Ministry of Petroleum & Natural Gas
Monthly Production Report for January 2022
Posted On:
23 FEB 2022 2:23PM by PIB Delhi
- Production of Crude Oil
Crude oil production[1] during January 2022 was 2511.66 TMT, which is 6.04% lower than target for the month and 2.40% lower than the production of January 2021. Cumulative crude oil production during April-January, 2021-22 was 24890.07 TMT, which is 4.63% and 2.61% lower than target for the period and production during corresponding period of last year respectively. Unit-wise and State-wise crude oil production is given at Annexure-I. Unit-wise crude oil production for the month of January 2022 and cumulatively for April-January 2021-22 vis-à-vis same period of last year has been shown in Table-1 and month-wise in Figure-1.
Table-1: Crude Oil Production (in TMT)
Oil Company
|
Target
|
January (Month)
|
April-January (Cumulative)
|
2021-22 (Apr-Mar)*
|
2021-22
|
2020-21
|
% over last year
|
2021-22
|
2020-21
|
% over last year
|
Target*
|
Prod.*
|
Prod.
|
Target*
|
Prod.*
|
Prod.
|
ONGC
|
20272.88
|
1726.31
|
1662.79
|
1715.74
|
96.91
|
16988.50
|
16259.10
|
16924.83
|
96.07
|
OIL
|
3182.60
|
282.72
|
255.32
|
242.58
|
105.25
|
2635.02
|
2499.16
|
2469.27
|
101.21
|
PSC Fields
|
7718.52
|
664.02
|
593.56
|
615.07
|
96.50
|
6475.29
|
6131.80
|
6162.71
|
99.50
|
Total
|
31173.99
|
2673.04
|
2511.66
|
2573.38
|
97.60
|
26098.81
|
24890.07
|
25556.80
|
97.39
|
Note: Totals may not tally due to rounding off. *: Provisional
Figure-1: Monthly Crude Oil Production
Unit-wise production details with reasons for shortfall are as under:
-
- Crude oil production by ONGC (Oil and Natural Gas Corporation) in nomination block during January 2022 was 1662.79 TMT, which is 3.68% lower than target of the month and 3.09% lower when compared with production of January 2021. Cumulative crude oil production by ONGC during April-January, 2021-22 was 16259.10 TMT, which is 4.29% and 3.93% lower than target for the period and production during corresponding period of last year respectively. Reasons for shortfall in production are as under:
- Less than anticipated production from WO-16 cluster due to delay in mobilization of MOPU Sagar Samrat.
- Less than anticipated production from Cluster-8 fields due to delay in inputs as installation of wellhead platforms got delayed due to Covid impact.
- Loss in oil production in Ratna & R-Series due to scaling in wells and delay in H2S package at R-13A wells.
- Less condensate receipt at Hazira due to less gas production from B&S Asset.
-
- Crude oil production by OIL (Oil India Ltd) in the nomination block during January 2022 was 255.32 TMT, which is 5.25% higher when compared with production of January 2021 but 9.69% lower than target of the month. Cumulative crude oil production by OIL during April-January 2021-22 was 2499.16 TMT, which is 1.21% higher than the production during corresponding period of last year but 5.16% lower than target for the period. Reasons for shortfall in production are as under:
- Less than planned contribution from workover wells and drilling wells.
- Less than planned due to local disturbance & miscreants activities in main producing area (MPA).
-
- Crude oil production by Pvt/JVs companies in the PSC/RSC regime during January 2022 was 593.56 TMT, which is 10.61% lower than the target of the reporting month and 3.50% lower than the month production of January 2021. Cumulative crude oil production by Pvt/JVs companies during April-January 2021-22 was 6131.80 TMT, which is 5.30% and 0.50% lower than target for the period and production during corresponding period of last year respectively. Reasons for shortfall in production are as under:
- MB/OSDSF/B80/2016 (Hindustan Oil Exploration Company Ltd.): Delay in commencement of production. Pre-commissioning in progress.
- RAVVA (Cairn Energy India Ltd): Production shortfall due to lower performance of wells RD-3ST and RD-6ST due to infectivity issues.
- CB-ONN-2004/2 (ONGC): Production shortfall due to less evacuation to IOCL due to leakage and choking in ONGC pipeline.
- CB-OS/2 ((Cairn Energy India Ltd): Production shortfall is due to natural decline and increase in water cut observed in aquifer supported pools and recent sanding/loading issues in the wells.
