Parliament Question: - National Highways in Bihar

Posted On: 19 DEC 2024 4:09PM by PIB Delhi

Development and maintenance of National Highways (NHs) is a continuous process. The list of NH projects in Bihar approved for implementation are at Annexure-I. The list of ongoing NH projects in Bihar are at Annexure-II. The list of NH projects in Bihar completed during last ten years is at Annexure-III.

The bottlenecks in the ongoing and approved for implementation of NH projects in Bihar including Katihar are mainly due to delay in land acquisition, forest clearance, utility shifting, etc.

 

21 new toll plazas have been proposed in the State of Bihar. There is no new toll plaza proposed in Katihar district.

User fee rates on NHs throughout the country including Bihar are revised annually in accordance with NH Fee Rules 2008.

The details of toll plaza-wise number of toll tenders which have been extended beyond their original period are at Annexure-IV.

 

ANNEXURE-I

ANNEXURE-I REFERRED TO IN REPLY TO PART (a) OF LOK SABHA UNSTARRED QUESTION NO. 4022 TO BE ANSWERED ON 19.12.2024, ASKED BY SHRI TARIQ ANWAR REGARDING NATIONAL HIGHWAYS IN BIHAR

List of NH projects in Bihar approved for implementation

 

Sl. No

Name of Project

NH No.

Length (km)

1

Construction of 4 lane with paved shoulder of Darbhanga (Dilli More) - Banwari Patti from km 0.00 to km 14.95 (Package-1) including Pre-construction activities from km 0.00 to km 53.133 of NH-105(New NH-527B)

527B

14.95

2

Four lane with Paved shoulder configuration from Existing Km 0+000 to Km 39+500 (design km (0+500) to Km 40+342, Design length km) of NH – 227A ( near Mehrauna Ghat (UP – Bihar Border) to Siwan on Hybrid Annuity Model (HAM) basis

227A

40.842

3

Construction of Four-Lane of Chausa-Buxar Bypass from Km 45.000 to Km 65.915 (Package – 2)

319A

20.915

4

Construction to two-laning with paved shoulder of Daudnagar Bypass, Nasriganj Bypass and Dawath Bypass of NH-120

120

5.535

5

Construction of 6 no of Mangobandhar Kendua, Tolesono, Jhajha,Narganjo & Bhairogunj Bypasses including Pre-Construction activities from km 72.000 to 134.000 of NH - 333A

333A

41.271

6

Construction of Four lane with paved shoulder of Bhagalpur– Kharhara village (Dhaka more) from Km- 0+000 to KM 36+600 of NH 133E

133 E

36.6

7

Construction for 2 Lane ROB over L.C. No 2 between Muktapur & Kishanpur Station on Samastipur - Darbhanga Road (NH-322) in Samastipur District

322

1.64

8

Construction of 3 no. of Bypasses at Sheikhpura, Jamui & Khaira including Pre-Construction activities from km 0 to km 72.00 of NH-333A

333A

13.472

9

Construction of additional 3-Lane Bridge over River Ganga for connection between Buxar and Bharauli on NH-922

 

922

 

3.30

 

10

 

4 lanning of Manikpur to Sahebganj section

 

139W

 

44.65

11

 

6L Patna – Purnia Expressway

 

--

 

270

 

ANNEXURE II

ANNEXURE-II REFERRED TO IN REPLY TO PART (a) OF LOK SABHA UNSTARRED QUESTION NO. 4022 TO BE ANSWERED ON 19.12.2024, ASKED BY SHRI TARIQ ANWAR REGARDING NATIONAL HIGHWAYS IN BIHAR

List of ongoing NH projects in Bihar

 

Sl . No

 

Name of Project

 

Length (km)

 

Appointed Date

Physical progress

%

Schedule/Revised Date of Completion

1

Construction of 2-lane combined ROB in km 1.10 & km 1.11 of NH- 101.

1.5

28.08.2019

95.3%

31.12.2024

2

Construction of 2-lane ROB of km 94 of NH-28B

1.744

09.03.2022

33.01%

30.06.2025

3

Construction of 2-lane ROB of km 91 of NH-28B

1.258

08.04.2022

87%

16.04.2025

4

Construction of ROB in km 49 of NH 131A at Gaushala

1.21

05.02.2021

69.25%

31.03.2025

5

Construction of ROB in km 194 (LC no. 53B/T-2) of NH 327E

1.58

16.05.2020

60.45%

31.03.2025

6

Construction of ROB in km 24 (LC no. 77A) of NH 327A

 

1.05

 

16.05.2020

 

98.3%

 

31.12.2024

7

Construction of 2 lane ROB and its approaches in km 158 on NH-104 at Jainagar Bypass in the state of Bihar on EPC mode

 

ROB

 

09.11.2022

 

51.00%

 

25.06.2025

8

Construction of 4 lane ROB and its approaches at the level of crossing (L C   No.   29-B)   of   Km   29

(Ekangansarai) at NH-110(New NH- 33) & Railway Km 32.63 of Fatwa (FUT) - Islampur (IPR) section in the state of Bihar on EPC mode.

