Ministry of Tribal Affairs
PM-JANMAN Scheme for PVTGs in Kerala
प्रविष्टि तिथि:
18 DEC 2025 3:23PM by PIB Delhi
Replying to an un-starred question today in Lok Sabha the Union Minister of State for Tribal Affairs Shri Durgadas Uikey informed that the details of benefits given under Pradhan Mantri Janjati Adivasi Nyaya Maha AbhiyaN (PM JANMAN) in the State of Kerala, Ministry-wise, since its inception is given in Annexure I.
On 15th November 2023, Hon'ble Prime Minister launched PM JANMAN for socio-economic development of 75 PVTG communities residing in 18 States and one UT. The mission aims to provide basic facilities to improve their socio-economic conditions such as safe housing, clean drinking water and improved access to education, health and nutrition, road and telecom connectivity, electrification of unelectrified households and sustainable livelihood opportunities in 3 years. These objectives are being met through 11 interventions implemented by 9-line Ministries.
In view of the implementation of PM JANMAN, the Ministry of Tribal Affairs through the State Governments/ UT Administration/departments has undertaken habitation level data collection exercise through PM Gati Shakti mobile application to estimate PVTG population figures and infrastructure gaps in order to cover PVTG population residing in villages & habitations under PM JANMAN.
The details of targets and achievements under the PM JANMAN since its inception is given in Annexure II.
To ensure the effective implementation and monitoring of the PM JANMAN, Ministry has been regularly reviewing the implementation with State Governments and District administrations. Further, the State Government is also required to comply with the instructions of Department of Expenditure regarding SNA SPARSH alongwith applicable GFRs. Besides, for monitoring the progress of the works under PM JANMAN, digital dashboard on PM GatiShakti portal has been developed. A Project Monitoring Unit in the Ministry has also been established for monitoring and coordination with Ministries and States / UT. NITI Aayog has conducted an evaluation study in 2025 covering Centrally Sponsored Schemes including PM JANMAN.
Annexure I
PM JANMAN Progress in the State of Kerala (as on 24th November 2025)
|
Ministry / Scheme
|
Activity
|
Progress
|
|
MoRD (PMAY-G)
|
Houses Sanctioned (No.)
|
965
|
|
Houses Completed (No.)
|
11
|
|
MoHFW (NHM)
|
MMUs operationalized (No.)
|
24
|
|
MoJS (JJM)
|
Sanctioned Villages (No.)
|
96
|
|
Saturated Villages (No.)
|
1
|
|
MoWCD (POSHAN 2.0)
|
AWCs sanctioned (No.)
|
7
|
|
AWCs operationalized (No.)
|
7
|
|
MoE (SSA)
|
Hostels sanctioned (No.)
|
4
|
|
MoP (RDSS)
|
HHs sanctioned (No.)
|
345
|
|
HHs electrified (No.)
|
313
|
|
MNRE
|
HHs sanctioned (No.)
|
98
|
|
MoC (DoT-USOF)
|
Habitation planned for coverage (No.)
|
52
|
|
Habitations covered (No.)
|
30
|
|
MoTA
|
MPCs sanctioned (No.)
|
15
|
|
MPCs Completed (No.)
|
4
|
|
VDVKs sanctioned (No.)
|
7
|
|
Business started (No.)
|
5
|
Annexure II
PM JANMAN Progress (as on 24th November 2025)
|
Name of Ministry
|
Activity
|
Mission Target (2023-2026)
|
Sanction details
|
Physical Achievements
|
|
M/o Rural Development
|
Provision of pucca houses
|
4.90 lakh houses
|
471300 houses
|
238133 houses completed
|
|
Connecting roads
|
8000 km road
|
6951.39 km road
|
825 Km road completed
|
|
M/o Health and Family Welfare
|
Mobile Medical Units
|
1000 MMU (733 MMUs sufficient to cover all)
|
694 MMUs
|
694 MMUs operationalized
|
|
M/o Jal Shakti
|
Piped Water Supply
|
19375 Villages
|
18463 Villages
|
7712 Villages 100% Saturated
|
|
M/o Women and Child Development
|
Construction and running of Anganwadi Centres
|
2500
|
2500 AWCs
|
2084 AWCs made operational.
|
|
M/o Education
|
Construction and running of hostels
|
500
|
500 Hostels
|
Work started in 111 Hostels.
|
|
M/o Power
|
Energization of unelectrified HHs
|
145083 HHs
|
145083 HHs
|
134102 HHs Electrified
|
|
M/o New and Renewable Energy
|
Households sanctioned under New Solar Power Scheme
|
As per identificaton of beneficiaries eligible for off-grid
|
8911 HHs
|
5814 HHs Electrified
|
|
M/o Communications
|
Installation of mobile towers
|
Coverage of 4543 habitations
|
4015 habitations planned for Coverage
|
2944 Habitations covered
|
|
M/o Tribal Affairs
|
Multipurpose Centers
|
1000
|
1000 MPCs
|
328 completed
|
|
Setting up of VDVKs
|
500
|
539 VDVKs
|
450 VDVKs Business Started
|
|
# As information provided by Ministry
|
*****