1. Commencement
of work of Hotgi-Kudgi-Gadag Doubling.
2. Commencement
of work of Gadag-Wadi New Line.
3. Dedication
to the Nation-Doubling of Tinaighat-Londa-Shivthan Section in Hospet-Tinaighat-Vasco
Doubling.
4. Dedication
to the Nation-Doubling of Banapur-Koppal in Hospet-tinaighat-Vasco Doubling.
5. Construction
of new station building & extension of platform shelter at Chikkodi Road
station.
6. Extension
of platform shelter at Rayabag station.
7. Provision
of Platform shelter on Platform no. 2 at Gadag station.
8. Construction
of new Platform 2 & 3 at Koppal station.
9. VIP
Lounge at Shivamogga Town station.
10. 500
Kwp Solar Roof Top System at Mysuru Work Shop.
11. Provision
of water conservation & recycling plant at Mysuru station.
12. Dedication
of Foot Over Bridge at Holenarasipura station.
13. New
DEMU Service between Baiyappanahalli-Whitefild-Baiyappanahalli.
14. Commencement
of work of ROB at LC 438 at Rayabag.
15. Laying
of foundation stone for Bye-pass lines at Wadi.
16. Commissioning
of Rail Bogie Karkhana, Yadgir (RVNL).
17. Laying
of foundation stone for doubling between Nethravathi and Mangalore Central
stations (at Mangalore Central Railway Station).
18. Laying
of foundation stone for new FOB at Mangalore Central station (at Mangalore
Central Railway Station).
Minister
of State for Railways Shri Rajen Gohain was specially present to grace
the occasion. Member Engineering, Railway Board, Shri Aditya Kumar Mittal,
other Railway Board Members and senior officials were also be present on the
occasion.
Speaking on the occasion, Minister of Railways Shri Suresh
Prabhakar Prabhu said, “Karnataka is an important state for Indian Railways, we
have allocated highest ever funds in the Budget for developing Railway
Infrastructure in Karnataka. Indian Railways have formed JV with the State
Government of Karnataka. Indian Railways is in transformation mode, Indian
Railways have been focusing on improving Rail Infrastructure & passenger
amenities like never before. Cleanliness & Make in India programmes have
been successfully implemented in Indian Railways. High Speed Railway network is
being worked upon Indian Railways. Soon, Indian Railways is working on the
project to operate trains at 200 Kmph on trunk routes like Delhi- Mumbai,
Delhi- Kolkata.
Salient Features of Projects
launched today
1.
Commencement of work of Hotgi-Kudgi-Gadag Doubling.
● At
present, Hotgi-Kudgi-Gadag route is a single line rail link between
Guntakal-Pune-Mumbai and Hospet-Hubli-Goa rail routes.
● A
number of Integrated Steel Plants/Power Plants/Cement Plants are coming up
along the Hotgi-Kudgi-Gadag route. This doubling work will provide the
necessary line capacity for introduction of additional trains and smooth
movement of rakes to/from the industries/power plants.
● Part
length for this Doubling project, i.e. from Hotgi-Kudgi (134 km) has been taken
up under “Customer Funding Model” with National Thermal Power Corporation
Limited (NTPC). NTPC is setting up the Thermal Plant at Kudgi station of 4000
MW capacity.
2.
Commencement of work of Gadag-Wadi New Line.
● The
new rail line would provide a direct shorter route for the people of the area
in Gadag, Koppal, Raichur and Gulbarga areas of Karnataka.
● Proposed
route will shorten the distance between Gadag and Secunderabad by 150 km.
● Project
is 50:50 Cost Sharing basis with Government of Karnataka (GoK) and land free of
cost by GoK.
3.
Dedication to the Nation-Doubling of Tinaighat-Londa-Shivthan &
Banapur-Koppal of Hospet-tinaighat-Vasco Doubling.
● The
Railway line passes through Bellary, Koppal, Gadag, Dharwad, Belgaum and Uttara
Kannada districts of Karnataka State. Bellary-Hospet region in Karnataka is the
heart of Iron ore industry in the country. Iron ore from this region is
transported to Chennai and Goa ports for export.
● The
doubling of railway track is also necessary to move imported coal from Marmagao
Port to the Steel industries and upcoming Thermal Power Plants in Jevargi In
Gulbarga District, Thermal Expansion Phase-2 in Bellary Dist. in North
Karnataka.