 

 

3.66

 

 

20.07.2024

 

 

2.50%

 

 

19.07.2026

9

Construction of a new 4 lane Major Bridge across River Kosi at Phulaut including Rehabilitation and upgradation of existing Birpur-Bihpur Section of NH-106 from km 106 to

136 to 2- Lane Paved shoulder on EPC mode

 

 

28.918

 

 

07.06.2021

 

 

59.70%

 

 

15.05.2026

10

Construction of a new 4 lane (Parallel to     existing         MG       Setu)       with   its

14.5

25.03.2021

48.21%

28.02.2026

 

 

approaches  from  km 0.00  to  km

14.500 across river Ganga on NH-19 at Patna on EPC basis.

 

 

 

 

11

Construction of New 4-Lane Bridge (Parallel to existing Vikramashila Setu)from km 8+920 to Km 13+375(including approach road 35m Naugachhia side &53 m Bhagalpur side)across River Ganga on newly declared NH-131B at Bhagalpur in the State of Bihar

 

 

 

4.5

 

 

 

9.05.2023

 

 

 

22.3%

 

 

 

08.05.2027

12

Construction of New high level RCC bridge at existing location of old Bridge cross Chir River in km 199 on NH-333A & its approaches having an aggregate length of 700 (350 m on both side) in District Banka in the state of Bihar on EPC mode

 

 

Bridge

 

 

15.11.2022

 

 

99.99%

 

 

31.12.2024

13

Construction of 6-Lane Elevated / Extra Dose Cable Bridge on River Ganga parallel to & Western side of Digha-Sonepur Rail cum-Road Bridge of NH 139W in the State of Bihar.

 

 

6.895

 

 

02.05.2024

 

 

0

 

 

02.11.2027

14

Widening & strengthening work from Km 26.3 to 26.75 and km 30.45 to

30.65,km 32.45 and km 32.66 ,33.910

to km34.200 & km 34.200 to km t km

34.4 of NH- 104 on item rate in state (New NH 331) in the state of Bihar for the year 2021-22

 

 

1.33

 

 

30.06.2022

 

 

90.0%

 

 

31.01.2025

15

Strengthening work in km 68 to 89 of NH110 under EPC Mode in the State of Bihar.

20.65

16.03.2021

98.0%

31.12.2024

16

Improvement of 2 lane with paved shoulder of stretch from Bikramganj Dawath Melayabagh Nawanagr - Dumrow of NH-120 (Km-201.665 to Km 240.200) excluding Dawath bypass under EPC mode in the state of Bihar

 

 

36.965

 

 

05.09.2023

 

 

60.00%

 

 

30.06.2025

17

Rehabilitation & widening work for 2' Lane with Paved Shouldering of Existing National Highway 80 Alignment from Km.'132.895 to Km '190.150 Bhagalpur- Kahalgaon - Mirzachowki section

 

 

57.255

 

 

04.11.2022

 

 

40.0%

 

 

30.06.2025

18

Rehabilitation & Widening work for 2-lane/2-Lane with Paved Shoulder of Existing NH-80 from km 70.15 to

50.875

01.02.2023

64.84%

31.03.2025

 

 

Km 121.025 of Munger-Suttanganj - Bhagatpur- Mirzachowki section on EPC Mode in the State of Bihar.

 

 

 

 

19

Improvement to two lane with paved shoulder from Ramnagar to Roseda from (km 3.500 to 43.000) of NH 527 E on EPC mode in State of Bihar.

 

39.5

 

12.10.2024

 

0

 

11.04.2026

20

Balance work for improvement to 2 lane with paved shoulders configuration in realignment from Km 52.320 to Km 52.940 (length- 0.620 Km) of NH-81, Protection works in HL Bridges at Km 33 & Km 36, Protection work for the approach of Mahananda River bridge and reconstruction of culvert in 30th km of NH-81 on EPC mode

 

 

 

 

0.62

 

 

 

 

16.11.2022

 

 

 

 

70.33%

 

 

 

 

31.03.2025

21

Improvement to two lane with paved shoulders of BH/WB Border- Amdabad-Manihari section from design Km 0+000 to Km23+945 of NH-131 A on EPC mode

 

23.945

 

27.09.2024

 

0.00%

 

26.03.2026

22

Improvement to two lane with paved shoulders of NH 122B from km 29.730 to km 72.348 under EPC mode including Pre construction activity of NH 122B from km 0 to 72.348.

 

 

42.618

 

 

8.05.2023

 

 

73.26%

 

 

31.03.2025

23

Improvement to two lane with paved shoulders of NH-319A from km 0 to km 45 in state of Bihar under EPC mode

 

45

 

20.06.2023

 

60.00%

 

31.03.2025

24

Widening to 2/4-lane with paved shoulders of left out portion of NH 30 from  existing  CH.125.285  to  CH

115.485 (Kayamnagar to Zero Mile) in the state of Bihar for the year 2021-22

 

 

8.6

 

 

21.04.2023

 

 

62.0%

 

 

31.03.2025

25

Construction of Bhabhua Bypass from Ch. 10+800 to Ch. 19+860 and Chand Bypass from Ch. 38+060 to Ch. 40+460 and widening of existing road to 2 - lane with Paved shoulder from Ch. 40+460 to Ch. 46+860 of NH-219

 

 

8.6

 

 

09.03.2024

 

 

0

 

 

08.09.2025

26

Construction of proposed 4_Lane Revelgunj bypass NH-19 in the State of Bihar on EPC mode.

