The Union Minister for Steel Shri Beni
Prasad Verma has said that the list of major integrated steel plants both in
public and private sector that are functioning in the various part of the
country, State/UTs-wise is given below:
(Crude
Steel Capacity in million tonnes)
S.No.
|
Company
|
Location
|
State
|
Current
approximate Capacity*
|
1
|
Steel
Authority of India Limited
|
IISCO,
Burnpur
|
West
Bengal
|
0.50
|
2.
|
Steel
Authority of India Limited
|
Bokaro
|
Jharkhand
|
4.36
|
3
|
Steel
Authority of India Limited
|
Bhilai
|
Chhattisgarh
|
3.93
|
4
|
Steel
Authority of India Limited
|
Rourkela
|
Orissa
|
1.90
|
5
|
Steel
Authority of India Limited
|
Durgapur
|
West
Bengal
|
1.80
|
6
|
Rashtriya
Ispat Nigam Limited
|
Visakhapatanam
|
Andhra
Aradesh
|
2.90
|
7
|
Tata
Steel Limited
|
Jamshedpur
|
Jharkhand
|
6.8
|
8
|
Essar
Steel Limited
|
Hazira
|
Gujarat
|
4.6
|
9
|
JSW
Steel Limited
|
Vijayanagar
|
Karnataka
|
6.6
|
10.
|
Jindal
Steel & Power Limited
|
Raigarh
|
Chhattisgarh
|
2.4
|
11
|
Ispat
Industries Limited
|
Dolvi
|
Maharastra
|
3.0
|
12
|
Bhushan
Power & Steel Limited
|
Jharsugda
|
Orissa
|
1.2
|
13
|
Bhushan
Steel Limited
|
Angul-Dhenkanal
|
Orissa
|
1.5
|
As per the latest information available in
the Ministry of Steel.
In a written reply in the Rajya Sabha
today. he said that in addition, there are several medium and small steel units
in the country including Mini Blast Furnace, Sponge Iron Units, Induction
Furnace Units and Rolling Mills. The
total number of such units is approximately 3647, as per the last survey
conducted by Joint Plant Committee in 2009-10.
Steel is a deregulated sector and Ministry of Steel maintains record of
public sector steel units and private sector integrated steel units having
capacity 1 million tonne or higher.
The Minister informed that the detailed status of major new steel plants
likely to come up by end of the next five year plan period, as furnished by the
concerned companies are Annexed.
He said that steel being a deregulated
sector, the detailed strategy regarding physical and financial matters of the private
sector projects are decided by the individual investors themselves. Ministry of Steel facilitates the
implementation of the major private sector projects through coordination with
concerned Ministries and State Governments.
An Inter-Ministerial Group (IMG) has been
set up in the Ministry which is vested with the job of monitoring and
coordinating on the issues concerning major steel investments, he added.
ANNEXURE
1. NMDC
Ltd. Chhattisgarh Greenfield project at Bastar (3 MTPA)
Proposed capacity:3.0 MTPA
Total land requirement – 1934 acres. 1783
acres already in possession. Balance
land is under process of allotment.
Total expenditure to be made-Rs.15525
crores.
Stage 1 clearance for diversion of 63.56
acres forest land has been received.
MoU signed between NMDC and CMDC Ltd. for
allocation, development, production and marketing of iron ore of Bailadila
Deposit No.4 for meeting the requirement of steel plant.
Date of completion – 42 months from”Zero
date” i.e. receipt of all statutory clearance/approvals and placement of orders
for major technological packages.
2. Tata
Steel Ltd. Orissa Greenfield project at Kalingnagar (6 MTPA)
Proposed capacity:6.0 MTPA (Phase I - 3.0 MTPA, PhaseII – 6.0 MTPA)
3040 acres land is registered in the
companies name. Proposal submitted to
IDCO for 580 acres of land for township and 226 acres for Rail Corridor. Acquisition of land delayed due to law and
order issues on land encroachment.
Partial land possession.
Total expenditure made – Rs.6500 crores.
Capacity of 6 mtpa likely to be achieved by
FY’2014.
3. Tata
Steel Ltd. Chhattisgarh Greenfield plant at Bastar (5.5 MTPA)
Proposed capacity :5.5 MTPA
PL granted for Bailadila Deposit – 1. Law
suits filed by NMDC and pending in court.
