NHSRCL Signs Agreement for Track related works for Mumbai Ahmedabad Bullet Train Project in Maharashtra

Posted On: 11 SEP 2025 5:00PM by PIB Ahmedabad

National High Speed Rail Corporation Limited signed an agreement today, with M/s Larsen & Toubro Limited for Design, Supply and Construction of Track and Track related Works including Testing and Commissioning for Double Line High Speed Railway’ in the state of Maharashtra. Totalling about 157 route km alignment, the complete alignment between Mumbai Bullet Train station and Zaroli village at Maharashtra-Gujarat border also includes the track works for four (04) stations and rolling stock depot at Thane.

Work on track construction in Gujarat (under package T-2 & T-3) is progressing rapidly on more than 200 km of viaduct. All three track construction work related packages have been awarded to Indian companies, thus increasing India’s overall expertise and knowhow in high speed rail track construction technology.

 

The ballast-less slab track system as used in Japanese HSR (Shinkansen) is being used for India’s first HSR project (MAHSR). This track system consists of four main components viz. RC Track Bed, Cement Asphalt Mortar (CAM), Pre-cast Track Slab and Rails with Fasteners.

Under an MOU with NHSRCL, the Japan Railway Technical Service (JARTS) has conducted comprehensive training and certification programs for Indian engineers, work leaders, supervisors, and technicians. Covering 15 specialized modules, these programs focussed on key areas such as track slab manufacturing, RC track bed construction, slab track installation, and CAM installation. Under the T-2 and T-3 packages in Gujarat, around 436 engineers have already been trained in these advanced techniques. A similar initiative is planned under this package to train engineers and supervisors in Maharashtra before the commencement of track works.

Project Progress as on 8th September 2025

  • Viaduct construction: 320 km
  • Pier works: 397 km
  • Pier Foundation: 408 km
  • 17 river bridges, 09 steel bridges and 05 PSC (pre stressed concrete) bridges are completed
  • 4 lakhs noise barriers installed along 203 km of stretch
  • 202 track km of track bed construction completed
  • 1800 OHE masts installed covering approx. 44 km of mainline viaduct
  • Work on 21 km tunnel between BKC and Shilphata in Maharashtra in progress
  • Excavation work on 07 mountain tunnels in Palghar district in progress
  • Superstructure work on all stations in Gujarat is at advanced stage. Work started on all three elevated stations and base slab casting at Mumbai underground station in Maharashtra is in progress

 

 

 

 

 

 

 

 

 


(Release ID: 2165715) Visitor Counter : 2