 

7.155

 

10.07.2023

 

35.0%

 

09.07.2025

 

27

Improvement to two lane with paved shoulder of Saraigarh ( on NH – 327A ) – Lalganj-Ganpatganj upto NH – 106 (New NH 131) from km

0.000 to km 10.672 of NH 327AD

 

10.672

 

15.09.2023

 

14.00%

 

15.03.2025

28

Widening from 2-lane to 4- lane of km 92.935(starting point of old NH 82) to 99.685 km (End Point of Gaya Bypass of NH- 33) of NH – 120.

 

6.75

 

22.08.2024

 

0

 

21.02.2026

29

Geometric improvement of NH- 327E at Bhargama and Sukela More including provision of Raniganj Bypass in the state of Bihar.

 

5.529

 

12.06.2024

 

3%

 

12.12.2025

30

Construction to 2 lanes with Paved Shoulder of Jandaha Bypass of NH 103(NH-322) in CH 0.000 (existing Km 35 of NH-103) in the state of Bihar.

 

4.8

 

15.01.2024

 

2.6%

 

15.07.2025

31

Improvement to two lane with paved shoulder of Sarwan – Chakai upto NH-333 from km 0.00 to Km 15.972 of NH 333C

 

15.972

 

01.11.2024

 

20%

 

30.04.2026

32

Widening & Strengthening to 2-lane with paved shoulder of NH-81 from Km 30.250 to Km 55.400

25.15

30.09.2024

8.5%

29.09.2025

33

Improvement to Two lane with paved shoulder from Junction of NH-22 near Hajipur to Junction of NH-122 at Bachhwara via Mahnar and Mohiuddin Nagar from km 0.00 to 29+730 of NH 122B

 

 

29.73

 

 

30.08.2024

 

 

3%

 

 

28.02.2026

34

Rehabilitation and Upgrading to 2 lanes/2-lane with paved shoulders configuration and strengthening of Birpur – Bihpur Section (from km 0.0 to Km 106) of NH – 106 i under phase –I of National Highways Interconnectivity                                   Improvement Projects (NHIIP)

 

 

 

106

 

 

 

03.10.2016

 

 

 

90.10%

 

 

 

31.03.2025

35

Four Laning of Gaya Hisua-Rajgir- Nalanda-Biharsharif Section Km 0.00 to 92.935 on NH-82 in state of Bihar

92.935

07.11.2016

96.45%

31.03.2025

36

Construction of two lane with paved shoulders standard- 4 no. of Bypasses at Katoria, Lakhpura, Banka & Panjwara including Pre- Construction  activities  from  Km

134.000 to Km 190.233 of NH-333A

 

 

14.359

 

 

09.12.2024

 

 

0.00%

 

 

08.12.2026

 

37

4L Greenfield Alignment of Amas to Shivrampur         from    0.000                     Km.    to

55.002 Km. of NH 119 D (Pkg-I)

55.00

31.03.2023

10.88

29.03.2025

38

6L of Aurangabad to Bihar-Jharkhand border (Chordaha) section from km. 209.827 to Km. 249.525 of NH-19 (PKG-02)

 

39.70

 

05.04.2022

 

63.92

 

31.03.2025

39

4L Elevated Section and at-grade improvements at Begusarai town (Simaria - Khagaria section) from Km. 221.047 to Km. 225.302 of NH- 31

 

4.26

 

27.06.2022

 

63.17

 

31.03.2025

40

Aunta - Simaria including Ganga Bridge

8.15

30.08.2018

88.77

31.03.2025

41

Maheshkunt-Saharsa-Purnea (Pkg I) km 0.00 to km. 90.00 of NH-107

90.00

20.12-2019

76

31.03.2025

42

Widening with additional 3L abetting Chhapra Bypass Section of NH-19 from Km. 143.200 to Km. 159.255 (Pkg-1)

 

16.05

 

30.08.2024

 

4.42

 

29.08.2026

43

6L Bridge and its approaches across River Ganga as Part of Patna Ring Road (NH-131G) starting from Km

8.480 near Sherpur to Km 23.000 near Dighwara

 

14.52

 

05.09.2023

 

1.25

 

05.09.2027

44

Chhapra - Hajipur from km. 143.200 to km. 209.200

66.74

27.01.2011

86.7

30.04.2025

45

Construction of Major Bridge over Baghmati and Lakhandei River along with Approaches from Design km.16.500 to km.21.500

 

5.00

 

30.10.2024

 

0

 

31.03.2027

46

4L of Greenfield Alignment from Km.        47.000     to          Km.       89.210     of

Balbhadarpur to Bela Nawda Section of NH-119D

 

42.21

 

11.03.2024

 

6.6

 

10.03.2026

47

4L Elevated Highway and at grade improvements at Gopalganj Town from Km. 384.000 to Km. 386.750 on NH-27

 

2.75

 

04.03.2022

 

92.18

 

31.03.2025

48

2L PS of Majhauli to Charout section from km. 0.00 to km. 63.655

63.66

05.11.2019

96.05

31.03.2025

49

Permanent rectification of 8 Nos. of blackspots on NH-27 & 1 No of at - grade junction removal near Satanpur junction

 

10.259

 

19.11.2024

 

0.00

 

18.11.2026

 

50

4L Greenfield starting from NH-30 near Saristabad (Patna) to Nathupur (Project end point of Patna-Gaya- Dobhi Section of NH-83)

 

3.91

 

27.02.2024

 

10.2

 

07.09.2025

51

4L      Greenfield     Alignment          of Shivrampur to Ramnagar from Km.

