Crude
Oil
1.
Crude oil production
during August, 2017 was 3019.94 TMT which is 4.93% lower than target and 1.56%
lower when compared with August 2016. Cumulative crude oil production during
April-August, 2017 was 15104.60 TMT which is 3.11% lower than target for the period
and 0.27% lower than production during corresponding period of last year. Unit-wise
and state-wise crude oil production is given at Annexure-I. Unit-wise crude oil
production for the month of August, 2017 and cumulatively for the period April-August,
2017 vis-à-vis same period of last year has been shown in Table-1 and month-wise
in Figure-1.
Table-1: Crude
Oil Production (in TMT)
Oil Company
|
Target
|
August (Month)
|
April-August (Cumulative)
|
2017-18 (Apr-Mar)
|
2017-18
|
2016-17
|
% over last year
|
2017-18
|
2016-17
|
% over last year
|
Target
|
Prod.*
|
Prod.
|
Target
|
Prod.*
|
Prod.
|
ONGC
|
23071.00
|
1956.69
|
1898.47
|
1865.31
|
101.78
|
9569.08
|
9457.74
|
9225.22
|
102.52
|
OIL
|
3734.00
|
316.98
|
288.48
|
272.08
|
106.03
|
1564.87
|
1416.81
|
1342.94
|
105.50
|
PSC
Fields
|
10562.00
|
903.03
|
832.98
|
930.42
|
89.53
|
4455.49
|
4230.06
|
4578.05
|
92.40
|
Total
|
37367.00
|
3176.70
|
3019.94
|
3067.80
|
98.44
|
15589.44
|
15104.60
|
15146.22
|
99.73
|
Note: Totals may not
tally due to rounding off. *:
Provisional
Figure-1: Monthly Crude Oil Production
Unit-wise
production details with reasons for shortfall are as under:
1.1
Crude
oil production by ONGC during August, 2017 was 1898.47 TMT which is 2.98% lower
than the monthly target but 1.78% higher when compared with August, 2016.
Cumulative crude oil production by ONGC during April-August, 2017 was 9457.74
TMT which is 1.16% lower than target for the period but 2.52% higher than production
during corresponding period of last year. Reasons for shortfall in production
are as under:
Ø Offshore: Natural
decline and increase in water cut from matured fields of Western Offshore. Due
to severe monsoon and harsh weather conditions, wells at unmanned platforms
could not be attended / monitored which affected regular operations like Gas
Lift De-optimization, ESP failure & minimum well monitoring / stimulation
etc.
Ø Onshore:
Power
shut down in Mehsana (heavy rain) and Assam Assets.
1.2
Crude
oil production by OIL during August, 2017 was 288.48 TMT which is 8.99% lower
than monthly target but 6.03% higher than production in August, 2016. Cumulative
crude oil production by OIL during April-August, 2017 was 1416.81 TMT which is 9.46%
lower than target for the period but 5.50% higher than production during corresponding
period of last year. Reasons for shortfall in production are as under:
Ø Less than
planned achievement due to higher decline in production potential of wells
mainly in Greater Hapjan and Greater Chandmari areas.
Ø Less than
planned contribution from work over wells.
1.3
Crude
oil production by Pvt/JVs during August, 2017 was 832.98 TMT which is 7.76% lower
than the monthly target and 10.47% lower than August, 2016. Cumulative crude
oil production by Pvt/JVs during April-August, 2017 was 4230.06 TMT which is 5.06%
lower than target for the period and 7.60% lower than the production during
corresponding period of last year. Reasons for shortfall in production are as
under:
Ø RJ-ON-90/1
(CIL): Around 120 wells are closed either due to high water cut or require WOJ.
Poor reservoir performance of Bhagyam. Production stopped from Guda,
Kaameshwari West, Raageshwari and Saraswati due to non-availability of tanker
since July’17.
Ø Panna-Mukta
(Shell): Certain wells closed due to integrity issues in Aug’17. Also, natural
decline in Panna-Mukta.
Ø CY-ONN-2002/2
(ONGC): Test production from 5 oil wells. PML not yet granted.
Ø CB-ONN-2004/2
(ONGC): Underperformance of wells.
Natural Gas
2.
Natural gas production during August, 2017 was 2772.94
MMSCM which is 5.38% lower than the target for the month but 3.69% higher when
compared with August, 2016. Cumulative natural gas production during April-August,
2017 was 13689.67 MMSCM which is 5.39% lower than target for the period but 4.31%
higher than the production during corresponding period of last year. Unit-wise
and state-wise natural gas production is given at Annexure-II. Unit-wise
natural gas production for the month of August, 2017 and cumulatively for the
period April-August, 2017 vis-à-vis same period of last year has been shown in Table-2
and month-wise in Figure-2.
