Status of Construction of Bridges in GOA on NH-17

Posted On: 18 JUL 2017 2:18PM by PIB Delhi

In a written reply to a question in the Rajya Sabha today, the Minster of State for Road Transport & Highways and Shipping, Shri Mansukh L. Mandaviya gave the status of  construction of the bridges proposed on National Highway-17 in Goa sector as follows:-

 

S.No

Name of the bridge

Status of construction

Target of completion

Cost of construction (in Rs. Crores)

Mode of financing

Parties involved

1.

Zuari river bridge

In Progress

(1%)

23/11/2019

936.40

Financed by Ministry under budgetary resources

Government of India

2.

Mandovi river bridge

In Progress

(60%)

31/05/2018

517.00

Financed by the State Government and National Bank of Agriculture and Rural Development (NABARD)

Government of Goa through Goa State Infrastructure Development Corporation (GSIDC)

3

Talpona, Galjibag, Maxem bridges as part of Canacona bypass from km 68/00 to km 85/740 of NH-17 in the state of Goa on EPC mode

In Progress

(36%)

06/12/2017

280.16

Financed by Ministry under budgetary resources

Government of India

 

*****

NP/MS