55.002 to Km. 109.300 of NH 119 D (Pkg-II)

 

54.32

 

04.07.2023

 

10.3

 

03.07.2025

52

4L of Balance works of Patna - Gaya

-Dobhi (Pkg-II) from km. 39.00 to km. 83.00 of Old NH-83

44.00

09.11.2020

98.5

31.12.2024

53

4L of Balance works of Patna - Gaya

-Dobhi (Pkg-III) from km. 83.00 to km. 127.217 of Old NH-83

44.22

24.11.2020

98.4

31.12.2024

54

4L of Balance works of Patna - Gaya

-Dobhi (Pkg-I) from km. 0.00 to km.

39.00 of Old NH-83

39.00

14.12.2020

99.9

31.12.2024

55

4L of Siwan- Masrakh section of Ram Janki Marg from Km 230.385 to Km 281.391 of NH-227A

50.12

20.11.2024

0

20.11.2026

56

Construction of 2 flyovers of 4- lanes at Chhatauni Chowk and Awadesh Chowk on NH-28A, Re-construction of 3 no. of gantry girder gates with the statue of Mahatma Gandhi on NH-28 and NH-28A & Construction of Service Road and Drain near Piprakothi on NH27

 

 

 

3.34

 

 

 

11.07.2024

 

 

 

0

 

 

 

11-01-2026

57

Rehabilitation and Upgradation of Chroma - Bairgania Section of National Highway No 227F to 2 lane with paved shoulders from Design Ch.0.000 to Ch. 34.566

 

34.57

 

01.02.2024

 

43.5

 

31.01.2026

58

Permanent rectification of 3 nos. of black spots in U.P border - Dewapur - Kotwa section & Permanent rectification of 5 nos. of black spots in Kotwa - Mehsi - Muzaffarpur Section of NH - 27

 

 

13.60

 

 

12.12.2023

 

 

0

 

 

11.12.2025

59

Balance work - WB-10 (Gandak Bridge) Km 402.00 to Km 440.00 (Devanpur - Kotwa)

2.75

30.07.2022

62.48

31.03.2025

60

4L of Munger – Mirzachauki section from Munger to Kharia village junction from Km 69+520 to Km 95+580 (Pkg-1)

 

26.06

 

31.03.2022

 

35.02

 

30.06.2025

61

4L of Munger – Mirzachauki section

29.42

12.03.2022

64.23

25.03.2025

 

 

from Km 95+580 to Km 125+000 (Pkg-2)

 

 

 

 

62

4L of Munger – Mirzachauki section from start of existing Bhagalpur bypass to Rasulpur from Km 125+000 to Km 157+350 (Pkg-3)

 

32.35

 

06.04.2022

 

45.05

 

30.09.2025

63

4L of Munger – Mirzachauki section from Km 157+350 to Km 193+931 (Pkg-4)

36.58

17.08.2022

60.89

31.03.2025

64

Strengthening under one time improvement of 4L of Bakarpur Hat (NH19 Bypass) –Manikpur section of NH-139W

 

38.81

 

08.10.2024

 

0

 

05.04.2027

65

4L Elevated Corridor from Danapur to Bihta

25.08

11.03.2024

13.64

08.09.2026

66

4L Greenfield Alignment from Kalyanapur to Tal Dashraha of NH- 119D (Pkg-III)

47.00

16.02.2023

13.85

31.12.2025

67

Bakhtiyarpur-Rajauli  Pkg-III                                   from km. 101.630 to km.152.520

50.89

31.12.2021

98.23

15.02.2025

68

Bakhtiyarpur    (Km     153.300)    to Mokama (Km 197.900)

44.60

14.06.2017

96

31.03.2025

69

Maheshkunt -Saharsa-Purnea Pkg II

87.96

13.12.2018

76.88

31.03.2025

70

Ara - Mohania (Pkg-II)

60.80

16.01.2021

98.45

31.03.2025

71

Six      Laning     of     Varanasi     to Aurangabad from km. 786.00 to km.

978.40 of Old NH-2

192.40

12.09.2011

86.14

31.03.2025

72

Umagaon-Saharsa          (Package-V) Bakaur-Parsarma-Bangaon-Bariyahi & Spur to Mahishi

39.18

15.12.2023

46.89

14.12.2025

73

Umagaon-Saharsa (Package-IV) Koshi Bridge & approach Road - (Bheja-Bakaur)

13.30

12.02.2020

68.2

30.06.2025

 

ANNEXURE III

ANNEXURE-III REFERRED TO IN REPLY TO PART (a) OF LOK SABHA UNSTARRED QUESTION NO. 4022 TO BE ANSWERED ON 19.12.2024, ASKED BY SHRI TARIQ ANWAR REGARDING NATIONAL HIGHWAYS IN BIHAR

List of NH projects in Bihar completed during last ten years

 

SI.

No.

Name of Project

Length (in km)

Expenditure ( Rs. in crore)

Date of Completion

1

Widening & Strengthening of existing single lane to double lane carriageway in Km 68.10 to Km 86.25 of NH-110

18

58.71

28.04.2017

2

Strengthening & widening to 2 lane with paved shoulder from Km 39 to Km 56 of NH-327E

17

44.13

23.03.2017

3

Strengthening & widening to 2 lane with paved shoulder from Km 98 to Km 112 of NH-327E.