- Production of Natural Gas
Natural gas production during January 2022 was 2861.09 MMSCM, which is 12.17% higher than the production of January 2021 but 16.47% lower than the monthly target. Cumulative natural gas production during April-January 2021-22 was 28535 MMSCM, which is 20.50% higher than production during corresponding period of last year but 9.59% lower when compared with target for the period. Unit-wise and state-wise natural gas production is given at Annexure-II. Unit-wise natural gas production for the month of January 2022 and cumulatively for April-January 2021-22 vis-à-vis same period of last year has been shown in Table-2 and month-wise in Figure-2.
Table-2: Natural Gas Production (in MMSCM)
Oil Company
|
Target
|
January (Month)
|
April-January (Cumulative)
|
2021-22 (Apr-Mar)*
|
2021-22
|
2020-21
|
% over last year
|
2021-22
|
2020-21
|
% over last year
|
Target*
|
Prod.*
|
Prod.
|
Target*
|
Prod.*
|
Prod.
|
ONGC
|
23335.10
|
2000.05
|
1749.35
|
1865.72
|
93.76
|
19488.61
|
17291.18
|
18410.04
|
93.92
|
OIL
|
2949.65
|
250.00
|
232.98
|
211.95
|
109.92
|
2472.91
|
2422.75
|
2081.78
|
116.38
|
PSC Fields
|
11834.60
|
1175.19
|
878.76
|
473.01
|
185.78
|
9600.67
|
8821.07
|
3187.82
|
276.71
|
Total
|
38119.35
|
3425.25
|
2861.09
|
2550.68
|
112.17
|
31562.19
|
28535.00
|
23679.64
|
120.50
|
Note: Totals may not tally due to rounding off. *: Provisional
Figure-2: Monthly Natural Gas Production
-
- Natural gas production by ONGC in the nomination blocks during January 2022 was 1749.35 MMSCM, which is 12.53% lower than target for the month and 6.24% lower than the production of January 2021. Cumulative natural gas production by ONGC during April-January, 2021-22 was 17291.18 MMSCM, which is 11.28% and 6.08% lower than target for the period and production during corresponding period of last year respectively. Reasons for shortfall in production are as under:
- Less than anticipated production from WO-16 cluster due to delay in mobilization of MOPU Sagar Samrat.
- Less than planned production from Vasistha /S1 wells in EOA due to certain reservoir related issues.
- Delay in commencement of gas production from U1 field of KG-98/2 Cluster-II due to covid impact as manufacturing of subsea items and well completion got delayed.
- Less production due to decline in Tapti-Daman block in B&S Asset.
-
- Natural gas production by OIL in the nomination block during January 2022 was 232.98 MMSCM which is 9.92% higher than target for the month and 6.81% lower than the production of January 2021. Cumulative natural gas production by OIL during April-January 2021-22 was 2422.75 MMSCM, which is 16.38% higher than production during corresponding period of last year but 2.03% lower than target for the period. Shortfall in production is due to less than planned contribution from workover wells and drilling wells.
-
- Natural gas production by Pvt/JVs companies in the PSC/RSC/CBM regime during January 2022 was 878.76 MMSCM, which is 85.78% higher than the production of January 2021 but 25.22% lower than the target for the month. Cumulative natural gas production by Pvt/JVs during April-January, 2021-22 was 8821.07 MMSCM, which is 176.71% higher than production during corresponding period of last year but 8.12% lower than target for the period. Reasons for shortfall in production are as under:
- KG-DWN-98/2 (ONGC): Delay in commencement of production. Pre-commissioning in progress.
- KG-DWN-98/3 (RIL): Production shortfall due to well intervention jobs in some wells.
- RJ-ON-90/1 (Cairn Energy India Ltd): Few Gas wells of RDG field are not producing as per expectations.
- RANIGANJ EAST (Essar Oil and Gas Exploration and Production Ltd.): Shortfall because delay in scheduled operations.
- RJ-ON//6 (FEL): Production shortfall due to less offtake by customer.
- Crude Oil Processed (Crude Throughput)
Crude Oil Processed during January 2022 was 21708.56 TMT, which is 3.03% lower than target for the month and 0.46% lower than the January 2021. Cumulative crude processed during April-January 2021-22 was 198923.79 TMT, which is 1.24 and 9.20% higher than target for the period and production during corresponding period of last year respectively. Refinery-wise details of the crude throughput and capacity utilization during the month of January 2022 vis-à-vis January 2021 are given at Annexure-III and Annexure-IV. Company-wise crude throughput for the month of January 2021 and cumulatively for the period April-January 2021-22 vis-à-vis same period of last year has been shown in Table-3 and month-wise in Figure-3.
