Ministry of Power
Adequate Generation Capacity available to meet the electricity demand in the country: Shri R. K. Singh, Union Power & NRE Minister
51843.5 MW capacity (Thermal, Gas, Hydro, Nuclear) under construction; 22840 MW additional coal based thermal capacity planned by 2030: Shri R. K. Singh, Union Power & NRE Minister
Posted On:
27 JUL 2023 7:06PM by PIB Delhi
The consumption of electricity has increased in the country during the last three years and the current year. The details of all India Power Supply Position in the country in terms of Energy during the last three years and current year (up-to June, 2023) is given at Annexure-I. There is adequate generation capacity to meet the demand of the country. in order to meet the increasing demand of power, 18 numbers of coal based thermal power projects having total capacity of 25440 MW, one (1) gas based thermal power project having capacity of 370 MW and 42 numbers of hydro-electric projects (above 25 MW) having total capacity of 18033.5 MW are under construction in the country as on 30th June 2023. Further, Nuclear capacity totalling to 8000 MW is under various stages of construction. Also, 22840 MW additional coal based thermal capacity has been planned by 2030, out of which 15300 MW will be under Central Sector and 7540 MW under State Sector. Details are given at Annexure-II
As per the Electricity Act, 2003, generation is a de-licensed activity and any generating company may establish, operate and maintain a generating station without obtaining a license under this Act if it complies with the technical standards related to connectivity with the grid. The concurrence of the Central Electricity Authority (CEA) is required only in case of setting up of hydro-generating station.
Two (02) numbers of coal based Thermal Power Project in Central Sector (NTPC) having capacity of 3720 MW (two units of 660 MW each in North Karanpura TPS and three units of 800 MW each in Patratu TPS are under construction in the State of Jharkhand. Further, Koderma Thermal Power Project having capacity of 1600 MW is planned in the State of Jharkhand by DVC.
ANNEXURE-I
The details of all India Power Supply Position in the country in terms of Energy during the last three and current year 2023-24 (upto June, 2023) :
FY
|
Energy Requirement (MUs)
|
Energy Supplied (MUs)
|
% Growth Energy Requirement
|
% Growth Energy Supplied
|
% Energy not Supplied
|
(1)
|
(2)
|
(3)
|
(4)
|
(5)
|
2020-21
|
1275534
|
1270663
|
-
|
-
|
0.4
|
2021-22
|
1379812
|
1374024
|
8.2
|
8.1
|
0.4
|
2022-23
|
1511847
|
1504264
|
9.6
|
9.5
|
0.5
|
2023-24 ( Upto June, 2023)*
|
408621
|
407762
|
1.0
|
1.8
|
0.2
|
*Provisional
********
AM/DP
ANNEXURE-II
I Under Construction Coal Based Thermal Projects
UTILITY NAME
|
Project Name
|
Capacity Under Construction
|
I. Central Sector (12580-MW)
|
NTPC /PVUNL
|
Barh STPP, St-I (3x660 MW)
|
1320
|
Telangana STPP St-I (2x800 MW)
|
1600
|
North Karanpura STPP (3x660 MW)
|
1320
|
Patratu STPP (3x800 MW)
|
2400
|
Talcher TPP, St - III (2x660 MW)
|
1320
|
SJVN
|
BUXAR TPP (2x660 MW)
|
1320
|
NUPPL
|
Ghatampur TPP (3x660MW)
|
1980
|
THDC
|
Khurja SCTPP (2x660 MW)
|
1320
|
II. State Sector (12860 MW)
|
TANGEDCO
|
North Chennai TPP St-III (1x800 MW)
|
800
|
Ennore SEZ STPP (2x660 MW)
|
1320
|
Udangudi STPP, St-I (2x660 MW)
|
1320
|
UPRVUNL
|
Jawaharpur STPP (2x660 MW)
|
1320
|
Obra–C STPP (2x660 MW)
|
1320
|
Panki TPS Ext (1x660 MW)
|
660
|
APGENCO / APPDCL
|
Dr.NT TPS, St-V (1x800 MW)
|
800
|
TSGENCO
|
Yadadri TPS (1x800 MW)
|
4000
|
MAHAGENCO
|
Bhusawal TPS (1x660 MW)
|
660
|
WBPDCL
|
Sagardighi TPP, St-III (1x660 MW)
|
660
|
Total
|
25440 MW
|
|
|
|
|
|
II Under Construction Hydro Electric Projects (above 25 MW)
Sl. No
|
Name of Scheme
|
Sector
|
District
|
I.C. ( No. X MW.)