14

63.83

25.03.2017

4

Strengthening & widening to 2 lane with paved shoulder from Km 68 to km 75 NH-327E

7

33.42

15.03.2017

5

Strengthening & widening to 2 lane with paved shoulder from Km 154 to Km 166 of NH-327E

12

57.0

05.04.2017

6

Widening and strengthening of existing road into 2 lane from km 14.50 to km 30 of NH-101 (Job No-101-BR-2012-839)

15.5

30.06

31.03.2018

 

7

Widening to 2-lane and improvement from km 0.00 to km 14.60 of Malaypur- Barhat-Lalmatia-Khadigram                                                      Road (MDR) in under LWE

 

14.6

 

20.87

 

25.03.2014

 

8

Widening and strengthening of existing road into 2 lane with paved shoulder in km 0.00 (Dobhi) to 11.400 (Gosaidih) of NH-99

 

11.4

 

40.28

 

31.05.2018

 

9

Widening & Strengthening of existing single lane to double lane Carriage way from km. 0.00 to km 28 of NH-105 under Special Project Scheme

 

28

 

86.53

 

30.05.2018

 

 

10

Balance work Construction of 5 x 24.00 High Level R.C.C. Bridge across Noon River in replacement of old narrow and damaged screw pile bridge in Km 45th of NH 103 (Hajipur - Musarigharari Section) for the year 2006 - 07

 

 

MJB

 

 

18.68

 

 

30.06.2018

11

Strengthening   &    Widening   work                        of existing 2-lane to two lane with paved

4.5

4.5

30.06.2018

 

 

shoulder including service road & divided carriageway in Araria from km 93.612 to

98.00 of NH-327E.

 

 

 

 

12

Widening and strengthening existing single/ intermediate lane to 2-lane from km. 30.25 to km 55.40 of NH 81 under special project for 2011-12.

 

25

 

139.61

 

30.06.2018

 

13

Upgradation of existing carriageway to 2 lanes/2 lane with paved shoulders configuration of Anishabad-Aurangabad- Hariharganj Section (km 0.0 – km 154.625) of NH-98 -Lot-II

 

89

 

365.58

 

25.09.2018

 

14

Strengthening & Widening of existing carriageway to 2 lane with paved shoulders from Km 40 to km 64 of NH- 28B

 

24

 

93.84

 

30.06.2018

 

15

Widening & Strengthening of existing single lane to double lane Carriage way from km. 28 to 53.76 of NH-105 under Special Project Scheme

 

25.76

 

164.48

 

15.10.2018

16

Construction of Bhagalpur bypass from Km 124/175 to 140/200 of NH-80 under EPC mode

16.7

301.91

11.06.2019

17

Strengthening & Widening of existing carriageway to two lane with paved shoulder from km 0 to 39 of NH 327E

39

108.06

25.03.2019

 

18

Upgradation to 2 lanes/2 lane with paved shoulders of Anishabad-Aurangabad- Hariharganj Section (km 0.0 – km 154.625) of NH-98 - Lot-I

 

62

 

355.36

 

24.10.2019

19

Strengthening & Widening to 2 lane with paved shoulder from km 0.00 to 40.00 on EPC mode on NH 2C

40

231.3

28.12.2019

 

20

Strengthening & Widening of existing carriageway to two lane with paved shoulder from km 56 to km 68 of NH 327E

 

12

 

40.71

 

31.05.2019

 

21

Strengthening & Widening of existing carriageway to two lane with paved shoulder from km 75 to 93.612 of NH 327E

 

18.612

 

72.62

 

05.12.2019

 

22

Improvement of stretch & junction at km

0.00 to 1.40 of NH-80 for the year 2016-

17 under job no. NH-080-BR-2016-17- RSCE-032.

 

1.4

 

18.5

 

29.12.2018

23

Widening & strengthening to 2-lane with paved shoulder from km 62 to 75 of NH- 333

13

68.5

20.06.2019

 

 

24

Widening & strengthening to 2 lane with paved shoulder & Geometric Improvements in Bettiah -Kushinagar section from km 25 to 40 of NH-28B

 

15

 

76.3

 

20.02.2019

 

25

Balance work of widening to 2-lane and Improvement of Biharsharif (Telhara) - Jehanabad- Arwal (Kendui) Km 36.00 to

68.10 of NH-110

 

32.1

 

82.97

 

31.07.2019

26

Strengthening from 136 to 166 including replacement of 1 Minor Bridge in km 143 of NH-80

31

37.85

31.03.2021

 

27

Strengthening and widening to 2 lane with paved shoulder from km 112.00 to

136.440 (Gitawas-Raniganj JVC Canal) of NH-327E

 

24.385

 

100.44

 

07.01.2021

28

Strengthening work from km 0.00 to km

36.50 (Mehrauna UP Border to Siwan) of NH-227A on EPC

36.5

37.25

30.01.2021

29

HL RCC Minor Bridge (2x21m) in km 24 of NH-333 job no.

Bridge

4.43

27.06.2020

 

30

Construction of High level New RCC Bridge (5x11eff) in replacement of existing old narrow and damaged bridge no. 135/1 in km 135 of NH-327E

 

Bridge

 

5.95

 

15.07.2020

31

Strengthening and Raising of NH-19 (Chapra-Manjhi section) from km 129 to 135 & from km 139 to 143.