Table-2: Natural Gas Production
(MMSCM)
Oil Company
|
Target
|
August (Month)
|
April-August (Cumulative)
|
2017-18 (Apr-Mar)
|
2017-18
|
2016-17
|
% over last year
|
2017-18
|
2016-17
|
% over last year
|
Target
|
Prod.*
|
Prod.
|
Target
|
Prod.*
|
Prod.
|
ONGC
|
24208.00
|
1992.35
|
1953.25
|
1845.50
|
105.84
|
9884.16
|
9737.62
|
8841.62
|
110.13
|
OIL
|
3000.00
|
264.97
|
261.47
|
244.05
|
107.14
|
1273.19
|
1235.22
|
1230.88
|
100.35
|
PSC
Fields
|
8034.00
|
673.18
|
558.22
|
584.59
|
95.49
|
3312.04
|
2716.83
|
3050.93
|
89.05
|
Total
|
35242.00
|
2930.51
|
2772.94
|
2674.15
|
103.69
|
14469.39
|
13689.67
|
13123.43
|
104.31
|
Note: Totals may not
tally due to rounding off. *:
Provisional
Figure-2:
Monthly Natural Gas Production
2.1
Natural
gas production by ONGC during August, 2017 was 1953.25 MMSCM which is 1.96% lower
than the monthly target and 5.84% higher when compared with August, 2016. Cumulative
natural gas production by ONGC during April-August, 2017 was 9737.62 MMSCM
which is 1.48% lower than the cumulative target but 10.13% higher than the
production during the corresponding period of the last year Reasons for
shortfall in production are as under:
Ø Offshore:
Bassein field gas production from BPB installation affected (13th
-29th Aug’17) for rectifying pipeline gas leakage from 24 inch
discharge line.
Ø Onshore:
OTPC, Tripura plant shut down for 20 days since 19.08.2017.
2.2
Natural
gas production by OIL during August, 2017 was 261.47 MMSCM which is 1.32% lower
than the monthly target but 7.14% higher than August, 2016. Cumulative natural
gas production by OIL during April-August, 2017 was 1235.22 MMSCM which is 2.98%
lower than the cumulative target but 0.35% higher than the production during
the corresponding period of last year Reasons for shortfall in production are
as under:
Ø Low production
potential availability of old wells due to water ingress, sand ingress and
unexpected down hole problems.
Ø Unplanned shut
down of gas turbines of RRVUNL.
2.3
Natural
gas production by Pvt/JVs during August, 2017 was 558.22 MMSCM which is 17.08%
lower than the monthly target and 4.51% lower when compared with August, 2016. Cumulative
natural gas production by Pvt/JVs during April-August, 2017 was 2716.83 MMSCM
which is 17.97% lower than the cumulative target and 10.95% lower than the
production during the corresponding period of last year. Reasons for shortfall
in production are as under:
Ø Underperformance
of wells in KG- OSN-2001/3 (GSPC)
Ø Sohagpur West
(RIL): Underperformance of CBM wells.
Ø Raniganj East
(Essar): Few wells closed for planned maintenance and refrac jobs
Ø AAP-ON-94/1
(HOEC): Production deferred due to delay in grant of PML. Production commenced
from 26th Aug’17
Ø RJ-ON-90/1
(CIL): Around 120 wells are closed either due to high water cut or require WOJ.
Ø Closure of 2
wells in D1D3 field and 1 well in MA field in KG-DWN-98/3 (RIL).
3.
Refinery Production (in terms of crude oil
processed)
Refinery
production during August, 2017 was 20451.48 TMT which is 4.36%
higher than the target for the month and 0.79% higher when compared with August,
2016. Cumulative production during April-August, 2017 was 101881.81 TMT which
is 4.02% higher than the target for the period and 0.10% higher than the
production during corresponding period of last year. Unit-wise production is
given at Annexure-III. Company-wise production for the month of August, 2017
and cumulatively for the period April-August, 2017 vis-à-vis same period of
last year has been shown in Table-3 and month-wise in Figure-3.