Table 3: Crude Oil Processed (Crude Throughput) (in TMT)
Oil Company
|
Target
|
January (Month)
|
April-January (Cumulative)
|
2021-22 (Apr-Mar)*
|
2021-22
|
2020-21
|
% over last year
|
2021-22
|
2020-21
|
% over last year
|
Target*
|
Prod.*
|
Prod.
|
Target*
|
Prod.*
|
Prod.
|
CPSE
|
143300.54
|
13762.56
|
12876.14
|
13204.06
|
97.52
|
116065.59
|
111874.24
|
102932.72
|
108.69
|
IOCL
|
69120.46
|
6791.00
|
5843.72
|
6278.12
|
93.08
|
56191.56
|
55243.43
|
51036.68
|
108.24
|
BPCL
|
29801.53
|
2715.00
|
2752.96
|
2893.30
|
95.15
|
24380.53
|
24418.03
|
20788.41
|
117.46
|
HPCL
|
17751.16
|
1579.64
|
1644.80
|
1438.94
|
114.31
|
14070.69
|
10923.44
|
13464.67
|
81.13
|
CPCL
|
9130.00
|
998.39
|
915.07
|
917.46
|
99.74
|
7133.21
|
7049.89
|
6521.75
|
108.10
|
NRL
|
2840.00
|
248.00
|
271.97
|
248.84
|
109.29
|
2368.00
|
2202.18
|
2239.35
|
98.34
|
MRPL
|
14594.35
|
1425.00
|
1440.33
|
1419.84
|
101.44
|
11869.35
|
11974.68
|
8815.80
|
135.83
|
ONGC
|
63.04
|
5.53
|
7.30
|
7.56
|
96.52
|
52.25
|
62.59
|
66.06
|
94.74
|
JVs
|
18079.47
|
1514.50
|
1821.92
|
1495.73
|
121.81
|
15208.47
|
17036.26
|
14019.61
|
121.52
|
BORL
|
7058.47
|
578.50
|
721.98
|
694.44
|
103.97
|
5968.47
|
6111.79
|
4986.03
|
122.58
|
HMEL
|
11021.00
|
936.00
|
1099.94
|
801.29
|
137.27
|
9240.00
|
10924.47
|
9033.58
|
120.93
|
Private
|
78008.07
|
7109.20
|
7010.49
|
7109.19
|
98.61
|
65218.19
|
70013.29
|
65218.19
|
107.35
|
RIL
|
60940.96
|
5564.40
|
5277.05
|
5564.40
|
94.84
|
51174.65
|
53102.23
|
51174.65
|
103.77
|
NEL
|
17067.11
|
1544.80
|
1733.44
|
1544.80
|
112.21
|
14043.54
|
16911.06
|
14043.54
|
120.42
|
TOTAL
|
239388.08
|
22386.26
|
21708.56
|
21808.99
|
99.54
|
196492.25
|
198923.79
|
182170.52
|
109.20
|
|
|
|
|
|
|
|
|
|
|
|
Note: Totals may not tally due to rounding off. *: Provisional
Figure 3: Crude Oil Processed (Crude Throughput)
3.1 CPSE Refineries’ crude oil processed during January 2022 was 12876.14 TMT, which is 6.44% lower than target for the month and 2.48% lower than the production of January 2021. Cumulative crude throughput during April-January 2021-22 was 111874.24 TMT which is 8.69% lower than corresponding period of last year but 3.61% lower than target for the period. Reasons for shortfall in production are as under:
- IOCL-Haldia Refinery: Monthly Crude processed lower due to deferment of Crude Distillation Unit-2 (CDU) shutdown and Extension of CDU-2 shutdown.
- IOCL-Mathura & Panipat Refinery: Monthly Crude processed in line of products demand.
- IOCL-Bongaigaon Refinery: Monthly Crude processed in line of crude availability.
- IOCL-Paradip Refinery: Monthly crude processed marginally low due to leak in reaction furnace of Sulphur recovery unit.
- HPCL, Visakh Refinery: Monthly Crude processed lower due to shutdown of Primary Crude Processing Units.
- CPCL-Manali Refinery: Monthly Crude processed lower due to lower Bitumen/Petcoke upliftment.
3.2 JV refineries’ crude oil processed during January 2022 was 1821.92 TMT, which is 20.30% higher than the target for the month and 21.81% higher than January 2021. Cumulative crude throughput during April-January 2021-22 was 17036.26 TMT, which is 12.02% and 21.52% higher than target for the period and production during corresponding period of last year respectively.
3.3 Private refineries’ crude oil processed during January 2022 was 7010.49 TMT, which is 1.39% lower than the corresponding month of last year. Cumulative crude throughput during April-January 2021-22 was 70013.29 TMT, which is 7.35% higher than the corresponding period of last year.