● In
this Project, 28.75 km doublings have been commissioned and being dedicated to
Nation.
4.
Construction of new station building & extension of platform shelter at
Chikkodi Road station.
● A
new station building with built up area of 275 Sq. Meter has been constructed
at Chikkoddi Road Station. Improvement to circulating area is done by providing
paver blocks for area of 500 Sq.M. to improve the aesthetics of this station.
● For
convenience of passengers, platform at Chikkodi Road railway station has been
extended by 320 meter with cement concrete flooring. New platform shelter has
been provided for a length of 64 meter with seating arrangements. Above
amenities towards improvements of Chikkodi Road Station were taken up at a cost
of Rs. 15 Lakhs
5.
Extension of platform shelter at Rayabag station.
6.
Provision of Platform shelter on Platform no. 2 at Gadag station.
7.
Construction of new Platform 2 & 3 at Koppal station.
● Along
with the doubling of Hosapete- Tinaighat railway line, Koppal railway station
was provided with an additional platform No. 2/3.
● This
is a high level island platform having length of 540 meters which has been
constructed within a time span of 2 months, and at a cost of Rs.60 lakhs.
8.
VIP Lounge at Shivamogga Town station.
● Shivamogga
town is an important A category station of Mysore Division which attracts large
number of tourists in the Malnad area of Karnataka. This station has been
further upgraded by providing majestic VIP lounge. The VIP lounge is provided
with proper ambience with granite flooring and cladding, air-conditioned
seating arrangement with Sofa set, Luggage rack and improved bath-cum toilet
facilities with hot and cold water. This facility to a great extent will grant
better waiting experience to the travelling passengers visiting Shivamogga
station.
9.
500 Kwp Solar Roof Top System at Mysuru Work Shop.
10.
Provision of water conservation & recycling plant at Mysuru station.
● The
water consumption at Mysuru junction is quite high. The demand of water is
being arranged through Municipal Corporation with hefty payment to the tune of
Rs.18.00 Lakhs per month (Rs 2.16 crores per annum).
● It
is proposed to set up one water Recycling Plant of 4.00lakh liters capacity
for using recycled water, which will have environmental benefit as well as
economy by bringing down the reduction in the water bills.
11.
Dedication of Foot Over Bridge at Holenarasipura station.
● Holenarasipura
is important D category station of Mysuru Division which is a famous for an
important ancient Narasimha Temple dedicated to Lord Narasimha and river Hemavati,
one of the many tributaries of the Kaveri.
● Being
the important tourist destination, the station was identified for upgradation
as Adarsh station during year 2015-16. The important Passenger Amenity works to
the tune of Rs.2.85 crores are added to upgrade the station as per norms of
Adarsh station.
● The
work has been completed in stages and foot over bridge has been completed in
the month July-17. After commissioning of foot over bridge at Holenarasipura,
will have all required facilities as per Adarsh station norms.
12.
New DEMU Service between Baiyappanahalli-Whitefild-Baiyappanahalli.
13.
Commencement of work of ROB at LC 438 at Rayabag.
14.
Laying of foundation stone for Bye-pass lines at Wadi.
●
Wadi station is strategically located
at the junction of 3 Divisions –Sholapur, Guntakal & SC Division . Though
bye-pass exists towards Secunderabad(SC) from Guntkal(GTL), yet, heavy
detentions occur due to interlocking arrangements and large no. of cross
movements.
●
The proposed Bye-pass between Wadi and
Nalwar reduces the distance by about 12 Kms and is the most effective option to
decongest Wadi Yard besides avoiding cascading detentions at adjoining
stations.
15.
Commissioning of Rail Bogie Karkhana, Yadgir (RVNL).
16.
Laying of foundation stone for doubling between Nethravathi and Mangalore
Central stations (at Mangalore Central Railway Station).
● The
doubling of this section will facilitate running of additional mail/Express
trains from MAQ, since MAQ is an important feeder Coaching terminal to Konkan
Railway, Mysore/Bangalore directions and to the Entire State of Kerala and
Tamilnadu.
17.
Laying of foundation stone for new FOB at Mangalore Central station (at
Mangalore Central Railway Station).
*****
AKS/MKV/ENS