Government Develops Industrial Townships Under NICDP Through Centre-State Partnership Model


Government Approves 20 Industrial Nodes Under NICDP; ₹16,172.95 Crore Sanctioned for Industrial Corridor Development

Four Industrial Corridor Projects Completed with World-Class Infrastructure; Government Fast-Tracks Remaining Nodes

प्रविष्टि तिथि: 04 AUG 2026 3:20PM by PIB Delhi

Government of India has undertaken development of industrial townships under the National Industrial Corridor Development Programme (NICDP), through Special Purpose Vehicles formed jointly with the State Government. The project development activities include identification of industrial nodes as per the prioritisation of the State government, followed by preparation and approval of concept master plan and development plan, environmental clearance and detailed design plan by the State government, prior to consideration of the project for approval. The State Government contribution is in the form of land and Govt of India’s contribution is in the form of equity and/or debt.

Government of India has approved a total of 20 industrial nodes under NICDP. Out of these, 12 projects were approved during the last 5 years. The State wise details of these projects is at Annexure I.

Department for Promotion of Industry and Internal Trade (DPIIT) has sanctioned and released funds amounting to Rs.16,172.95 Crore to National Industrial Corridor Development and Implementation Trust (NICDIT) for development of Industrial Corridor Projects. NICDIT has further released funds to the extent of Rs.14,569.97 Crore to the project SPVs to carry out project development for various industrial nodes/projects under NICDP.

Details regarding the funds released to the project SPVs by NICDIT for the approved projects, State and project-wise is at Annexure II.

Out of the 20 projects approved under NICDP, four projects have been completed. The current status of ongoing projects (16 no.) under NICDP is at Annexure III. The total construction timeline for project completion is 36-48 months from the actual date of appointment of EPC contractor.

The internal trunk infrastructure, including roads, water supply, sewerage and power distribution within the industrial city/node, are executed through EPC contractors engaged by the respective project SPVs. External connectivity infrastructure such as bulk water supply, power, telecom and roads—have been comprehensively mapped and examined on the PM Gati Shakti National Master Plan (NMP) portal and undertaken by concerned state SPVs as per SHA/SSA conditions in consultation with State department/Central agencies.

The following components have been developed in the 04 completed projects:

 

S.

No.

State

Node

Infrastructure components developed

i.

Gujarat

Dholera Special Investment Region (DSIR)

  • Roads & Services
  • Administrative Building
  • Water sourcing and transmission Water
  • Treatment Plant
  • Sewage
  • Treatment Plant Common Effluent Treatment Plant
  • Power
  • infrastructure      Information     and communication Technology (ICT)

facilities

ii.

Maharashtra

Shendra-Bidkin Industrial Area (SBIA)

iii

Uttar Pradesh

Integrated Industrial Township – Greater Noida (IIT-GN)

iv

Madhya Pradesh

Integrated Industrial Township – Vikram Udyogpuri (IIT-VUL)

 

The following steps are taken to expedite implementation and ensure timely

completion of projects:

 

  • An Apex Monitoring Authority periodically reviews the activities of NICDIT and the progress of the Industrial Corridor projects
  • DPIIT through NICDIT periodically monitors the development of these projects with the officials of State Govt(s)/respective agencies/stakeholders.
  • All necessary regulatory as well as statutory clearances are obtained on time through coordination with stakeholders and line agencies to reduce risk.
  • Regular monitoring at various levels is carried out and necessary policy interventions are made wherever required.
  • The PRAGATI and PMG portals are leveraged to fast-track project implementation and ensure timely completion to remove bottlenecks wherever required.

 

ANNEXURE-I

 

 

Sl.No

State

Name

Project approval year

1

Uttarakhand

IMC at Khurpia

August, 2024

2

Punjab

IMC at Rajpura

3

Maharashtra

Dighi Port Industrial Area

4

Kerala

Palakkad Industrial Area

5

Rajasthan

Jodhpur Pali Marwar Industrial Area

6

Haryana

IMC at Hisar

7

Uttar Pradesh

IMC at Agra

8

IMC at Prayagraj

9

Bihar

IMC at Gaya

10

Andhra Pradesh

Orvakal Industrial Area

11

Kopparthy Industrial Area

12

Telangana

Zaheerabad Industrial Area

 

 

ANNEXURE-II

 

Sl.

No

State

Name

Project Cost

(in crore)

Funds  released

(in crore)

1.

Gujarat

Dholera Special Investment Region (DSIR)

2784

Equity - 2784

2.

Maharashtra

Shendra-Bidkin Industrial

Area (SBIA)

7947

Equity - 3000

Dighi Port Industrial Area

5469

Equity - 701.13

3.

