19 MAR 2018 5:38PM by PIB Bengaluru
Programme - Karnataka
Sagarmala Programme - Karnataka
- In Karnataka, 48 projects planned (Rs. 24,772 Cr)
- Port Modernization (24 projects, Rs. 6,795 Cr); Port Connectivity (16, Rs. 9,969 Cr), Port-led Industrialization (2, Rs. 7,520 Cr), Coastal Community Development (6, Rs. 488 Cr)
- 3 projects completed (Rs 135 cr.), 8 under implementation (Rs 1,735 cr.), 7 DPRs prepared to be implemented shortly (Rs 764 cr.), 9 Projects DPR under preparation (Rs 4,951 cr.)
Port Modernization
- 8port capacity expansion projects (cost: Rs. 3,039 Cr) identified to add 300 lakh ton capacity at NMPTby 2025:
- New major port planned at Belikeri – TEFR Prepared
- 6 projects (Rs. 454 Cr) under Coastal Berth Scheme.
#
|
Project Name
|
Project Cost
(Rs. Cr)
|
1
|
Extension of Southern breakwater by 145m and construction of 1,160 m northern break-water at Karwar Port
|
224
|
2
|
coastal cargo berth at Old Mangaluru Port
|
65
|
3
|
Coastal cargo berth of 250 m at Karwar Port
|
61
|
4
|
Capital dredging at Karwar Port
|
50
|
5
|
Capital Dredging at Old Port Mangalore (Bengre Side)
|
29
|
6
|
Coastal cargo berth at Malpe Port
|
25
|
Port Connectivity
- 7Road projects(Rs. 6,094 Cr and 781 Km)- 1 project under implementation Rs 1,200 cr
- 6rail connectivity projects (Rs. 3,075 Cr and 238 Km)- DPR under preparartion for 1 project- Rs 2,315 cr.
- 3 National Waterway projects (Rs. 800 Cr, 111 Km) planned in Karnataka.
Sr. No.
|
National Waterway
|
Length (Km)
|
Cost (Rs. Cr)
|
Status
|
1
|
NW43 Netravathi river
|
10
|
100
|
DPR under Preparation
|
2
|
NW74 (Bengre to Netravathi Dam, Dharmsthala on Netravathi river)
|
78
|
500
|
DPR under Preparation
|
3
|
NW51 on Kabini river
|
23
|
200
|
DPR under Preparation
|
Total
|
111
|
800
|
|
Port-led Industrialization
- 1Coastal Economic Zones (CEZs) – Perspective Plan Prepared.
Project Name
|
Project Cost
(Rs. Cr)
|
Project Status
|
CEZ in Dakshin Kannada
|
3,000
|
Perspective plan prepared
|
- 1Industrial clusters(Rs. 4,520 Cr)
#
|
Type of Cluster
|
Project Name
|
Project Cost
(Rs. Cr)
|
Implementing agency
|
Project Status
|
1
|
Petrochemical
|
Petrochemical cluster in Mangalore
|
4,520
|
Ministry of Chemicals & Fertilizers
|
DPR to be Prepared
|
|
|
|
|
|
|
|
|
|
Coastal Community Development
- Skill development: Action plan prepared for 3 coastal districts (Dakshin Kannada, Udupi and Uttar Kannada); Rs. 1.52 Cr sanctioned and Rs. 0.76 Cr released for DDU-GYK Scheme
- 4Fishing Harbor projects(Rs. 391 Cr); 2 projects sanctioned and 4 under consideration
Project Name
|
Project Cost
(Rs. Cr)
|
Project Status
|
Kulai
|
197
|
DPR Prepared
|
HejmaadiKodiHarbour in Udupi
|
139
|
DPR Prepared
|
expansion of fishing harbour of Malpe in Udupi
|
37
|
Completed
|
Amadalli in Uttara Kannada
|
19
|
Under Implementation
|
Important Projects
#
|
Project Name
|
Status
|
Cost
(Rs. Cr)
|
Port Modernization
|
1
|
New port at Belekeri
|
DPR to be Prepared
|
2,783
|
2
|
Deepening of Eastern dock at NMPT
|
DPR to be Prepared
|
1,200
|
3
|
Development of Berth 16 for bulk cargo
|
