Crude Oil
1. Crude oil production during June, 2017 was 2984.50 TMT which is 2.13% lower than target but 0.60% higher when compared with June 2016. Cumulative crude oil production during April-June, 2017 was 9022.37 TMT which is 1.49% lower than target for the period but 0.24% higher than production during corresponding period of last year. Unit-wise and state-wise crude oil production is given at Annexure-I. Unit-wise crude oil production for the month of June, 2017 and cumulatively for the period April-June, 2017 vis-à-vis same period of last year has been shown in Table-1 and month-wise in Figure-1.
Table-1: Crude Oil Production (in TMT)
Oil Company
|
Target
|
June (Month)
|
April-June (Cumulative)
|
2017-18 (Apr-Mar)
|
2017-18
|
2016-17
|
% over last year
|
2017-18
|
2016-17
|
% over last year
|
Target
|
Prod.*
|
Prod.
|
Target
|
Prod.*
|
Prod.
|
ONGC
|
23071.00
|
1891.49
|
1859.48
|
1803.06
|
103.13
|
5652.99
|
5640.77
|
5492.14
|
102.71
|
OIL
|
3734.00
|
284.47
|
278.71
|
265.37
|
105.03
|
856.22
|
839.86
|
798.18
|
105.22
|
PSC Fields
|
10562.00
|
873.55
|
846.32
|
898.19
|
94.22
|
2649.78
|
2541.74
|
2710.69
|
93.77
|
Total
|
37367.00
|
3049.51
|
2984.50
|
2966.61
|
100.60
|
9158.99
|
9022.37
|
9001.01
|
100.24
|
Note: Totals may not tally due to rounding off. *: Provisional
Figure-1: Monthly Crude Oil Production
Unit-wise production details with reasons for shortfall have been given in following sub-sections:
1.1 Crude oil production by ONGC during June, 2017 was 1859.48 TMT which is 1.69% lower than the monthly target but 3.13% higher when compared with June, 2016. Cumulative crude oil production by ONGC during April-June, 2017 was 5640.77 TMT which is 0.22% lower than target for the period but 2.71% higher than production during corresponding period of last year. Reasons for shortfall in production are as under:
Ø Offshore: Natural decline/increase in water cut from matured fields of Western Offshore and repair job of sub-sea lines.
Ø Onshore: GEB power shutdowns / electrical faults due to heavy rain / flood in Mehsana and pressure decline & increase in water cut in Gandhar field affected Ankleshwar production
1.2 Crude oil production by OIL during June, 2017 was 278.71 TMT which is 2.03% lower than monthly target but 5.03% higher than production in June, 2016. Cumulative crude oil production by OIL during April-June, 2017 was 839.86 TMT which is 1.91% lower than target for the period but 5.22% higher than production during corresponding period of last year. Reasons for shortfall in production are as under:
Ø Less than planned achievement due to higher decline in production potential of wells mainly in Greater Hapjan and Greater Chandmari areas.
Ø Less than planned contribution from work over wells.
1.3 Crude oil production by Pvt/JVs during June, 2017 was 846.32 TMT which is 3.12% lower than the monthly target and 5.78% lower than June, 2016. Cumulative crude oil production by Pvt/JVs during April-June, 2017 was 2541.74 TMT which is 4.08% lower than target for the period and 6.23% lower than the production during corresponding period of last year. Reasons for shortfall in production are as under:
Ø RJ-ON-90/1 (CIL): Around 100 wells are closed either due to high water cut or require WOJ and poor reservoir performance of Bhagyam. Power fluid pumps maintenance job ongoing in Mangala.
Ø Panna-Mukta (BG): Closure of certain wells in June 2017 owing to well integrity issues and natural decline.
Ø CY-ONN-2002/2 (ONGC): Test production from 5 oil wells. PML not yet granted.
Ø CB-ONN-2004/2 (ONGC): Underperformance of wells
Natural Gas
2 Natural gas production during June, 2017 was 2755.48 MMSCM which is 2.75% lower than the target for the month but 6.05% higher when compared with June, 2016. Cumulative natural gas production during April-June, 2017 was 8057.72 MMSCM which is 5.55% lower than target for the period but 4.04% higher than the production during corresponding period of last year. Unit-wise and state-wise natural gas production is given at Annexure-II. Unit-wise natural gas production for the month of June, 2017 and cumulatively for the period April-June, 2017 vis-à-vis same period of last year has been shown in Table-2 and month-wise in Figure-2.