Land acquisition is in progress and 70% of
PAP has taken compensation/
Total expenditure made – Rs.129 crores.
DPR completed.
Capacity of 5.5 mtpa likely to be achieved
by FY’2015.
4. Tata
Steel Ltd., Jharkhand Greenfield plant at Seraikela (12 MTPA)
Proposed capacity:12.0 MTPA
Notification was awaited for private
land. Government of Jharkhand asking the
company to acquire Private Land directly.
Total expenditure made – Rs.25.5 crores.
DPR completed.
Capacity of 12.0 mtpa likely to be achieved
by FY’2016.
5. Essar
Steel Orissa Ltd. Orissa Greenfield plant at Paradeep (6.0MTPA)
Proposed Capacity:6.0 MTPA
Total land required for the project is 2649
acres in Paradeep and Dabuna.
For ISP – Out of 1822 acres, 456 acres of
private land has been acquired and 812 acres of private land is under
acquisition.
Proposed project cost – Rs.22,600 crores.
Project implemented time – 36 months from
the date of land acquisition.
Essar Steel Chhattisgarh Ltd. Chhattisgarh
Greenfield plant at Bastar (3.2 MTPA)
Proposed Capacity:3.2 MTPA
The company has applied for 608.33 Ha
(Private land – 393.21 Ha & Government land – 215.15 Ha) of land. Award under section 11 for the private land
has been passed by the Authorities.
Proposed project cost – Rs.11,000 crores.
Project implemented time – 36 months from
financial closure.
Essar Steel Jharkhand Ltd Jharkhand
Greenfield plant at Chaibasa (3.0 MTPA)
Proposed Cpacity:3.0MTPA
Total land required 2459 acres (GM Land –
338.26 acres & Raiyati land 2120.65 acres) approx. Due to resistance from villagers in and
around the proposed site, alternate sites have been identified and are being
evaluated.
Proposed project cost – Rs.23,000 crores.
Project implemented state – 36 months from
financial closure.
Essar Steel Karnataka Ltd., Karnataka
Greenfield plant at Bellary (6.0 MTPA)
Proposed Capacity: 6.0 MTPA
Total land required 2800 acres. Site survey has been done.
Proposed project cost – Rs.23,050 crores.
Project implemented stage – Phase 1 of 3
mtpa in about 36 months after completion of all preliminary work and
development of land.
Jindal Steel & Power Ltd. Orissa
Greenfield plant at Angul (6.0MTPA)
Proposed Capacity:6.0 MTPA
Total land required 4332 acres. 3882 acres of land is in possession.
Environment clearance and its amendment for
revised configuration received from MoEF.
Stage II clearance received for 416 acres
of forest land.
Proposed project cost – Rs.23,000 crores
(Steel and captive power plant).
Environmental clearance for 5.5 mtpa coal
mines obtained from MoEF.
Utkal B1 coal block in Talcher coal field
area has been allotted for captive use.
Project implemented stage – 2mtpa steel
making and 1.5 mtpa plate mill will be commissioned by December 2011.
Jindal Steel & Power Ltd. Jharkhand
Greenfield plantat Patratu (6.0 MTPA)
Proposed Capacity:6.0MTPA
Total land requirement for 3 mtpa – 1715
acres; Purchased/applied to Govt. with seller’s consent – 1463 acres.
No forest land involved for 3 mtpa project
under execution.
Proposed project cost for 3 mtpa –
Rs.12,500 crores, 22,000 crores for 6 MTPA.
Project implemented stage – completion of 3
mtpa (Phase 1) capacity will be 2013.
11. Jindal
Steel & Power Ltd. Jharkahdn Greenfield platn at Asanboni (5.0MTPA)
Proposed Capacity : 5.0 MTPA
Total land required 2895 acres. Purchased – 285 acres.
Forest clearance for 89 acres applied and
pending
Proposed project cost – Rs.20,000 crores.
Environmental clearance applied and
pending.
Jitpur coal block for CPP allocated.
ML for Jeraldaburu iron ore mine having
reserves of 70 million tonne granted.
Project implemented stage – First phase
would be completed by 2015.
12. Posco
India Project Orissa Greenfield plant at Jagatsinghpur (12.0 MTPA)
Proposed Capacity:12.0 MTPA in three
phases.
Total land required – 4004 acres. 628 acres
of non forest Govt. land was leased to the company.
Environment clearance and CRZ clearance for
construction of port issued by MoEF.