|
Cap. Under Execution (MW)
|
River/Basin
|
|
(Executing Agency)
|
|
|
Andhra Pradesh
|
|
|
|
|
|
|
1
|
Polavaram (APGENCO/ Irrigation Dept., A.P.)
|
State
|
East & West Godavari
|
12x80
|
960.00
|
Godavari/ EFR
|
|
2
|
Lower Sileru Extension (APGENCO)
|
State
|
Alluri Sitharamaraju
|
2x115
|
230.00
|
Sileru/ Godavari
|
|
3
|
Pinnapuram (Greenko AP01 IREP Private Limited)
|
Private
|
Kurnool
|
4x240 + 2x120
|
1200.00
|
Pennar Basin/EFR
|
|
|
Sub-total: Andhra Pradesh
|
|
|
|
2390.00
|
|
|
|
Arunachal Pradesh
|
|
|
|
|
|
|
4
|
Subansiri Lower (NHPC)
|
Central
|
Lower Subansiri
|
8x250
|
2000.00
|
Subansiri/ Brahmaputra
|
|
5
|
Dibang Multipurpose Project (NHPC)
|
Central
|
Lower Dibang Valley
|
12x240
|
2880.00
|
Dibang / Brahmaputra
|
|
|
Sub-total: Arunachal Pradesh
|
|
4880.00
|
|
|
|
|
Assam
|
|
|
|
|
|
|
6
|
Lower Kopli (APGCL)
|
State
|
Dima Hasao & Karbi Anglong
|
2x55+2x2.5+1x5
|
120.00
|
Kopili/ Brahmaputra
|
|
|
Sub-total: Assam
|
|
|
|
120.00
|
|
|
|
Himachal Pradesh
|
|
|
|
|
|
|
7
|
Parbati St. II (NHPC)
|
Central
|
Kullu
|
4x200
|
800.00
|
Parbati/Beas/Indus
|
|
8
|
Luhri-I (SJVN)
|
Central
|
Kullu/Shimla
|
2x80+2x25
|
210.00
|
Satluj/Indus
|
|
9
|
Dhaulasidh (SJVN)
|
Central
|
Hamirpur/ Kangra
|
2x33
|
66.00
|
Beas/Indus
|
|
10
|
Sunni Dam (SJVN)
|
Central
|
Shimla/Mandi
|
4x73+1x73+1x17
|
382.00
|
Satluj
|
|
11
|
Uhl-III (BVPCL)
|
State
|
Mandi
|
3x33.33
|
100.00
|
Uhl/Beas/
Indus
|
|
12
|
Shongtong Karcham (HPPCL)
|
State
|
Kinnaur
|
3x150
|
450.00
|
Satluj/ Indus
|
|
13
|
Chanju-III (HPPCL)
|
State
|
Chamba
|
3x16
|
48.00
|
Chanju Nallah
|
|
14
|
Tidong-I (Statkraft IPL)
|
Private
|
Kinnaur
|
3x50
|
150.00
|
Tidong/ Satluj/Indus
|
|
|
|
|
|
|
|
|
|
|
|
15
|
Kutehr (JSW Energy Ltd)
|
Private
|
Chamba
|
3x80
|
240.00
|
Ravi/ Indus
|
|
16
|
Tangnu Romai (TRPG)
|
Private
|
Shimla
|
2x22
|
44.00
|
Pabbar/Tons/ Yamuna/ Ganga
|
|
|
Sub-total: Himachal Pradesh
|
|
2490.00
|
|
|
|
|
Jammu & Kashmir
|
|
|
|
|
|
|
17
|
Pakal Dul (CVPPL)
|
Central
|
Kishtwar
|
4x250
|
1000.00
|
Marusadar/ Chenab /
Indus
|
|
18
|
Kiru (CVPPL)
|
Central
|
Kishtwar
|
4x156
|
624.00
|
Chenab/ Indus
|
|
19
|
Ratle (RHEPPL / NHPC)
|
Central
|
Kishtwar
|
4x205 + 1x30
|
850.00
|
Chenab/Indus
|
|
20
|
Kwar (CVPPPL)
|
Central
|
Kishtwar
|
4x135
|
540
|
Chenab/ Indus
|
|
21
|
Parnai (JKSPDC)
|
State
|
Poonch
|
3x12.5
|
37.50
|
Jhelum/ Indus
|
|
22
|