Table-2: Natural Gas Production (MMSCM)
Oil Company
|
Target
|
June (Month)
|
April-June (Cumulative)
|
2017-18 (Apr-Mar)
|
2017-18
|
2016-17
|
% over last year
|
2017-18
|
2016-17
|
% over last year
|
Target
|
Prod.*
|
Prod.
|
Target
|
Prod.*
|
Prod.
|
ONGC
|
24208.00
|
1943.53
|
1974.47
|
1748.60
|
112.92
|
5840.95
|
5728.81
|
5172.40
|
110.76
|
OIL
|
3000.00
|
241.45
|
237.36
|
241.25
|
98.39
|
725.26
|
723.52
|
730.71
|
99.02
|
PSC Fields
|
8034.00
|
648.33
|
543.65
|
608.55
|
89.33
|
1964.71
|
1605.39
|
1841.54
|
87.18
|
Total
|
35242.00
|
2833.32
|
2755.48
|
2598.40
|
106.05
|
8530.92
|
8057.72
|
7744.65
|
104.04
|
Note: Totals may not tally due to rounding off. *: Provisional
Figure-2: Monthly Natural Gas Production
2.1 Natural gas production by ONGC during June, 2017 was 1974.47 MMSCM which is 1.59% higher than the monthly target and 12.92% higher when compared with June, 2016. Cumulative natural gas production by ONGC during April-June, 2017 was 5728.81 MMSCM which is 1.92% lower than the cumulative target but 10.76% higher than the production during the corresponding period of the last year.
2.2 Natural gas production by OIL during June, 2017 was 237.36 MMSCM which is 1.70% lower than the monthly target and 1.61% lower than June, 2016. Cumulative natural gas production by OIL during April-June, 2017 was 723.52 MMSCM which is 0.24% lower than the cumulative target and 0.98% lower than the production during the corresponding period of last year. The major reason for shortfall in production was unplanned shutdown in BVFCL, Namrup Plant –Unit-III.
2.3 Natural gas production by Pvt/JVs during June, 2017 was 543.65 MMSCM which is 16.15% lower than the monthly target and 10.67% lower when compared with June, 2016. Cumulative natural gas production by Pvt/JVs during April-June, 2017 was 1605.39 MMSCM which is 18.29% lower than the cumulative target and 12.82% lower than the production during the corresponding period of last year. Reasons for shortfall in production are as under:
Ø Sohagpur West (RIL): Underperformance of CBM wells. Production restrained due to maximum CBM intake limited by IFFCO to 1,80,000 SCMD at GAIL’s Phulpur terminal
Ø Raniganj East (Essar): Few wells closed for planned maintenance and refrac jobs
Ø AAP-ON-94/1 (HOEC): Production deferred due to delay in grant of PML.
Ø Closure of 2 wells in D1D3 field and 1 well in MA field in KG-DWN-98/3 (RIL).
Ø RJ-ON-90/1 (CIL): Around 100 wells are closed either due to high water cut or require WOJ and poor reservoir performance of Bhagyam. Power fluid pumps maintenance job ongoing in Mangala.
Ø Panna-Mukta (BG): Closure of certain wells owing to well integrity.
3. Refinery Production (in terms of crude oil processed)
Refinery production during June, 2017 was 20057.80 TMT which is 0.11% higher than the target for the month but 0.54% lower when compared with June, 2016. Cumulative production during April-June, 2017 was 60898.38 TMT which is 3.19% higher than the target for the period and 1.04% higher than the production during corresponding period of last year. Unit-wise production is given at Annexure-III. Company-wise production for the month of June, 2017 and cumulatively for the period April-June, 2017 vis-à-vis same period of last year has been shown in Table-3 and month-wise in Figure-3.
Figure 3: Monthly Refinery Production
Table 3: Refinery Production (TMT)
Oil Company
|
Target
|
June (Month)
|
April-June (Cumulative)
|
2017-18 (Apr-Mar)
|
2017-18
|
2016-17
|
% over last year
|
2017-18
|
2016-17
|
% over last year
|
Target
|
Prod.*
|
Prod.
|
Target
|
Prod.*
|
Prod.