- Production of Petroleum Products
-
- Production of Petroleum Products during January 2021 was 22997.96 TMT, which is 3.55% higher than production of January 2021 and 3.72% higher than target for the month. Cumulative production during April-January, 2021-22 was 209006.59 TMT, which is 1.71% and 9.29% higher than target for the period and production during corresponding period of last year respectively. Unit-wise production of petroleum products is given at Annexure-V. Company-wise production for the month of January 2021-22 and cumulatively for April-January, 2021 vis-à-vis same period of last year has been shown in Table-4 and month-wise in Figure-4.
Figure 4: Monthly Refinery Production of Petroleum Products
Table 4: Production of Petroleum Products (TMT)
Oil Company
|
Target
|
January (Month)
|
April-January (Cumulative)
|
2021-22 (Apr-Mar)*
|
2021-22
|
2020-21
|
% over last year
|
2021-22
|
2020-21
|
% over last year
|
Target*
|
Prod.*
|
Prod.
|
Target*
|
Prod.*
|
Prod.
|
CPSE
|
135423.57
|
12617.32
|
12161.89
|
12536.36
|
97.01
|
110518.32
|
105927.22
|
97481.15
|
108.66
|
IOCL
|
65757.60
|
6161.75
|
5602.18
|
6126.82
|
91.44
|
54011.23
|
53005.56
|
49048.58
|
108.07
|
BPCL
|
27811.21
|
2558.84
|
2578.29
|
2684.05
|
96.06
|
22696.04
|
23293.33
|
19835.97
|
117.43
|
HPCL
|
16583.96
|
1478.45
|
1522.96
|
1420.09
|
107.24
|
13142.69
|
10173.94
|
12580.36
|
80.87
|
CPCL
|
9279.11
|
864.85
|
860.95
|
825.11
|
104.34
|
7633.11
|
6455.10
|
5955.69
|
108.39
|
NRL
|
2839.03
|
247.92
|
272.87
|
252.95
|
107.88
|
2367.19
|
2165.08
|
2267.67
|
95.48
|
MRPL
|
13092.62
|
1300.24
|
1317.71
|
1220.14
|
108.00
|
10618.31
|
10774.50
|
7729.59
|
139.39
|
ONGC
|
60.02
|
5.27
|
6.92
|
7.21
|
96.01
|
49.75
|
59.71
|
63.29
|
94.34
|
JVs
|
16813.56
|
1322.16
|
1651.08
|
1378.92
|
119.74
|
14161.02
|
15754.65
|
13002.12
|
121.17
|
BORL
|
6547.56
|
539.16
|
647.61
|
598.49
|
108.21
|
5530.02
|
5441.70
|
4368.42
|
124.57
|
HMEL
|
10266.00
|
783.00
|
1003.47
|
780.43
|
128.58
|
8631.00
|
10312.96
|
8633.70
|
119.45
|
Private
|
93222.97
|
7907.34
|
8850.89
|
7907.34
|
111.93
|
77209.90
|
83893.87
|
77209.90
|
108.66
|
RIL
|
76683.16
|
6429.86
|
7227.56
|
6429.86
|
112.41
|
63602.59
|
67649.24
|
63602.59
|
106.36
|
NEL
|
16539.81
|
1477.48
|
1623.33
|
1477.48
|
109.87
|
13607.31
|
16244.63
|
13607.31
|
119.38
|
Total Refinery
|
245460.10
|
21846.83
|
22663.86
|
21822.62
|
103.85
|
201889.24
|
205575.75
|
187693.17
|
109.53
|
Fractionators
|
4331.28
|
363.33
|
334.10
|
350.53
|
95.31
|
3609.63
|
3430.84
|
3550.95
|
96.62
|
TOTAL
|
249791.38
|
22210.16
|
22997.96
|
22173.16
|
103.72
|
205498.88
|
209006.59
|
191244.12
|
109.29
|
Note: Totals may not tally due to rounding off. *: Provisional
-
- Production of petroleum Products by Oil’s Refineries during January 2022 was 22663.86 TMT, which is 3.74% higher than production of January 2021 and 3.85% higher when compared with target for the month. Cumulative production during April-January, 2021-22 was 205575.75 TMT, which is 1.83% and 9.53% higher than target for the period and production during corresponding period of last year respectively.
-
- Production of petroleum Products by Fractionators during January 2022 was 334.10 TMT, which is 8.05% lower than the target for the month and 4.69% lower than production of January 2021. Cumulative production during April-January, 2021-22 was 3430.84 TMT, which is 4.95% and 3.38% lower than target for the period and production during corresponding period of last year respectively.
Click here to see Annexure I
Click here to see Annexure II
Click here to see Annexure III
Click here to see Annexure IV
Click here to see Annexure V
YB/RM
***********
(Release ID: 1800505)
Visitor Counter : 2017
Read this release in:
Hindi