Proposed project cost – Rs.51,000 crores
approx.
Government of Orissa PL for 2500 Ha in Khandadhar
in favour of the company. Matter
Sub-judice in Supreme Court in respect
of Khandadhar iron ore mines.
On 29.12.2009, Ministry of Environment
& Forests, accorded final (Stage-II) approval, for diversion of the forest
land. Forest Clearance (Stage II) kept
suspended since 06.08.2010.
Phase i: 3.0 MTPA will be commissioned 3
years after land possession.
13. Arcelor
Mittal India Orissa Greenfield plant at Keonjhar (12.0 MTPA)
Proposed Capacity: 12.0 MTPA
Total land required – 7700 acres. Nil in possession
Proposed project cost - @$ 12,000/T
Thermal coal allocaton in Rampia & dip
side of Rampia block allocated.
Project implemented stage – 2016 (3 MTPA).
14. Arcelor
Mittal India Jharkhand Greenfield plant at Bokaro (12.0 MTPA)
Proposed Capacity:12.0 MTPA
Total land required – 3000 acres for phase
1 of 12 mtpa. Nil in possession
Proposed project cost - @$ 12,000/T
ML obtained for about 202 Ha in Karmapada.
Seregarha coal block allocated jointly with
GVI Industries in Jan.2008. PL order
issued by Govt. of Jharkhand inSept. 2010.
Project implemented stage – 2015 (3 MTPA)
15. Arcelor
Mittal India Karnataka Greenfield plant at Bellary (6.0 MTPA)
Proposed Capacity:6.0 MTPA
Total land required – 3500 acres. Land acquisition process is on.
cost - @$ 12,000/T
Govt. of Karnataka recommended ML for 211
Ha in Donimalai range on June, 15, 2010.
Project implemented stage – 2015 (3 MTPA).
16. Ispat
Industries Ltd, Jharkhand Greenfield project (2.8 MTPA)
Proposed capacity – 2.8 MTPA, which will be
expanded to 5 MTPA
Project cost – 10000.00 crores approx for
Phase 1.
Phase 1 will be commissioned within 36
months after receiving required supported like land, iron ore coal etc.
17. Ispat
Industries Ltd. Karnataka Greenfield project (2.8 MTPA)
Proposed capacity – 2.8 MTPA
Project cost – 10000.00 Crores approx for
Phase 1.
Phase 1 will be ommissioned within 36
months after receiving required supported like land, iron ore coal etc.
18. Monnet
Ispat & Energy Limited Orissa Greenfield plant at Angul (1.05 MTPA Stee
Plant)
Proposed Capacity:1.05 MTPA
Total land required – 202 acres. 110 acres
in possession
No forest land
Proposed project cost – Rs.281.09 crores.
0.25 MTPA will be commissioned by December
2011.
19. Monnet
Ispat & Energy Limited Jharkhand Greenfield plant at Bokaro (1.5 MTPA steel
plant)
Proposed Capacity: 1.5 MTPA
Total land required – 1000 acres. 15 acres
purchased in Kumhari VIII.
Proposed project cost – Rs.1400.00 crores.
1.5 MTPA will be commissioned by December
2013.
20. Electrosteel
Steel Limited Jharkhand Greenfield plant at Bokaro (2.2 MTPA)
Proposed Capacity:2.2MTPA
Purchased nearly 2000 acres of private land
Financial closure achieved.
Proposed project cost for phase I – Rs.7300.00
crores approx. Expenditure made till 31.10.2010 – Rs.5700.00 crores approx.
Phase I will be completed by end of 2011.
21. Visa
Steel Ltd. Orissa Greenfield plant at Jajpur (1.5MTPA)
Proposed Capacity:1.5 MTPA
1200 acres land requested, out of which
land allotted 525 acres, possessed 523 acres.
Balance 675 acres pending in IDCO.
Proposed project cost – Rs.4500 crores.
Environmental clearance for the upcoming
projects have been accorded by MoEF
22. Visa
Steel Ltd Chhattisgarh Greenfield plant at Raigarh (2.5 MTPA)
Proposed Capacity:2.5 MTPA
Approx 270 acres land is in possession
& further 750 acres land acquisition is under progress.
Environmental clearance for the upcoming
projects have been accorded by MoEF
Likely date of completion of current
capacity under execution – April 2013
********
NSK/PM