9.218

14.67

26.10.2020

 

32

Strengthening & Widening work of existing 2-lane to two lane with paved shoulder from 0.00 to 25.010 of NH- 327A

 

25.01

 

76.74

 

31.05.2020

 

33

Strengthening & Widening work of existing 2-lane to two lane with paved shoulder and geometric improvement from km 64.00 to 97.00 of NH-28B

 

29.6

 

243.1

 

24.06.2021

34

Strengthening work in Km 53.00 to 89.00 of NH-33(old NH-110) on EPC mode

35.609

28.85

03.05.2021

 

35

Widening & Strengthening of existing Single lane to Double lane carriageway in Km 0 to 40 of NH-104 in Bihar under EPC mode

 

40

 

186.84

 

29.02.2020

36

Strengthening from 194.01 to 227.11 of NH-327E

33.1

34.69

24.06.2020

37

Balance work of widening & strengthening from km 167 to km 180 of NH- 80 for the year 2016-17

13

21.37

31.05.2018

38

Widening to 2 lane with paved shoulder

19.04

90.32

02.11.2021

 

 

in km 0.00 to 19.04 of NH-81 on EPC Mode

 

 

 

39

Construction of 4-lane ROB of km 119 of NH-30 (L.C No 48-A/3T)

1.56

96.49

25.05.2021

 

 

40

Rehabilitation and upgrading to 2 lanes/ 2 lane with paved shoulders configuration of Fathua-Harnaut-Barh section (km 0.00 to km 69.00) of NH-30A in Bihar - One time Improvement of left out portion of Harnaut Bypass of NH-30A

 

 

3.12

 

 

2.1

 

 

27.09.2021

41

Strengthening work in Km 35.00 to 64(P) of NH-333A on EPC mode

29.25

24.4

16.06.2021

 

42

Strengthening work of NH 227A (Part) from Chakia (NH-28) to Lalachhapra chowk via Kesariya from km 118.040 to km 142.756 on EPC mode.

 

24.716

 

27.24

 

14.12.2021

43

Strengthening work in Km 35.00 to 64(P) of NH-333A on EPC mode

29.25

24.4

16.06.2021

 

44

Strengthening including improvement of geometrics work from km 104.20 to km 110 of NH-28B (New NH-727) on EPC

mode

 

5.8

 

16.6

 

31.03.2021

45

Construction of 4-lane ROB (L.C No SK/257C) of km 11 of NH-327E

ROB

79.7

31.07.2022

46

Strengthening from km 38.85 to 97.05 of NH-227A

56.75

64.97

21.03.2022

47

One time improvement of left out portion of ROB at km 12 of NH-103 and km 132 & 135 of NH-19 on item rate mode

4.95

3.95

27.09.2021

 

48

Widening and strengthening of existing road into 2 lane with paved shoulder from Pokhrauni Chowk to Junction with NH- 57 near Jhanjharpur (km 0.00 o 28.00) of NH-527A in the State of Bihar

 

26.3

 

98.84

 

30.09.2022

49

Strengthening and widening to 2 lane with paved shoulder from km 103.865 to

142.050 (Gaya-Goh) of NH-120

37.885

126.28

31.03.2022

50

Strengthening work in Km 38.84 to 59.00 Of NH-333 on EPC mode.

20.16

21.59

30.06.2021

51

Strengthening work in km 123.00 to

142.00 of NH-333A on EPC Mode

19

15.81

30.06.2021

52

Strengthening work in Km 75.25 to 91.00 of NH-333 on EPC Mode

15.75

21.9

31.03.2021

53

Strengthening of Road from km 91.00 to

115.00 of NH-333 on EPC mode

24

26.7

15.05.2021

 

54

Widening and strengthening from km

115.00    (Tola    Kurwa)    to               141.050 (Bishunpur) of NH-333

26.5

95.77

15.02.2022

55

Construction of RCC Minor bridge in km 02, km 14, km 40 and km 43 of NH-333

bridge

23.5

30.09.2022

 

56

Strengthening              work   from  Km                     0.00 (Paswan    chowk)                         to                 58.450

(Mushrigharari) of NH-103    on EPC Mode

 

55.5

 

64.3

 

30.04.2022

57

Reconstruction of damaged Bridge over river Tungi Bridge on NH-82 (H.L. RCC Bridge Km 38)

Bridge

19.3

19.08.2021

 

58

Strengthening including improvement of geometrics work from km 97 to km

104.20 of NH-28B (New NH-727 on EPC

mode

 

7.2

 

8.52

 

16.10.2020

59

Construction of 2-lane combined ROB in lieu of level crossing No-KK-12 of km 48 (Pranpur) of NH-81

1.48

48.5

21.09.2022

60

Construction of Major bridge over Bhangia River at km 86.936 of NH-327E & its approaches on EPC mode

0.34

14.01

30.01.2023

61

Widening to 2 lane with paved shoulder and strengthening from km 19.860 to

38.060 of NH-219 on EPC Mode

18.2

99.41

07.05.2022

62

Strengthening from Ch. 16.000 to 19.860 and Ch 38.060 to Ch 40.000 of NH-219 on EPC mode in the State of Bihar

5.8

19.6

01.08.2022

63

Strengthening work in Km 0.00 to 34.00 of NH-333A on EPC Mode.