Lower Kalnai (JKSPDC)
|
State
|
Kishtwar
|
2x24
|
48.00
|
Chenab/ Indus
|
|
|
Sub-total: Jammu & Kashmir
|
|
3099.50
|
|
|
|
|
Kerala
|
|
|
|
|
|
|
23
|
Pallivasal (KSEB)
|
State
|
Idukki
|
2x30
|
60.00
|
Mudirapuzha/ Periyar/ Baypore Periyar/ WFR
|
|
24
|
Thottiyar (KSEB)
|
State
|
Idukki
|
1x30+1x10
|
40.00
|
Thottiyar/ Periyar/
/ Baypore Periyar/ WFR
|
|
25
|
Mankulam (KSEB)
|
State
|
Idukki
|
2x20
|
40.00
|
Melachery
|
|
|
Sub-total: Kerala
|
|
140.00
|
|
|
|
|
Madhya Pradesh
|
|
|
|
|
|
|
26
|
Maheshwar (SMHPCL)
|
Private
|
Khargone & Khandwa
|
10x40
|
400.00
|
Narmada/CIRS
|
|
|
Sub-total: Madhya Pradesh
|
|
400.00
|
|
|
|
|
Maharashtra
|
|
|
|
|
|
|
27
|
Koyna Left Bank (WRD,MAH)
|
State
|
Satara
|
2x40
|
80.00
|
Koyna/ Krishna/EFR
|
|
|
Sub-total: Maharashtra
|
|
80.00
|
|
|
|
|
Punjab
|
|
28
|
Shahpurkandi (PSPCL/ Irrigation Deptt., Pb.)
|
State
|
Pathankot
|
3x33+3x33+1x8
|
206.00
|
Ravi/ Indus
|
|
|
Sub-total: Punjab
|
|
|
|
206.00
|
|
|
|
Sikkim
|
|
|
|
|
|
|
29
|
Teesta St. VI NHPC
|
Central
|
South Sikkim
|
4x125
|
500.00
|
Teesta/Brahmaputra
|
|
30
|
Rangit-IV (NHPC)
|
Central
|
West Sikkim
|
3x40
|
120.00
|
Rangit/ Teesta/
Brahmaputra
|
|
31
|
Bhasmey (Gati Infrastructure)
|
Private
|
East Sikkim
|
2x25.5
|
51.00
|
Rangpo/ Teesta/
Brahmaputra
|
|
32
|
Rangit-II (Sikkim Hydro)
|
Private
|
West Sikkim
|
2x33
|
66.00
|
Greater Rangit/ Teesta/
Brahmaputra
|
|
33
|
Panan (Himagiri)
|
Private
|
North Sikkim
|
4x75
|
300.00
|
Rangyongchu/ Teesta/
Brahmaputra
|
|
|
Sub-total: Sikkim
|
|
|
|
1037.00
|
|
|
|
Tamil Nadu
|
|
|
|
|
|
|
34
|
Kundah Pumped Storage Phase-I,II&III)
|
State
|
Nilgiris
|
4x125
|
500.00
|
Kundah/ Bhavani/ Cauvery/EFR
|
|
|
Sub-total: Tamil Nadu
|
|
|
500.00
|
|
|
|
|
Uttarakhand
|
|
|
|
|
|
|
35
|
Vishnugad Pipalkoti (THDC)
|
Central
|
Chamoli
|
4x111
|
444.00
|
Alaknanada/ Ganga
|
|
36
|
Naitwar Mori (SJVNL)
|
Central
|
Uttarkashi
|
2x30
|
60.00
|
Tons/Yamuna/ Ganga
|
|
37
|
Tapovan Vishnugad (NTPC)
|
Central
|
Chamoli
|
4x130
|
520.00
|
Dhauliganga / Alaknanada & /Ganga
|
|
38
|
Tehri PSS (THDC)
|
Central
|
Tehri Garhwal
|
4x250
|
1000.00
|
Bhilangna/ Bhagirathi/
Ganga
|
|
39
|
Lakhwar Multipurpose Project (UJVNL)
|
State
|
Dehradun & Tehri Garhwal
|
3x100
|
300.00
|
Yamuna
|
|
40
|
Lata Tapovan (NTPC)
|
Central
|
Chamoli
|
3x57
|
171.00
|
Dhauliganga / Alaknanada & Ganga
|
|
41
|
Phata Byung (LANCO)