Uttar Pradesh

Integrated Industrial Township – Greater Noida

(IIT-GN)

1714

Equity - 617.20

Multi Modal Logistics Hub (MMLH) at Dadri & Multi

Modal Transport Hub (MMTH) at Boraki

3907

Equity - 853.05

IMC at Prayagraj

658

Equity - 323.09

IMC at Agra

1812

Equity – 2.50

4

Madhya Pradesh

Integrated Industrial

Township – Vikram Udyogpuri (IIT-VUL)

808

Equity - 55.93

Debt – 83.70

5

Haryana

Integrated Multi-Modal Logistics Hub – Nangal Chaudhary (IMLH- NC)

1029

Equity - 211.63

Debt – 212.15

IMC at Hisar

4,680

Equity - 2.45

6

Rajasthan

Jodhpur Pali Marwar Industrial Cluster (JPMIA)

922

Equity - 327.69

7

Andhra Pradesh

Krishnapatnam Industrial

Area

2,139

Equity - 533.86

Orvakal Industrial Area

2,786

Equity - 500.26

Kopparthy Industrial Area

2,136

Equity - 500.20

8

Karnataka

Tumakuru Industrial Area

1,701

Equity - 586.74

9

Kerala

Palakkad Industrial Area

3,805

Equity - 936.96

10

Uttarakhand

IMC at Khurpia Farm

1,265

Equity – 405.46

11

Punjab

IMC at Rajpura Patiala

1,367

Equity - 215.60

12

Bihar

IMC at Gaya

1,339

Equity - 134.72

13

Telangana

Zaheerabad Industrial Area

2,360

Equity - 536.23

 

 

ANNEXURE-III

 

S.

No.

Name of Project & Corridor

Area (acre)

Status

1

Krishnapatnam, Andhra Pradesh - CBIC

2,006

EPC contractor appointed in Feb’ 2024.

2

Tumakuru, Karnataka - CBIC

1,736

EPC contractor appointed in Feb’ 2023.

06    industrial    plots    admeasuring     250 acres allotted.

3

Integrated Multi-Modal Logistics Hub – Nangal Chaudhary

(IMLH-NC), Haryana - DMIC

886

Project to be executed on PPP basis.

External connectivity works (road, power and external rail connectivity) are complete.

Project appraised by PPPAC in July, 2025.

The locomotive trial run to check the fitness of all tracks has been completed in June 2026.

4

Multi Modal Logistics Hub (MMLH)- Uttar Pradesh - DMIC

825

Project to be executed on PPP basis.

Tender       re-floated       for      appointment                  of concessionaire in July 2026.

 

Multi Modal Transport Hub (MMTH) - Boraki, Uttar Pradesh - DMIC

358

The project declared as a Special Railway Project by Ministry of Railway in Dec 2024.

Engineering Scale Plan (ESP) for Boraki station-Development approved by NCR in May, 2025 for

finalization of master plan, cost estimates, appointment of EPC contractor.

5

Dighi,

Maharashtra

-

6,056

Execution of SHA & SSA:

 

DMIC

 

 

 

Completed. Incorporation of SPV: Completed.

6

Jodhpur

Pali

Marwar

1,577

 

Industrial

 

Cluster

 

Programme Manager for New Cities (PMNC)

 

(JPMIA) - Rajasthan

 

onboarded except Prayagraj.

7

Rajpura, Punjab - AKIC

1,099

EPC onboarded for 10 projects.

8

Khurpia,      Uttarakhand

1,002

 

- AKIC

 

 

9

Prayagraj,          Uttar

351

 

 

Pradesh - AKIC

 

 

10

Gaya, Bihar - AKIC

1,670

 

11

Kopparthy,          Andhra

2,595

 

 

Pradesh - VCIC

 

 

12

Orvakal,

 

Andhra

2,621

 

 

Pradesh - HBIC

 

 

13

Zaheerabad,

3,245

 

 

Telangana - HNIC

 

 

14

Palakkad,       Kerala     –

1,710

 

 

CBIC extn.

 

 

15

Hisar, Haryana - AKIC

2,988

Execution of SHA & SSA:

Completed. Incorporation of SPV: Completed. PMNC onboarded.

16

Agra, Uttar Pradesh - AKIC

1,058

Matter awaiting clearance from the Supreme Court  on  account  of  falling  under  the  Taj

Trapezium Zone (TTZ).

               

 

This information was given by Minister of State for Ministry of Commerce and Industry, Shri Jitin Prasada in a written reply in Lok Sabha today.

***

Abhishek Dayal/ Abhijith Narayanan/ Ishita Biswas