34

27.58

30.11.2022

 

 

64

Rehabilitation of 4-lane 5.575 km long, 4- lane MG Setu over Ganga River on NH-

19 from km 212.72 to km 218.95 by dismantling the damaged pre stressed cantilever arms Superstructure and subsequent redecking by steel truss in Patna on EPC mode

 

 

5.575

 

 

1856.98

 

 

31.07.2022

 

 

 

65

Engineering, Procurement, and Construction of Rehabilitation and Upgrading to 2- lanes/2 - lane with Paved Shoulders                          Configuration                          and Strengthening of Fatuah-Harnaut-Barh Section (km 0 to km 69.6) of NH-30A in the State of Bihar under Phase-I of National Highways Inter-connectivity Improvement Projects (NHIIP)

 

 

 

71.8

 

 

 

812.6

 

 

 

31.05.2022

66

Widening & Strengthening to 2 lane with paved shoulder from Km 30.00 to 45.00 of NH-101 in the State of Bihar item rate

15

63.86

15.04.2022

 

67

Construction of 2-lane ROB in lieu of level crossing No-KK-4A of km 31 (Mania)of NH-81

ROB

47.95

20.01.2023

 

68

Widening  &  Strengthening  from  km

100.40 to km 107.80 (from Lakhanpur More to Faijullahpur) of NH-227A under EPC mode in the state of Bihar

 

7.4

 

22.69

 

30.05.2022

 

69

Strengthening & widening to 2 lane with paved shoulder from Km 0.00 to 14.50 of NH-101 for the year 2017-18 in the State of Bihar on item rate

 

13

 

53.09

 

15.12.2021

 

 

70

Construction of 03 Nos. New High Level RCC Minor Bridges (2*21.60m) in Km

62 (Chainage-61+247), (2*18.60m) in Km 62 (Chainage-61+650) & (2*18.60m) in Km 64 in Replacement of existing old Narrow and damaged Bridge of NH-110 on EPC mode in the State of Bihar

 

 

Bridge

 

 

15.42

 

 

31.03.2023

71

Strengthening & Widening from km 0.00 to 10.80 of NH-21

67.13

50.67

30.06.2022

72

Widening and strengthening from km

179.00 to 198.93 of NH-333A

52.4

40.28

31.03.2021

 

73

Construction of New High Level RCC major Bridge (13X31m)in place of old submersible damaged bridge in Km178 on NH-333A across River Chanan in the state of Bihar on EPC mode

 

0.503

 

42.94

 

24.11.2023

74

Construction of 2-lane ROB of km 46 (LC No KT2-2/B)of NH-131A (Katihar)

1.051

43.11

01.06.2023

 

75

Widening to 2 lane with paved shoulder and strengthening from km 45.00 to 65.00 (design length- 18.990) of NH-101 on EPC Mode

 

20

 

84.70

 

30.06.2022

 

 

76

Remaining work for Strengthening & Widening work of existing road into 2 lane with paved shoulder from Pokhrauni Chowk to Junction with NH 57 near Jhanjharpur (km 0.00 to 28.00) of NH - 527A in the State of Bihar.

 

 

0.57

 

 

25.1

 

 

31.12.2022

77

Strengthening and widening to 2 lane with paved shoulder from km 142.05 to 167 (Goh- Daudnagar) of NH-120

25.415

89.41

12.12.2022

78

Construction of road side covered drain in km 213 (P) to 215 (P) in Bihra Bazar of NH-327E on EPC Mode

0

4.24

17.09.2022

 

79

One time improvement of left out portion of NH-80 from km 119+885 (Dogachhi) to km 132+895 (Zero mile Bhagalpur) on EPC mode in the State of Bihar

 

13.01

 

12.03

 

06.10.2023

 

 

80

Widening to Two Lane with Paved shoulders including strengthening of existing pavement from km 0.00 to km 24.800 of NH-28B (New NH 727) on

EPC mode in the state of Bihar

 

24.8

 

74.83

 

22.09.2023

 

81

Widening to two lane with paved shoulders including strengthening of existing pavement from km 14.5 to km

30.00 of NH 101 (New NH 331) on EPC

mode in the state of Bihar

 

15.5

 

61.78

 

07.10.2023

82

Construction of 2-lane ROB of km 100 of NH-327E

1.8

62.26

31.12.2023

83

Construction of 4-lane ROB of km 12 of NH-103

2.11

123.23

31.03.2024

84

Construction of High level New RCC Bridge at km 81.00 of NH-327E on EPC Mode

0.48

10.93

31.05.2024

85

Construction of 2-lane ROB of km 132 of NH-19

2

77.38

26.08.2019

 

86

Balance work of construction of 3x 18m (eff. Span ) High level RCC Bridge across river Mani in Km 94 of NH-80 in the state of Bihar

 

0.41

 

7.73

 

05.03.2022

 

 

87

Construction of additional two lane with paved shoulder of NH-98 (New NH 139) from existing Ch 7.000 to Ch 17.840(Design  Ch  0.000  to  10.840)

[AllMS (Bhusaula Golambar ) to Naubatpur (Patna Ring Road ) section] on EPC mode

 

 

10.84

 

 

56.8

 

 

31.05.2024

 

88

Strengthening and widening to 2 lane with paved shoulder from km 181.465 to 201.665 of NH-120 Nasriganj - Vikramganj

 

20.2

 

74.90

 

31.03.2024

89

Construction of High Level R.C.C Major Bridge at Km. 38 (Bandhuganj) on N.H.- 110 in the State of Bihar

Bridge

18.41

31.08.2024

90

Construction of 2-lane ROB of km 135 of NH-19 (L.C No 62-A/3-E)

ROB

50.0

15.09.2024

91

Simaria (Km. 206.050) to Khagaria (Km. 266.282)

60.23

567

30.03.2023

92

Construction of approaches to Rail cum Road bridge across river Ganga near Munger ghat

14.52

293.16

30.09.2022

93

Bhojpur Buxar section of NH-84 from km.27.37 to km. 75.00

47.9

681.67

16.05.2023

94

Bakhtiyarpur-Rajauli  Pkg-II  from  km.