|
Private
|
Rudraprayag
|
2x38
|
76.00
|
Mandakini/ Alaknanda
Ganga
|
|
|
Sub-total: Uttarakhand
|
|
2571.00
|
|
|
|
|
West Bengal
|
|
|
|
|
|
|
42
|
Rammam-III (NTPC)
|
Central
|
Darjeeling
|
3x40
|
120.00
|
Rammam/ Rangit/Teesta Brahmaputra
|
|
|
Sub-total: West Bengal
|
|
|
|
120.00
|
|
|
|
Total:
|
|
|
|
18033.50
|
|
|
|
|
|
|
|
|
|
|
|
|
III Under Construction Gas based thermal Power plant
Sl. No
|
PROJECT
|
State
|
Sector
|
UNIT
|
Capacity (MW)
|
1
|
Yelahanka CCPP
(KPCL)
|
Karnataka
|
STATE
|
GT+ST
|
370
|
|
|
|
|
|
|
|
IV. Under Construction Nuclear Capacity
State
|
Location
|
Project
|
Capacity (MW)
|
Projects Under Construction
|
Gujarat
|
Kakrapar
|
KAPP- 4
|
1 X 700
|
Rajasthan
|
Rawatbhata
|
RAPP-7&8
|
2 X 700
|
Tamilnadu
|
Kudankulam
|
KKNPP-3&4
|
2 X 1000
|
KKNPP-5&6
|
2 X 1000
|
Kalpakkam
|
PFBR
|
500
|
|
(implemented by BHAVINI)
|
Haryana
|
Gorakhpur
|
GHAVP-1&2
|
2 X 700
|
Total
|
8000
|
V. Central Sector Additional Planned Thermal Capacity upto 2030
State
|
Utility Name
|
Project Name
|
Capacity Planned (MW)
|
|
|
|
|
Bihar
|
SJVN
|
Buxar (1x660)
|
660
|
|
|
Chhattisgarh
|
NTPC
|
Lara STPP-II (2x800)
|
1600
|
|
|
NTPC
|
Sipat-III (1x800)
|
800
|
|
|
Jharkhand
|
DVC
|
Koderma (2x800)
|
1600
|
|
|
Odisha
|
NTPC
|
Darlipali-II (1x800)
|
800
|
|
|
NLC
|
Talabira STPS (3x800)
|
2400
|
|
|
TamilNadu
|
NLC
|
Neyveli TPS-II 2nd Expansion (2x660)
|
1320
|
|
|
Uttar Pradesh
|
NTPC
|
Singrauli –III (2x800)
|
1600
|
|
|
NTPC
|
Meja II (2x800)
|
2400
|
|
|
West Bengal
|
DVC
|
Raghunathpur (2x660)
|
1320
|
|
|
DVC
|
Durgapur (1x800)
|
800
|
|
|
Total
|
15300 MW
|
|
|
VI : State Sector Additional Planned Thermal Capacity upto 2030
Utility Name
|
Project Name
|
Capacity Planned
|
Chhattisgarh
|
Super Critical Power Plant at Korba West, Korba (2x660)
|
1320
|
MSPGCL, Maharashtra
|
Chandrapur STPP
(1x660)
|
660
|
MPPCL, Madhya Pradesh
|
Amarkantak TPS (1x660)
|
660
|
Satpura TPP U-12, Phase –V (1x660)
|
660
|
Odisha
|
OPGC Expansion Project Stage III IB TPP (2x660)
|
1320
|
Rajasthan
(RRVUNL)
|
Kalisindh TPS
(1x800)
|
800
|
Telangana
|
Singareni TPS (Stage-II) (1x800)
|
800
|
MSPGCL, Maharashtra
|
Koradi (2x660)
|
1320
|
|
Total
|
7540 MW
|
This information was given by The Union Minister of New Renewable Energy & Power Sh. R. K. Singh in Lok Sabha in a written reply today.
******
AM/DP
(Release ID: 1943391)
Visitor Counter : 5003