Table 3:
Refinery Production (TMT)
Oil Company
|
Target
|
August (Month)
|
April-August (Cumulative)
|
2017-18 (Apr-Mar)
|
2017-18
|
2016-17
|
% over last year
|
2017-18
|
2016-17
|
% over last year
|
Target
|
Prod.*
|
Prod.
|
Target
|
Prod.*
|
Prod.
|
CPSE
|
139090
|
10552.05
|
11197.45
|
10985.15
|
101.93
|
55071.56
|
58851.85
|
56599.51
|
103.98
|
IOCL
|
65750
|
4814.00
|
5293.07
|
4953.45
|
106.86
|
25503.00
|
28191.72
|
26736.96
|
105.44
|
BPCL
|
27000
|
2150.00
|
2128.41
|
2150.36
|
98.98
|
10500.00
|
10866.36
|
10485.93
|
103.63
|
HPCL
|
17309
|
1323.53
|
1575.77
|
1253.23
|
125.74
|
7060.63
|
7630.03
|
7152.95
|
106.67
|
CPCL
|
10300
|
932.47
|
944.76
|
1006.67
|
93.85
|
4439.59
|
4507.82
|
4645.52
|
97.04
|
NRL
|
2670
|
226.65
|
233.25
|
239.04
|
97.58
|
1119.01
|
1176.76
|
1163.62
|
101.13
|
MRPL
|
16000
|
1100.00
|
1017.27
|
1376.01
|
73.93
|
6425.00
|
6448.29
|
6380.23
|
101.07
|
ONGC
|
62
|
5.40
|
4.93
|
6.40
|
77.02
|
24.32
|
30.87
|
34.29
|
90.02
|
JVs
|
15201
|
1345.00
|
1507.39
|
1521.67
|
99.06
|
5376.00
|
4864.70
|
7358.17
|
66.11
|
BORL
|
6000
|
525.00
|
620.35
|
587.60
|
105.57
|
2625.00
|
3004.83
|
2771.82
|
108.41
|
HMEL
|
9201
|
820.00
|
887.04
|
934.07
|
94.97
|
2751.00
|
1859.87
|
4586.34
|
40.55
|
Private
|
90480
|
7699.47
|
7746.64
|
7783.51
|
99.53
|
37495.57
|
38165.26
|
37826.87
|
100.89
|
RIL
|
70174
|
6002.57
|
5967.65
|
6002.57
|
99.42
|
29068.16
|
29489.23
|
29068.16
|
101.45
|
EOL
|
20306
|
1696.90
|
1778.99
|
1780.94
|
99.89
|
8427.41
|
8676.04
|
8758.71
|
99.06
|
TOTAL
|
244771
|
19596.52
|
20451.48
|
20290.32
|
100.79
|
97943.12
|
101881.81
|
101784.55
|
100.10
|
Note:
Totals may not tally due to rounding off. *:
Provisional
Figure 3: Monthly Refinery
Production
3.1
CPSE
Refineries’ production during August, 2017 was 11197.45 TMT which is 6.12% higher
than the target for the month and 1.93% higher than the production achieved in
the corresponding month of last year. Cumulative production by
CPSE refineries during April-August, 2017 was 58851.85 TMT which is 6.86% higher
than the target for the period and 3.98% higher than the production during
corresponding period of last year. Reasons for shortfall of refinery production
in some CPSE refineries are as under:
Ø IOCL,
Panipat: Throughput lower due to deferment of M&I shutdown from Jul’17 to
Jul-Aug’17.
Ø IOCL,
Bongaigaon: High product stock due to restriction in rake movement on account
of floods in Assam/Bihar/Bengal.
Ø BPCL,
Mumbai: Lower due to planned outage of CDU3/Hydrogen / Hydrocracker units’
turnaround for revamp.
Ø MRPL,
Mangalore: Advancement of planned shutdown by 3 days for turnaround of DCU and
CDU-1.
3.2 Production
in JV refineries during August, 2017 was 1507.39 TMT which is 12.07% higher
than the target for the month but 0.94% lower than the production achieved in
the corresponding month of last year. Cumulative production by
JVs refineries during April-August, 2017 was 4864.70 TMT which is 9.51% lower
than the target for the period and 33.89% lower than the production during corresponding
period of last year.
3.3 Production
in private refineries during August, 2017 was 7746.64 TMT which is 0.61% higher
than the target for the month but 0.47% lower when compared with August, 2016. Cumulative
production by private refineries during April-August, 2017 was 38165.26 TMT
which is 1.79% higher than the target for the period and 0.89% higher than the
production during corresponding period of last year.
3.4 Refinery-wise
details of the capacity utilization and production of petroleum products during
the month of August, 2017 and cumulatively for the period April-August, 2017
vis-à-vis April-August, 2016 are given at Annexures - IV and
V respectively.
Click Here to See Annexures: