Number of Steel Plants in India

 

The Union Minister for Steel Shri Beni Prasad Verma has said that the list of major integrated steel plants both in public and private sector that are functioning in the various part of the country, State/UTs-wise is given below:

 

                                                                                                 (Crude Steel Capacity in million tonnes)

 

S.No.

Company

Location

State

Current approximate Capacity*

1

Steel Authority of India Limited

IISCO, Burnpur

West Bengal

0.50

2.

Steel Authority of India Limited

Bokaro

Jharkhand

4.36

3

Steel Authority of India Limited

Bhilai

Chhattisgarh

3.93

4

Steel Authority of India Limited

Rourkela

Orissa

1.90

5

Steel Authority of India Limited

Durgapur

West Bengal

1.80

6

Rashtriya Ispat Nigam Limited

Visakhapatanam

Andhra Aradesh

2.90

7

Tata Steel Limited

Jamshedpur

Jharkhand

6.8

8

Essar Steel Limited

Hazira

Gujarat

4.6

9

JSW Steel Limited

Vijayanagar

Karnataka

6.6

10.

Jindal Steel & Power Limited

Raigarh

Chhattisgarh

2.4

11

Ispat Industries Limited

Dolvi

Maharastra

3.0

12

Bhushan Power & Steel Limited

Jharsugda

Orissa

1.2

13

Bhushan Steel Limited

Angul-Dhenkanal

Orissa

1.5

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

As per the latest information available in the Ministry of Steel.

 

In a written reply in the Rajya Sabha today. he said that in addition, there are several medium and small steel units in the country including Mini Blast Furnace, Sponge Iron Units, Induction Furnace Units and Rolling Mills.  The total number of such units is approximately 3647, as per the last survey conducted by Joint Plant Committee in 2009-10.  Steel is a deregulated sector and Ministry of Steel maintains record of public sector steel units and private sector integrated steel units having capacity 1 million tonne or higher.

 

The Minister informed that  the detailed status of major new steel plants likely to come up by end of the next five year plan period, as furnished by the concerned companies are Annexed.

 

He said that steel being a deregulated sector, the detailed strategy regarding physical and financial matters of the private sector projects are decided by the individual investors themselves.  Ministry of Steel facilitates the implementation of the major private sector projects through coordination with concerned Ministries and State Governments. 

 

An Inter-Ministerial Group (IMG) has been set up in the Ministry which is vested with the job of monitoring and coordinating on the issues concerning major steel investments, he added. 

 

 

ANNEXURE

 

1.         NMDC Ltd. Chhattisgarh Greenfield project at Bastar (3 MTPA)

Proposed capacity:3.0 MTPA

Total land requirement – 1934 acres. 1783 acres already in possession.  Balance land is under process of allotment.

Total expenditure to be made-Rs.15525 crores.

Stage 1 clearance for diversion of 63.56 acres forest land has been received.

MoU signed between NMDC and CMDC Ltd. for allocation, development, production and marketing of iron ore of Bailadila Deposit No.4 for meeting the requirement of steel plant.

Date of completion – 42 months from”Zero date” i.e. receipt of all statutory clearance/approvals and placement of orders for major technological packages.

 

2.         Tata Steel Ltd. Orissa Greenfield project at Kalingnagar (6 MTPA)

 

Proposed capacity:6.0 MTPA (Phase I -  3.0 MTPA, PhaseII – 6.0 MTPA)

3040 acres land is registered in the companies name.  Proposal submitted to IDCO for 580 acres of land for township and 226 acres for Rail Corridor.  Acquisition of land delayed due to law and order issues on land encroachment.  Partial land possession.

Total expenditure made – Rs.6500 crores.

Capacity of 6 mtpa likely to be achieved by FY’2014.

 

3.         Tata Steel Ltd. Chhattisgarh Greenfield plant at Bastar (5.5 MTPA)

 

Proposed capacity :5.5 MTPA

PL granted for Bailadila Deposit – 1. Law suits filed by NMDC and pending in court.

Land acquisition is in progress and 70% of PAP has taken compensation/

Total expenditure made – Rs.129 crores.

DPR completed.

Capacity of 5.5 mtpa likely to be achieved by FY’2015.

