Ministry of Commerce & Industry

Eight projects under National Industrial Corridor Development and Implementation Trust (NICDIT) sanctioned and approved by Government

Posted On: 08 FEB 2023 5:38PM by PIB Delhi

Eight (8) projects under National Industrial Corridor Development and Implementation Trust (NICDIT) have been sanctioned and approved by Government. Out of eight Projects for four projects, namely, Dholera Special Investment Region in Gujarat, Shendra Bidkin Industrial Area in Maharashtra, Integrated Industrial Township in Greater Noida, Uttar Pradesh & Integrated Industrial Township – Vikram Udyogpuri in Madhya Pradesh, the major trunk infrastructure works have been completed, the Minister of State for Commerce and Industry, Shri Som Parkash said in reply to a parliamentary question today.

The land allotment has started to industries and other users through the Special Purpose Vehicles (SPVs) formed with respective State Governments. A Total of 229 plots measuring nearly 1,601 acres have been allotted to companies with an investment of more than Rs. 18,691 crore in these 04 greenfield smart industrial regions/nodes/areas. Apart from the above-allotted plots, approx. 4,900 acres of developed land parcels are available for immediate allotment across multiple uses.

The other 04 approved projects are in various stages of implementation/development. The status of these projects is given as below:

    1. Tumakuru Node in Karnataka under Chennai Bengaluru Industrial Corridor (CBIC) – EPC contractor for the construction of trunk infrastructure has been appointed. Detailed master planning and preliminary engineering activities for an area of 1,736 acres as  an activation area have been completed. Environment Clearance has been obtained. State Govt. has transferred 1668.30-acre land to the SPV of the project. The Hon’ble Prime Minister laid the foundation stone on February 06, 2023.
    1. Krishnapatnam Node in  Andhra  Pradesh  under  CBIC  – Detailed Master Planning and Preliminary Design & Engineering of the total project area of 12,798 Acre has been completed, out of which an area of 2,500 Acres has been identified as Phase-1 area. The State Govt. has transferred 2139.15 acres to the project SPV. Environment Clearance has been obtained.
    1. Integrated Multi Modal Logistics Hub at Nangal Chaudhary in Haryana under Delhi Mumbai Industrial Corridor (DMIC) – Works related to water, power, and roads are almost completed. Rail connectivity works approved by DFCCIL have been started.
    1. Multi-Modal Logistics/Transport  Hub  at  Dadri  in  Uttar Pradesh under DMIC– 227.48 Ha land has been transferred to the SPV of the project. Project development activities like preparation and approval of Detailed Project Reports (DPR) have been started.

       The details of fund allocated to these projects is given below:

Sl.

no.

 

Corridor

 

 

Name of Projects sanctioned

Funds released           to SPVs (in Rs. crore) upto

31.01.2023

 

 

 

 

 

 

 

 

1.

 

 

 

 

 

 

DMIC: Delhi Mumbai Industrial Corridor

Dholera Special Investment Region

(DSIR), Gujarat

Equity – 2784.83

Shendra Bidkin Industrial Area

(SBIA),Maharashtra

Equity – 3000.00

 

Integrated Industrial Township – Greater Noida (IIT-GN), Uttar

Pradesh

Equity – 617.20

Integrated Industrial Township – Vikram Udyogpuri (IIT-VUL),

Madhya Pradesh

Equity – 55.93

Debt – 260.54

Integrated Multi-Modal Logistics

Hub – Nangal Chaudhary, Haryana

Equity – 208.05

Debt – 100.00

Multi Modal Logistics Hub & Multi

Modal Transport Hub (MMLH & MMTH), Uttar Pradesh

Equity – 853.05

2.

CBIC,Chennai Bengaluru

 Industrial

Corridor

Krishnapatnam Industrial Area,

Andhra Pradesh

Equity – 533.86

Tumakuru Industrial Area, Karnataka

Equity – 586.74

***

AD/MS/KP



(Release ID: 1897398) Visitor Counter : 4403