Ministry of Road Transport & Highways
Funds allocated for Dimapur-Kohima Highway
Posted On:
02 JAN 2018 6:49PM by PIB Delhi
The Minister of State for Road Transport & Highways, Shipping and C&F Shri Mansukh L Mandaviya while answering a question in Rajya Sabha today informed that the entire four lane highway between Dimapur-Kohima is divided into 3 packages. Package-wise fund allocation for this highway is as under:
|
Pkg.-1
(from 123.840 Km to 138.775 Km)
|
Pkg.-2
(from 138.775 Km to 152.490 Km)
|
Pkg.-3
(from 152.490 Km to 166.700 Km)
|
Total Sanction Cost package wise (₹ in Cr.)
|
489.01
|
519.72
|
562.98
|
Total (₹ in Cr.)
|
1571.71
|
He said that the fund utilization details (till date) is as follows:
|
Pkg.-1
(from 123.840 Km to 138.775 Km)
|
Pkg.-2
(from 138.775 Km to 152.490 Km)
|
Pkg.-3
(from 152.490 Km to 166.700 Km)
|
Fund Utilization in Civil work
(₹ in Cr.)
|
59.79
|
86.57
|
8.17
|
Fund Utilization in Authority Engineer
(₹ in Cr.)
|
2.99
|
Fund Utilization Land Acquisition & Utility Shifting
(₹ in Cr.)
|
27.80
|
Total
(₹ in Cr.)
|
185.32
|
He also informed that the timeline set to finish the highway construction as per contract agreement is as under-
|
Pkg.-1
(from 123.840 Km to 138.775 Km)
|
Pkg.-2
(from 138.775 Km to 152.490 Km)
|
Pkg.-3
(from 152.490 Km to 166.700 Km)
|
Timeline to finish construction
|
16.09.2019
|
02.08.2019
|
08.08.2019
|
*****
NP/MS
(Release ID: 1515097)