 

4.         Tata Steel Ltd., Jharkhand Greenfield plant at Seraikela (12 MTPA)

 

Proposed capacity:12.0 MTPA

Notification was awaited for private land.  Government of Jharkhand asking the company to acquire Private Land directly.

Total expenditure made – Rs.25.5 crores.

DPR completed.

Capacity of 12.0 mtpa likely to be achieved by FY’2016.

 

5.         Essar Steel Orissa Ltd. Orissa Greenfield plant at Paradeep (6.0MTPA)

 

Proposed Capacity:6.0 MTPA

Total land required for the project is 2649 acres in Paradeep and Dabuna.

For ISP – Out of 1822 acres, 456 acres of private land has been acquired and 812 acres of private land is under acquisition.

Proposed project cost – Rs.22,600 crores.

Project implemented time – 36 months from the date of land acquisition.

Essar Steel Chhattisgarh Ltd. Chhattisgarh Greenfield plant at Bastar (3.2 MTPA)

 

Proposed Capacity:3.2 MTPA

The company has applied for 608.33 Ha (Private land – 393.21 Ha & Government land – 215.15 Ha) of land.  Award under section 11 for the private land has been passed by the Authorities.

Proposed project cost – Rs.11,000 crores.

Project implemented time – 36 months from financial closure.

 

Essar Steel Jharkhand Ltd Jharkhand Greenfield plant at Chaibasa (3.0 MTPA)

 

Proposed Cpacity:3.0MTPA

Total land required 2459 acres (GM Land – 338.26 acres & Raiyati land 2120.65 acres) approx.  Due to resistance from villagers in and around the proposed site, alternate sites have been identified and are being evaluated.

Proposed project cost – Rs.23,000 crores.

Project implemented state – 36 months from financial closure.

 

Essar Steel Karnataka Ltd., Karnataka Greenfield plant at Bellary (6.0 MTPA)

 

Proposed Capacity: 6.0 MTPA

Total land required 2800 acres.  Site survey has been done.

Proposed project cost – Rs.23,050 crores.

Project implemented stage – Phase 1 of 3 mtpa in about 36 months after completion of all preliminary work and development of land.

 

Jindal Steel & Power Ltd. Orissa Greenfield plant at Angul (6.0MTPA)

 

Proposed Capacity:6.0 MTPA

Total land required 4332 acres.  3882 acres of land is in possession.

Environment clearance and its amendment for revised configuration received from MoEF.

Stage II clearance received for 416 acres of forest land.

Proposed project cost – Rs.23,000 crores (Steel and captive power plant).

Environmental clearance for 5.5 mtpa coal mines obtained from MoEF.

Utkal B1 coal block in Talcher coal field area has been allotted for captive use.

Project implemented stage – 2mtpa steel making and 1.5 mtpa plate mill will be commissioned by December 2011.

 

Jindal Steel & Power Ltd. Jharkhand Greenfield plantat Patratu (6.0 MTPA)

 

Proposed Capacity:6.0MTPA

Total land requirement for 3 mtpa – 1715 acres; Purchased/applied to Govt. with seller’s consent – 1463 acres.

No forest land involved for 3 mtpa project under execution.

Proposed project cost for 3 mtpa – Rs.12,500 crores, 22,000 crores for 6 MTPA.

Project implemented stage – completion of 3 mtpa (Phase 1) capacity will be 2013.

 

 

 

11.       Jindal Steel & Power Ltd. Jharkahdn Greenfield platn at Asanboni (5.0MTPA)

 

Proposed Capacity : 5.0 MTPA

Total land required 2895 acres.  Purchased – 285 acres.

Forest clearance for 89 acres applied and pending

Proposed project cost – Rs.20,000 crores.

Environmental clearance applied and pending.

Jitpur coal block for CPP allocated.

ML for Jeraldaburu iron ore mine having reserves of 70 million tonne granted.

Project implemented stage – First phase would be completed by 2015.

 

12.       Posco India Project Orissa Greenfield plant at Jagatsinghpur (12.0 MTPA)

 

Proposed Capacity:12.0 MTPA in three phases.

Total land required – 4004 acres. 628 acres of non forest Govt. land was leased to the company.

Environment clearance and CRZ clearance for construction of port issued by MoEF.

Proposed project cost – Rs.51,000 crores approx.