DPR to be Prepared
|
500
|
4
|
Development of Berth 17 for bulk cargo
|
DPR to be Prepared
|
500
|
5
|
Mechanization of Berth 18
|
Under Implementation
|
470
|
6
|
Utilization of Berth 14 and Backup area as Container Terminal
|
DPR to be Prepared
|
200
|
7
|
Additional Storage area for bulk cargo
|
DPR to be Prepared
|
50
|
8
|
Development of 30 acres of stack yard and ancillary roads for parking of Ro-Ro cargoes and cars
|
Under Implementation
|
25
|
LIGHTHOUSES for DEVELOPMENT –KARNATAKA
- BHATKAL
- SURATKAL POINT
- KAP
- OYSTER ROCKS
Belgaum
Name of the work
|
Length (km)
|
cost
|
Importance of the Project
|
Four laning of Belgaum-Khanapur section of NH 4 A on Hybrid Annuity Mode (Package-I)
|
30 Km
|
856.20 Crores
|
( Belgaum-9 Km
Khanapur-4.85 Km)
- Major Bridges-1
- ROBs/RUBs -2
- VUP/LVUP-16
- Toll Plazas-1
|
Two laning with paved shoulder and two laning without paved shoulder (14km) from Km 70+800 to Karnataka/Goa Border of NH-4A
|
52.3 km
|
486.78 Crores
|
- Major Bridges-1
- ROBs/RUBs -3
- VUP/LVUP-3
- Toll Plazas-1
|
Kagwad
Name of the work
|
Length (km)
|
cost
|
Date of Completion
|
Importance of the Project
|
Construction to two lane with paved shoulder of Vijayapur - Sankeshwar section of SH-12 (in principle approved NH) in Karnataka on EPC mode (Package-I)
|
39.895 Km
|
260.44 Crores
|
October, 2019
|
This stretch connects Vijayapur to Sankeswar and thereby reduces decongestion and ensures free flow of traffic.
- Major Bridges -1
- Culverts -29
- Major Intersections-2
- Minor Intersections-9
|
Construction to two lane with paved shoulder of Vijayapur - Sankeshwar section of SH-12 (in principle approved NH) on EPC mode (Package-II)
|
39.777 km
|
271.06 Crores
|
October, 2019
|
This stretch connects Vijayapur to Sankeswar and thereby reduces decongestion and ensures free flow of traffic.
- Major Bridges -2
- Minor Bridges-3
- Culverts -30
- Major Intersections-4
- Minor Intersections-15
|
|
Up to 2014
|
2014-2017
|
Total
|
Declared
|
6760 Km
|
372Km
|
7132 Km
|
In principally declared
|
-
|
6433 Km
|
6433 Km
|
Total
|
|
6805 Km
|
13565 Km
|
Projects
|
No. of Projects
|
Length
|
Cost
|
Ongoing
|
105
|
2795 Km
|
19,638 Cr
|
likely to be awarded
|
19
|
230km
|
1676cr.
|
Annual Plan (2017-18)
|
|
435km
|
1229 cr
|
DPR
|
34
|
3000 Km
|
20,000 Cr
|
Tender
|
34
|
4000 Km
|
25,000Cr
|
CRF
|
462
|
|
5,728 Cr.
|
Future Investment:
- We shall invest approximately an amount of Rs 1,44,922 cr in the State in the next two years.
- Investments to be done in the State of Karnataka in coming years
Sl.No
|
Project
|
Length
|
Cost
|
1
|
Widening of declared 73 NHwith 2lane+paved shoulders/4 lane
|
6,433km
|
38,598 Cr
|
2
|
41 nos of works under Bharatmala program
|
3,726km
|
85,000 Cr
|
3
|
99 no’sworks under progress
|
2,597 km
|
19,421 Cr
|
4
|
25 no’s works to be awarded
|
408 km
|
1,903 Cr
|
|
Total
|
|
1,44,922 Cr
|
Important Projects:
Bangalore Ring Road (STRR)
- NHAI has taken up the work of Balance portion of STRR for Bangalore (West side) to Hosur in Tamil Nadu (connecting NH-4 to NH-7) under Bharatmala.