47.23

1065

27.04.2023

 

 

54.405 to km.101.630

 

 

 

95

Construction of 2nd flyover (LCW) in Kishanganj town starting from Km.472.300 to Km. 475.480 of NH-31

3.18

129.2

18.08.2023

96

Four lanning of Forbesganj to Jogbani section from Km. 0.000 to Km.9.258 (ICP jogbani) of NH-57A

9.26

247.36

31.07.2023

97

4L of Narenpur - Purnea Section of NH- 131A

49

1905

29.03.2024

98

4L of Galgalia - Bahadurganj section from Km 0.000 to Km 49.000 (Package-I) of NH327E

49

1051

06.04.2024

99

4 – lanning of Bahadurganj – Araria (Pkg-II)

45

1081.7

10.08.2024

100

2L with PS Piprakothi-Motihari-Raxaul NH-28A EPC

68.60

445.22

30.01.2024

101

4L Ara-Pararia section of NH - 319

54.53

700

31.01.2023

102

Kanhauli – Ramnagar of Patna Ring Road-pkg-I

39.16

797

31.05.2023

103

2l with paved shoulder of Chhapra- Gopalganj section of NH-85 from Km.0.000 to Km.93.500

94.258

644.27

09.07.2022

104

2L with PS Biharsharif – Barbigha – Mokama NH-82 (EPC)

54.76

297.27

28.02.2021

105

2LPS Chhapra - Rewaghat - Muzaffarpur section of NH - 722

73.07

427.06

17.01.2021

106

Forbesganj-Simrahi     CII-BR-3                                   (Km. 230.00 - Km. 190.00)

34.87

357

30.06.2016

107

2L with PS Mokama – Munger NH-80 on BOT (Annuity)

60.48

351.5

13.10.2018

108

2L with PS Khagaria – Purnea NH-31 on BOT (Annuity)

140

664

30.04.2018

 

ANNEXURE-IV

ANNEXURE-IV REFERRED TO IN REPLY TO PART (e) OF LOK SABHA UNSTARRED QUESTION NO. 4022 TO BE ANSWERED ON 19.12.2024 ASKED BY SHRI TARIQ ANWAR REGARDING NATIONAL HIGHWAYS IN BIHAR

Details of toll plaza-wise number of toll tenders which have been extended beyond their original period

 

 

Name of Toll Plaza

No of Extension of Original Contract Period during previous one year (excluding contractual extension) w.e.f Jan 2023

 

 

Babhaniyawan

1st time for 44 days (Original Contract Period 21.07.2023 to 21.10.2023) (Extended upto 05.12.2023)

2nd time for 80 days (Original Contract Period 23.01.2024 to 24.04.2024) (Extended upto 14.07.2024)

Kharik

1st Time for 14 days

2nd Time for 23 days

Maranga

1 time for 33 days

Kulhariya

1 time for 13 days

Saidpur

1 time for 09 days

Karigawan

1st time from May/2023 to 13-04-24 and 2nd tme 14-04-24 to till now

(Toll started in May/2023)

Runni

1 Time - for overstay period from 24.09.2024 (08:00:00) till

05.10.2024 (07:59:59).

Maithi

1st Time - for EOT approved period in case of FMC due to Covid & Demonitization from 19.07.2024 (00:00:00 Hrs.) till 13.10.2024

(21:24:00 Hrs.).

Raje

Asanpur

Hariabara

Saukala

M/s Eagle Infra India Ltd. [Original Contract period from 21.03.2022

(08:00 Hrs) to 21.03.2024 (08:00 Hrs)]. Extended for one month from 21.03.2024 (08:00 Hrs.) to 20.04.2024 (08:00 Hrs.)

Phulwaria

one time for 30 days (Original contract period 26.08.2024 to

26.11.2024)

Bishunpurwa

one time for 15 days (Original contract period 11.07.2023 to

11.07.2024)

Bishunpurwa

one time for 90 days (Original contract period 11.04.2022 to

11.04.2023)

Thawe

one time for 3 days (Original contract period 19.06.2023 to

19.06.2024

Sonho

one time for 71 days (Original contract period 30.07.2023 to

30.07.2024)

Chainwa

one time for 119 days (Original contract period 05.04.2022 to

05.04.2023)

Pokhraira

one time for 120 days (Original contract period 22.07.2023 to

22.07.2024)

Balgudar

two times, (original contract period from 06.06.2022 to 10.06.2023, extended upto 24.10.2023) & (Original contract period from 16.04.2024 to 15.07.2024, extended up-to 15.10.2024)

Bhagalpur

one time for 4 days, (Original contract period from 27.08.2022 to

27.08.2023, extended up-to 01.09.2023)

This information was given by the The Union Minister of Road Transport & Highways, Shri Nitin Gadkari in a written reply in Lok Sabha today.


***