Government of Orissa PL for 2500 Ha in Khandadhar in favour of the company.  Matter Sub-judice in Supreme  Court in respect of Khandadhar iron ore mines.

On 29.12.2009, Ministry of Environment & Forests, accorded final (Stage-II) approval, for diversion of the forest land.  Forest Clearance (Stage II) kept suspended since 06.08.2010.

Phase i: 3.0 MTPA will be commissioned 3 years after land possession.

 

13.       Arcelor Mittal India Orissa Greenfield plant at Keonjhar (12.0 MTPA)

 

Proposed Capacity: 12.0 MTPA

Total land required – 7700 acres.  Nil in possession

Proposed project cost - @$ 12,000/T

Thermal coal allocaton in Rampia & dip side of Rampia block allocated.

Project implemented stage – 2016 (3 MTPA).

 

14.       Arcelor Mittal India Jharkhand Greenfield plant at Bokaro (12.0 MTPA)

 

Proposed Capacity:12.0 MTPA

Total land required – 3000 acres for phase 1 of 12 mtpa.  Nil in possession

Proposed project cost - @$ 12,000/T

ML obtained for about 202 Ha in Karmapada.

Seregarha coal block allocated jointly with GVI Industries in Jan.2008.  PL order issued by Govt. of Jharkhand inSept. 2010.

Project implemented stage – 2015 (3 MTPA)

 

 

 

15.       Arcelor Mittal India Karnataka Greenfield plant at Bellary (6.0 MTPA)

 

Proposed Capacity:6.0 MTPA

Total land required – 3500 acres.  Land acquisition process is on.

cost - @$ 12,000/T

Govt. of Karnataka recommended ML for 211 Ha in Donimalai range on June, 15, 2010.

Project implemented stage – 2015 (3 MTPA).

 

16.       Ispat Industries Ltd, Jharkhand Greenfield project (2.8 MTPA)

 

Proposed capacity – 2.8 MTPA, which will be expanded to 5 MTPA

 Project cost – 10000.00 crores approx for Phase 1.

Phase 1 will be commissioned within 36 months after receiving required supported like land, iron ore coal etc.

 

17.       Ispat Industries Ltd. Karnataka Greenfield project (2.8 MTPA)

 

Proposed capacity – 2.8 MTPA

Project cost – 10000.00 Crores approx for Phase 1.

Phase 1 will be ommissioned within 36 months after receiving required supported like land, iron ore coal etc.

 

18.       Monnet Ispat & Energy Limited Orissa Greenfield plant at Angul (1.05 MTPA Stee Plant)

 

Proposed Capacity:1.05 MTPA

Total land required – 202 acres. 110 acres in possession

No forest land

Proposed project cost – Rs.281.09 crores.

0.25 MTPA will be commissioned by December 2011.

 

19.       Monnet Ispat & Energy Limited Jharkhand Greenfield plant at Bokaro (1.5 MTPA steel plant)

 

Proposed Capacity: 1.5 MTPA

Total land required – 1000 acres. 15 acres purchased in Kumhari VIII.

Proposed project cost – Rs.1400.00 crores.

1.5 MTPA will be commissioned by December 2013.

 

20.       Electrosteel Steel Limited Jharkhand Greenfield plant at Bokaro (2.2 MTPA)

 

Proposed Capacity:2.2MTPA

Purchased nearly 2000 acres of private land

Financial closure achieved.

Proposed project cost for phase I – Rs.7300.00 crores approx. Expenditure made till 31.10.2010 – Rs.5700.00 crores approx.

Phase I will be completed by end of 2011.

 

21.       Visa Steel Ltd. Orissa Greenfield plant at Jajpur (1.5MTPA)

 

Proposed Capacity:1.5 MTPA

1200 acres land requested, out of which land allotted 525 acres, possessed 523 acres.  Balance 675 acres pending in IDCO.

Proposed project cost – Rs.4500 crores.

Environmental clearance for the upcoming projects have been accorded by MoEF

 

22.       Visa Steel Ltd Chhattisgarh Greenfield plant at Raigarh (2.5 MTPA)

 

Proposed Capacity:2.5 MTPA

Approx 270 acres land is in possession & further 750 acres land acquisition is under progress.

Environmental clearance for the upcoming projects have been accorded by MoEF

Likely date of completion of current capacity under execution – April 2013

 

********