|
CPSE
|
139090
|
11493.28
|
12083.45
|
11095.09
|
108.91
|
34466.45
|
35690.25
|
33802.66
|
105.58
|
IOCL
|
65750
|
5405.00
|
5729.44
|
5183.04
|
110.54
|
16741.00
|
17520.83
|
16097.65
|
108.84
|
BPCL
|
27000
|
2200.00
|
2243.35
|
2059.72
|
108.92
|
6200.00
|
6338.05
|
6202.41
|
102.19
|
HPCL
|
17309
|
1449.76
|
1486.17
|
1422.76
|
104.46
|
4296.56
|
4490.39
|
4479.04
|
100.25
|
CPCL
|
10300
|
866.10
|
963.88
|
915.08
|
105.33
|
2574.66
|
2588.93
|
2642.64
|
97.97
|
NRL
|
2670
|
219.529
|
234.037
|
232.812
|
100.53
|
665.71
|
704.51
|
687.68
|
102.45
|
MRPL
|
16000
|
1350.000
|
1419.243
|
1273.915
|
111.41
|
3975.00
|
4027.15
|
3672.27
|
109.66
|
ONGC
|
62
|
2.891
|
7.327
|
7.762
|
94.40
|
13.52
|
20.39
|
20.97
|
97.25
|
JVs
|
15201
|
922.000
|
586.906
|
1410.598
|
41.61
|
2686.00
|
2594.84
|
4426.05
|
58.63
|
BORL
|
6000
|
525.00
|
586.91
|
532.28
|
110.26
|
1575.00
|
1773.20
|
1682.37
|
105.40
|
HMEL
|
9201
|
397.00
|
0.00
|
878.32
|
0.00
|
1111.00
|
821.64
|
2743.67
|
29.95
|
Private
|
90480
|
7619.62
|
7387.44
|
7661.85
|
96.42
|
21860.66
|
22613.29
|
22044.58
|
102.58
|
RIL
|
70174
|
5941.75
|
5723.77
|
5941.75
|
96.33
|
16827.06
|
17487.05
|
16827.064
|
103.92
|
EOL
|
20306
|
1677.87
|
1663.67
|
1720.10
|
96.72
|
5033.6
|
5126.238
|
5217.512
|
98.25
|
TOTAL
|
244771
|
20034.90
|
20057.80
|
20167.55
|
99.46
|
59013.11
|
60898.38
|
60273.29
|
101.04
|
Note: 1 HMEL Refinery undergone major turnaround during Apr-Jun, 2017 *: Provisional
2. Totals may not tally due to rounding off.
3.1 CPSE Refineries’ production during June, 2017 was 12083.45 TMT which is 5.13% higher than the target for the month and 8.91% higher than the production achieved in the corresponding month of last year. Cumulative production by CPSE refineries during April-June, 2017 was 35690.26 TMT which is 3.55% higher than the target for the period and 5.58% higher than the production during corresponding period of last year. Reasons for shortfall of refinery production in some CPSE refineries are as under:
Ø IOCL, Guwahati: Lower due to deferment shutdown of HGU, HDT & MSQ from Apr'17 to June'17.
Ø IOCL, Barauni: Lower due to BS- IV switchover (naphtha Containment).
Ø IOCL, Panipat: Marginally lower than plan due to high SRGO stocks
Ø IOCL, Gujarat: Lower Due to M&I shutdown of AU-1/AU-2/AU-4.
Ø IOCL, Haldia: Lower due to OHCU BLE issue.
Ø IOCL, Bongaigaon: Lower due to CDU-1 Idling due to low Crude Stock and High DHDT ISD due to HGU and DHDT S/D.
Ø BPCL, Mumbai: Lower due to planned shutdown of CDU3, NHGU and Hydrocracker unit for Turnaround and revamp.
Ø HPCL, Visakh: Lower due to unplanned shutdown of primary units.
Ø CPCL, Manali & CBR: Lower than target due to CDU-3/HGU shutdown (equipment problem) in Apr'17.
3.2 Production in JV refineries during June, 2017 was 586.91 TMT which is 36.34% lower than the target for the month and 58.39% lower than the production achieved in the corresponding month of last year. Cumulative production by JVs refineries during April-June, 2017 was 2594.84 TMT which is 3.39% lower than the target for the period and 41.37% lower than the production during corresponding period of last year. The major reason for shortfall in production was major turnaround underway in HMEL refinery during April - June, 2017.
3.3 Production in private refineries during June, 2017 was 7387.44 TMT which is 3.05% lower than the target for the month and 3.58% lower when compared with June, 2016. Cumulative production by private refineries during April-June, 2017 was 22613.29 TMT which is 3.44% higher than the target for the period and 2.58% higher than the production during corresponding period of last year.
3.4 Refinery-wise details of the capacity utilization and production of petroleum products during the month of June, 2017 and cumulatively for the period April-June, 2017 vis-à-vis April-June, 2016 are given at Annexures - IV and V respectively.
Click here to see Annexure
********