations

Name of Stations

Bihar

08

Banmankhi, Dauram Madhepura, Kahalgaon, Pirpainti, Sabaur, Shivanarayanpur, Simultala, Thawe

The activities for development at other stations have also been taken up at good pace and progress of some of the stations is as given below:

  • Saharsa station: The works of new main entry station building, parking, improvement to circulating area, platform shelter, entrance gate and boundary wall have been completed. The work of 12 m wide foot over bridge has been taken up.

  • Salauna station: The works of new main entry station building, platform shelter, improvement of circulating area, entrance gate and boundary wall have been completed. The work of 12 m wide foot over bridge has been taken up.

  • Sonpur station: The works of new atrium building, booking counter, improvement of station building, improvement of circulating area, parking and entrance porch have been completed. The work of 12 m wide foot over bridge has been taken up.

  • Anugraha Narayan Road station: The works of extension of platform no. 1/2 & 3/4, improvement of platform surface of platform no. 1/2 & 3/4 and new toilet block have been completed. The works of improvement of station building, improvement of circulating area, entry/exit gate, water booths, platform shelter and 6 m wide foot over bridge have been taken up.

  • Luckeesarai Junction station: The works of new main entry station building, extension of foot over bridge and improvement of circulating area have been completed. The work of lift for existing foot over bridge has been taken up.

Further, development/ redevelopment/ upgradation/ modernisation of stations on Indian Railways is a continuous and ongoing process and works in this regard are undertaken as per requirement, subject to inter-se priority and availability of funds. Development/ redevelopment / upgradation/ modernisation of a station is carried out based on category of station/ condition/ traffic handled etc.

Development/upgradation/modernisation of stations including under Amrit Bharat Station Scheme is generally funded under Plan Head-53 'Customer Amenities'. The details of allocation and expenditure under Plan Head-53 are maintained Zonal Railway- wise and not station-wise or state-wise. Bihar is covered under the jurisdiction of four railway zones, namely, Eastern Railway, East Central Railway, North Eastern Railway and Northeast Frontier Railway. For these zones, an allocation of ₹1,543 crore has been made for the current financial year, out of which an expenditure (up to June, 2026) of ₹677 crore has been incurred so far.

Development/Upgradation of railway stations is a complex in nature involving safety of passengers & trains and requires various statutory clearances such as tree cutting, heritage, fire clearance, airport clearance etc. These stations are in operation since long, so brownfield work challenges are being faced, such as shifting of utilities (involving water/sewage lines, optical fibre cables, gas pipelines, power/signal cables, etc.), infringements, operation of trains without hindering passenger movement, speed restrictions due to works carried out in close proximity of the tracks and near to high voltage power lines, etc. and these factors affect the progress of work and completion time.

*****

(This statement was given by MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND ELECTRONICS & INFORMATION TECHNOLOGY SHRI ASHWINI VAISHNAW in a written reply to a question in Lok Sabha on 12.08.2026)