Funds allocated for Dimapur-Kohima Highway

Posted On: 02 JAN 2018 6:49PM by PIB Delhi

 

The Minister of State for Road Transport & Highways, Shipping and C&F Shri Mansukh L Mandaviya while answering a question in Rajya Sabha today informed that the entire four lane highway between Dimapur-Kohima is divided into 3 packages. Package-wise fund allocation for this highway is as under:

 

 

Pkg.-1

(from 123.840 Km to 138.775 Km)

Pkg.-2

(from 138.775 Km to 152.490 Km)

Pkg.-3

(from 152.490 Km to 166.700 Km)

Total Sanction Cost package wise (₹ in Cr.)

489.01

519.72

562.98

Total (₹ in Cr.)

1571.71

         

       He said that the fund utilization details (till date) is as follows:

 

 

Pkg.-1

(from 123.840 Km to 138.775 Km)

Pkg.-2

(from 138.775 Km to 152.490 Km)

Pkg.-3

(from 152.490 Km to 166.700 Km)

Fund Utilization in Civil work

(₹ in Cr.)

59.79

86.57

8.17

Fund Utilization in Authority Engineer

(₹ in Cr.)

2.99

Fund Utilization Land Acquisition & Utility Shifting

(₹ in Cr.)

27.80

Total     

(₹ in Cr.)

185.32

 

He also informed that the timeline set to finish the highway construction as per contract agreement is as under-

 

 

Pkg.-1

(from 123.840 Km to 138.775 Km)

Pkg.-2

(from 138.775 Km to 152.490 Km)

Pkg.-3

(from 152.490 Km to 166.700 Km)

Timeline to finish construction

16.09.2019

02.08.2019

08.08.2019

 

*****