- This Ring road stretch connecting through Hosur, Anekal, Kanakapura, Ramanagara, Magadi, Dobaspet.
- The total length of this ring road is about 140 km in Karnataka State and 45 km in Tamil Nadu with a tentative cost of Rs. 10,000 crores.
Shiradi Ghat Tunnel:
- The work of construction of Tunnel for Shiradi Ghat for a length of 23.60 km with a tentative cost of Rs. 10,000 crores.
- The project consists of 6 No. of tunnels with a total length of 12.60 kms.
- The tunnel also connects with bridges having a longest bridge of 1.50 km with highest peer of 100 mtr.
- The tunnel consists of 2 driving lane with one emergency lane for each tube i.e. 10.50 m carriage way width
Ring Road to Belgaum:
- The construction of 4/6 laning of Belgaum bypass on Western side with eastern side by connecting NH-4A to NH-4 having a total length of 55 km.
- The tentative cost for this bypass will be around Rs. 1500 crores.
- This bypass will ease the traffic congestion and to facilitate the through traffic in the city,
Six laning of Access Control of Bangalore – Mysore Section:
- This project is a part of economic corridor of Bangalore – Mallapuram.
- Total length of 117 kms with an estimated cost of Rs. 7000 crores
- This project is consists of about 8 km elevated corridors, 9 major bridges and 4 ROBs.
- The entire project has been provided with Access Controlled Service Road.
- DPR has already been completed and bids have been received and are under evaluation.
Brief of Chennai- Bangalore Expressway:
- Bangalore – Chennai Expressway is on a new alignment which will connected Bangalore with Chennai which is an import/export hub due to existence of sea port.
- This project is identified as one of the priority projects under Chennai – Bangalore Industrial Corridor (CBIC).
- It will provide connectivity to the proposed Multimodal Logistic Park at Dobaspet which can be accessed through NH-207 or Bangalore Ring Road from BCE.
- This expressway passes through three states namely 76 kms inKarnataka, 91 kms in Andhra Pradesh &94 km inTamil Nadu with a tentative cost of Rs. 16,000 crores.
- Land acquisition is in advance stage in Karnataka State.
Amaravati – Bengaluru section:
- The connectivity between Bangalore with Amaravathi is two routes via Ananthapuramu and via Tirupathi.
- Bengaluru to Amaravathi via Ananthapuramu passess through NH-7 has already completed with 4 lane Elevated Highway of 4.50 km enroute to Bengaluru International Airport (BIA).
- The road from Bangalore to Amaravathi via Tirupathi passess through NH-4 has already been completed 4/6 lane (Bangalore – Kolar – Mulbagal –KNT/AP border).
Hyderabad – Bangalore section:
- The connectivity between two Capital Cities i.e. Bangalore capital of Karnataka with Hyderabad capital of Telangana via Ananthapuramu through NH-7 has already been developed with 4 lane Elevated Highway of 4.50 km enroute to Bengaluru International Airport (BIA).
Bharat Mala Project details:
- 41 nos of works aggregating to 3,726Km amounting to Rs. 85,000 Cr are approved under Bharat Mala Programme.
- 13nos of projects for a length of 1,435Km amounting to Rs.20,000Cr is under implementation.
- 12nos of projects for a length of 645Km amounting to Rs.15,000 Cr is under bidding stage.
- 16nos of projects for a length of 1646Km amounting to Rs.50,000Cr is under DPR stage.
Sethu Bharatam Project Details:
- 07 ROBs aggregating to Rs.473Cr are under tendering.
- Out of 7 Nos, 1 No. of ROB included under the 4 laning of Ballari – Hiriyur section under Bharatmala Pariyojana is being implemented.
(Release ID: 1525165)
|